Question
Suppose your firm would like to earn 10% yearly return from the following two investment projects of equal risk.(the table is attatched in the form of image)

(a)​If only one project can be accepted, based on the NPV method which one should it be? Support your answer with calculations. ​​​​​​(9 marks)
(b)​Suppose there is another four-year project (Project C) and its cash flows are as follows:
C0 = –$8,000
​C1 = $2,000
​C2 = $2,500
​C3 = $2,000
​C4 = $4,000
(i)​Given the above cash flow patterns, at what required rate of return will Project C have the same NPV as Project B? Briefly explain your answer.​​​(2 marks)
(ii)​If Project C has the same risk as Project B, without calculations, explain which project will you pick? ​​​​​​​​​(2 marks)
(iii)​If cash flow C4 of Project C is unknown to you (while C0 – C3 are known and as above) and the project’s cost of capital is 10%, what amount of C4 will make Project C worth accepting?​​​​​​​​​(4 marks)
(iv)​If your firm’s investment policy (based on payback method) is such that it only accepts projects whose initial investment can be recouped within three years, will Project B and/or Project C be accepted?​​​​​​​(2 marks)
(c)​Based on the estimated cash flows of Project A, will you expect its internal rate of return (IRR) to be positive? Briefly explain your answer WITHOUT calculations. ​(4 marks)
(d)​What kind of rate of return is the 10% interest stated in the question for Projects A and B? How can it be used in making investment decisions (i.e. its role in investment decision making)?​​​​​​​​​​(2 marks)

Please provide steppings for all if possible, much appreciated.

Question 4 (25 marks/Investment Decision Rules). Suppose your firm would like to earn 10% yearly return from the following tw
0 0
Add a comment Improve this question Transcribed image text
Answer #1

A) Statement showing NPV

Project A Project B
Year Cash Flow PVIF @ 10% PV Cash Flow PVIF @ 10% PV
0 -8000 1.0000 -8000 -8000 1.0000 -8000
1 2000 0.9091 1818 4000 0.9091 3636
2 3000 0.8264 2479 2000 0.8264 1653
3 5000 0.7513 3757 2500 0.7513 1878
4 1000 0.6830 683 2000 0.6830 1366
NPV(Sum of PV) 737 534

Thus Project A should be selected

B)

i) Let us assume rate to be 8%

Statement showing NPV of project C

Project C
Year Cash Flow PVIF @ 8% PV
0 -8000 1.0000 -8000
1 2000 0.9259 1852
2 2500 0.8573 2143
3 2000 0.7938 1588
4 4000 0.7350 2940
NPV(Sum of PV) 523

Now, Let us assume rate to be 7%

Project C
Year Cash Flow PVIF @ 7% PV
0 -8000 1.0000 -8000
1 2000 0.9346 1869
2 2500 0.8734 2184
3 2000 0.8163 1633
4 4000 0.7629 3052
NPV(Sum of PV) 737

Now using interpolation method we can find rate

Rate NPV
8% 523
7% 737
1% down 214
? 11

1*11/214

=0.0514

Thus rate = 8%- 0.0514%

=7.9485%

II) Project C, Since its has low cost of capital

III) Assuming Cash flow for Year 4 = 3826$

Project C
Year Cash Flow PVIF @ 10% PV
0 -8000 1.0000 -8000
1 2000 0.9091 1818
2 2500 0.8264 2066
3 2000 0.7513 1503
4 3826 0.6830 2613
NPV(Sum of PV) 0

Thus cash flow above 3826$ is required

iv) Project B as sum of it's 3 year cash flow is 8500$ ( 4000+2000+2500)

C) Yes, IRR will be positive for project A , since there are conventional cash flows i.e No negative cash flow after initial period

D) 10% Rate used can be called minimum required rate of return. i.e if one wants to start project , he/she will have to raise funds. the cost of funds suppose is 10%, thus they want project which have atlease 10% return so that they can break even.

