Question

In the CMAR method of project delivery, the CM advises the design team with respect to the constructability of design decisio

0 0
Add a comment Improve this question Transcribed image text
Answer #1

2nd Option is correct because CM means Construction Manager advises the owner in the selection of architect and design team member and advised the design team to the construction design and cost implementation and minimize the risk in the construction.

Add a comment
Know the answer?
Add Answer to:
In the CMAR method of project delivery, the CM advises the design team with respect to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 4. The Owner's ability to influence design and cost is highest at the construction phase. a....

    4. The Owner's ability to influence design and cost is highest at the construction phase. a. True b. False 5. The conceptual estimate is useful in the schematic design phase when design details are not available. a. True b. False 6. A Cost-Plus contract is considered a reimbursable type of contract. c. True d. False 7. An advantage of a Lump Sum Contract is that the owner assumes the risk of construction cost. e. True f. False 8. A Design-Bid-Build...

  • Dr. Megowatts wishes to construct his new office building in the Design/Build method. He has hired...

    Dr. Megowatts wishes to construct his new office building in the Design/Build method. He has hired an architect and contractor who created a joint venture to design and build his new building. The architect has completed the drawingbs and issued them for bidding. The Contractor has bid out the project amongst the subcontractors, and the final bid came in at $130,000 over the budget the doctor delineated at the beginning of the project. Explain what happened and provide a solution...

  • Suppose your team are assigned with a project that requires a comprehensive design of a bioprocess...

    Suppose your team are assigned with a project that requires a comprehensive design of a bioprocess operation for production of a new bioproduct. Based on the guidelines below, prepare a PROPOSAL detailing the whole process. (A) Background i) Define ONE (1) bioproduct that your team is planning to produce. Examples: enzymes, organic acids, vaccines, antibiotics, biofuels etc. ii) Describe the importance of the bioproduct of interest in the industrial applications. iii) Identify potential microorganisms that will produce the bioproduct of...

  • 7 In the work breakdown structure for a construction project: A. The different levels of detail...

    7 In the work breakdown structure for a construction project: A. The different levels of detail represents the logical hierarchical decomposition of the B. The smallest element in the WBS is the activity C. The project elements at various levels of the WBS relate to the contractor's project organizational structure, which defines the different responsibility levels D. All the above Negotiated cost-plus type of contracts is best used when: A. The risk is high B. No variations are expected C....

  • 1 According to the project plan, a contractor is scheduled to deliver some software components today...

    1 According to the project plan, a contractor is scheduled to deliver some software components today afternoon. A regular payment is due to be made to this contractor tomorrow. You and your project team received a note this morning informing you that the software delivery will be delayed by 2 weeks. What should you do right now? a You should delay the payment for two weeks b You must immediately find a different contractor c You should conduct a meeting...

  • Please help writing a well structured document using the below Agile Runbook - Our Overall Delivery Process How do we initiate a Project? Any project is a response to a pain point or desire expresse...

    Please help writing a well structured document using the below Agile Runbook - Our Overall Delivery Process How do we initiate a Project? Any project is a response to a pain point or desire expressed by either customers, internal stakeholders, employees, or regulatory authorities. In short, a project is a time bound and specific goal oriented task-system that is born out of an ask from any stakeholder. Project initiation is laying down a new project by defining its goals, objectives,...

  • Match the type of schedule listed with the description following. Schedule types may be used more than once a. Activity on arrow (AOA) b. Activity on node (AON) C. Matrix d. Bar chart 40 Grap...

    Match the type of schedule listed with the description following. Schedule types may be used more than once a. Activity on arrow (AOA) b. Activity on node (AON) C. Matrix d. Bar chart 40 Graphically the simplest Graphic style makes it adaptable to high-rise construction 42.Utilizes i-j notation 43 Could also be termed precedent notation Would be used for a summary report to the owner Questions 45-49 Match the terms listed with their description. Terms may be used only once...

  • !!!Only Project 2 need to be answered!!! Project Report 1 Once the business case has been approved, you need to make a...

    !!!Only Project 2 need to be answered!!! Project Report 1 Once the business case has been approved, you need to make a project plan showing each task. Assume you are a project manager to lead your team to acquire an additional delivery van for the company. Please find the details below. The current month is January. Activity (What is to be done?) Objective (Why will we do it?) Resources (Where will it be done?) Procedures (How will it be done?)...

  • Case Study 12: Hong Kong Police’s Project Management B Chuah Background In the 1990’s, Hong Kong...

    Case Study 12: Hong Kong Police’s Project Management B Chuah Background In the 1990’s, Hong Kong Police (HKP) was responsible for the public safety and internal security of Hong Kong. She came under the umbrella of the Security Bureau of the Government of Hong Kong. It had more than 34,000 employees, of these, over 26,000 were disciplinary staff. This was the largest department within the hierarchy of the Government of Hong Kong. The organization structure of HKP was rather complicated....

  • •Please help develop an overall delivery Process using the below to be in line with Agile project...

    •Please help develop an overall delivery Process using the below to be in line with Agile project management Project Management Office The Project Management Office (PMO) is an effective means for centralising all Project initiatives. It is the discipline of planning, organising and managing resources to bring about the successful completion of specific project goals and objectives. The key objective of PMO is to ensure all projects are executed on track, on schedule, within budget, and in adherence to business...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT