Relative Density of is comparison of the porosity or void ratio of the given soil with that of the same soil in its loosest and densest possible state and hence the term, relative density is introduced.
Relative Density = (e - e)/(e - e)
Determination of Relative Density:
Apparatus Required for determination of Relative Density are as follows:
1) Relative Density Apparatus
2) Mixing Pan (Suitable size are 60 x 90 cm and 10 cm deep and 40 x 40 cm and 5 cm deep)
3) Weighing Scale (100 kg capacity with sensitivity of 20 g)
Calibration of mould:
1. Measure inside diameter of mould at different depths using a bore gauge and take the average diameter.
2. Keep the mould on a flat surface or flat plate. Measure the height at different positions and take the average (accuracy = 0.025 mm).
3. Calculate the volume of the mould.
4. Fill the mould with distilled water till over flowing takes place.
5. Slid thick glass plate over the top surface of mould.
6. Weigh the water filled mould.
7. Note the temperature of water.
8. Obtain density of water for the above temperature from physical tables.
9. Calculate the volume of the mould which is weight of water filled mould /density of water.
Preparation of the Sample:
1. Dry the soil sample in a thermostatically controlled electric oven.
2. Cool in the sample in a desiccator.
3. Segregate soil lumps with out breaking individual particles
4. Sieve it through the required sieve size.
Minimum Density:
The mould is weighed accurately (W). Pour the dry pulverized soil into the mould through a funnel in a steady stream. The spout is adjusted so that the free fall of soil particle is always 25 mm. While pouring soil the spout must have a spiral motion from the rim to the centre. The process is continued to fill up the mould with soil upto about 25mm above the top. It is then leveled, with the soil and weight is recorded (W).
Let Volume of Mould = V cc.
Mass of Dry Soil, M = (W - W) gm.
Now, () = M/V gm/cc
e = G./()-1
Maximum Density:
Weigh the empty mould (W). Put the collar on top of the mould and clamp it. Fill the mould with the oven dried soil sample till 1/2 or 2/3 of the collar is filled. Place the mould on the vibrating deck and fix it with nuts and bolts. Then place the surcharge weight on it. The vibrator is allowed to run for 8 minutes. Then mould is weighed with the soil and weight is recorded (W2).
Let Volume of Mould = V cc.
Mass of Dry Soil, M = (W - W) gm.
Now, () = M/V gm/cc
e = G./()-1
Natural Density:
Weigh the mould with dry soil. Knowing the volume of the mould and weight of dry soil natural density, , can be calculated.
e = G./()-1
Relative Density = (e - e)/(e - e)
foundation design - Soil investigations in the past have shown that the soil at the site...
(22 marks) piles are to be constructed in a site with soil the ground surface) 2 m layer of new ilt, followed by 12 m layer of soft clay,f deep layer of dense the major sand. The Gwr is 0.5m below the ground surface geotechnical considerations for the piles (6 marks) (22 marks) piles are to be constructed in a site with soil the ground surface) 2 m layer of new ilt, followed by 12 m layer of soft clay,f...
Problem 7 The soil profile at a site consists of a top 4 m layer of dense sand followed by 2 m of clay, which is underlain by a stiff stratum. The water table is at 2 m below the ground level. The following data was obtained from a consolidation test on an undisturbed sample obtained from the middle of the clay layer: water content 5 36%, specific gravity of the clay grains = 2.72, compression index = 0.72, recompression...
[Problems 1-4] The soil profile at a site for a proposed office building consists of a layer of fine sand 10.4 m thick above a layer of soft, normally consolidated clay 2 m thick. Below the soft clay is a deposit of coarse sand. The groundwater table was observed at 3 m below ground level. The void ratio of the sand is 0.76, and the water content of the clay is 43%. The building will impose a vertical stress increase...
mblem No. 3 ( 30%) A steel eil tank with flexible foundation, 50m diameter and 12m height has oil y-9.42 kN The foundation soil is 3.3m of sand Ф.35° and Y-18.85 kNm' overlaying a layer of uniform. armally consolidated clay of 17tn thick with Ф-10° and Y-17.3 kN/m.c_ 12 kNtn.c -127 and C-04 underlain by another layer of sand. The water table is at the surface level. Oedometer test on a 2.54cm thick, doubly-drained sample from the clay stratum attained...
Homework #10 A soil exploration result of a site is shown in the following figure. A building is to be constructed at that site. First, it has been proposed to raise the elevation of the ground by filling the site with 10 ft thick compacted soil at an area of 25 ft x 25 ft. The unit weight of the compacted moist soil was 120 pcf. The foundation of proposed building was constructed at the center of the compaction area...
Figure P3 shows the soil profile at a site for a proposed office building. It is expected that the vertical stress at the top of the clay will increase by 150 kPa and at the bottom by 90 kPa. Assurning a linear stress distribution within the clay: (a) Calculate the consolidation settlement. You should divide the clay into five layers, compute the settlement for each layer, and then find the total settlement. Assume G = 2.7 for both sand and...
geotechnical engineering The soil profile at a site consists of a clay layer 10 m thick, sandwich between two sand layers. The top sand layer has a density of 1.9 Mg/m² and is 5 m thick. Below this layer is a 10 m thick clay layer with a saturated density of 1.8 Mg/m' and a saturated water content 42%. The deeper sand layer has a saturated density of 1.9 Mg/m² and extend to the depth investigated at the site. The...
A 5m wide and 10m long rectangular foundation is built on a site where the soil profile consists of 3m of gravel and 4m of clay overlying rigid impermeable rock as shown in Fiqure 8. The foundation carries a surcharge loading of q-65 kN/m2 Initially the water table is 1 m below the surface of the gravel. The water table rises to the surface of the gravel slowly over a period of time and the surface loading induces an increase...
A geotechnical engineer has to decide between two foundation designs at a site which is believed to contain a lens of soft clay, whose size can be discretized into large, medium or small. Design A assumes a large lens of soft clay, while design B assumes the size of soft clay lens, if any, is insignificant The expected cost-which includes initial and expected failure costs-for each design and lens size combination is given below (in million dollars): Size of Soft...
A 5m wide and 10m long rectangular foundation is built on a site where the soil profile consists of 3m of gravel and 4m of clay overlying rigid impermeable rock as shown in Figure 8. The foundation carries a surcharge loading of q=65 kN/m2 Initially the water table is 1 m below the surface of the gravel. The water table rises to the surface of the gravel slowly over a period of time and the surface loading induces an increase...