Add a comment
Know the answer?
Add Answer to:
Suppose your firm would like to earn 10% yearly return from the following two investment projects...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 18. Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...

    18. Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 9 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -21,000 11,000 31,000 2,000   Project B Cash Flow -31,000 11,000 21,000 51,000 Use the NPV decision rule to evaluate...

  • Your firm has identified three potential investment projects. The projects and their cash flows are shown...

    Your firm has identified three potential investment projects. The projects and their cash flows are shown below: Project    Cash Flow Today (millions) Cash Flow in One Year (millions) A    -$7 $15 B $7 $4 C $19 -$6 Suppose all cash flows are certain and the risk-free interest rate is 9%. (a) The NPV of Project A is $Answermillion. (Round to two decimal places.) (b) The NPV of Project B is $Answermillion. (Round to two decimal places.) (c) The...

  • Your firm has identified three potential investment projects. The projects and their cash flows are shown​...

    Your firm has identified three potential investment projects. The projects and their cash flows are shown​ here:  ​(Click on the icon located on the​ top-right corner of the data table below in order to copy its contents into a​ spreadsheet.) Project Cash Flow Today ​(millions) Cash Flow in One Year ​(millions) A -$15 $$16 B $4 $3 C $17 −$11 Suppose all cash flows are certain and the​ risk-free interest rate is 6%. a. What is the NPV of each​...

  • Calculate the NPV 8. Suppose your firm is considering two mutually exclusive, required projects with the...

    Calculate the NPV 8. Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 10 percent. and the maximum allowable payback and discounted payback statistic for the projects are two and a half and three and a half years, respective Project A Cash Hlow -1.000 Projcet B Cash Flow -500 200 Use the paybacced si ure to evaluate these...

  • Your firm has identified three potential investment projects. The projects and their cash flows are shown...

    Your firm has identified three potential investment projects. The projects and their cash flows are shown here: Cash Flow Today (millions) $7 $7 $18 Cash Flow in One Year (millions) $23 $3 -$8 Project Suppose all cash flows are certain and the risk-free interest rate is 11%. a. What is the NPV of each project? b. If the firm can choose only one of these projects, which should it choose? c. If the firm can choose any two of these...

  • Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....

    Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. Time: 0123 Project -35,000 25,000 45,000 16,000 A Cash Flow Project -45,000 25,000 35,000 B Cash Flow Use the NPV decision rule to evaluate these projects; which one(s) should...

  • 11.07 CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this...

    11.07 CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows:    0 1 2 3 4 5 Project M -$6,000 $2,000 $2,000 $2,000 $2,000 $2,000 Project N -$18,000 $5,600 $5,600 $5,600 $5,600 $5,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers...

  • Suppose your firm is considering Investing in a project with the cash flows shown below, that...

    Suppose your firm is considering Investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 11 percent, and that the maximum allowable payback and discounted payback statistics for your company are 3 and 3.5 years, respectively. Time: Cash flow: $235,000 $65,00 33,000 $1,000 $122,000 $1,200 Use the NPV decision rule to evaluate this project. (Do not round intermediate calculations and round your final answer to 2 decimal...

  • U2 - 6 ?(Round to two decimal? places.) Your firm has identified three potential investment projects....

    U2 - 6 ?(Round to two decimal? places.) Your firm has identified three potential investment projects. The projects and their cash flows are shown here: Cash Flow Today (millions) -$14 $4 S22 Cash Flow in One Year (millions) 523 $4 - $7 Project Suppose all cash flows are certain and the risk-free interest rate is 9% a. What is the NPV of each project? b. If the firm can choose only one of these projects, which should it choose? c....

  • Suppose your firm is considering investing in a project with the cash flows shown below, that...

    Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 9 percent, and that the maximum allowable payback and discounted payback statistics for the project are 2.0 and 3.0 years, respectively. Time: Cash flow: -$7,000 $1,130 $2,330 $1,530 $1,530 $1,330 $1,130 Use the NPV decision rule to evaluate this project. (Do not round intermediate calculations and round your final answer to 2...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT