Question
Need optimal solution for x,y, and value Z
The Attaran Corporation manufactures two electrical products: portable air conditioners and portable heaters. The assembly pr
0 0
Add a comment Improve this question Transcribed image text
Answer #1

From the given data, the LP model becomes:- • The aim is to maximize objective value That is profet → Max 2= 25x+BY where X:

Add a comment
Know the answer?
Add Answer to:
Need optimal solution for x,y, and value Z The Attaran Corporation manufactures two electrical products: portable...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Operations Management

    can someone help me to solved this problems ? the instruction is formulate mathematical model with using excel solver.objective functionconstrainsQuestionThe Attaran Corporation manufactures two electrical products: portable air conditioners and portable heaters. The assembly process for each is similar in that both require a certain amount of wiring and drilling. Each air conditioner takes 3 hours of wiring and 2 hours of drilling. Each heater must go through 2 hours of wiring and 1 hour of drilling. During the next production...

  • PLEASE SHOW HOW TO GRAPH ON EXCEL. I DONT KNOW HOW TO GRAPH IT. please also...

    PLEASE SHOW HOW TO GRAPH ON EXCEL. I DONT KNOW HOW TO GRAPH IT. please also solve as instructed in problem • B.5 The Attaran Corporation manufactures two electrical products: portable air conditioners and portable heaters. The assembly process for each is similar in that both require a certain amount of wiring and drilling. Each air conditioner takes 3 hours of wiring and 2 hours of drilling. Each heater must go through 2 hours of wiring and 1 hour of...

  • Exercise 1. Found 1 JU m b y P The Electrocomp Corporation manufactures two electrical products:...

    Exercise 1. Found 1 JU m b y P The Electrocomp Corporation manufactures two electrical products: air conditioners and large fans. The assembly process for each is similar in that both require a certain amount of wiring and drilling. Each air conditioner takes 3 hours of wiring and 2 hours of drilling. Each fan must go through 2 hours of wiring and 1 hour of drilling. During the next production period, 240 hours of wiring time are available and up...

  • .EI ot slimie Final Operations Management Similar to 7-14:0 The Electrocomp Corporation manufactures two electrical products:...

    .EI ot slimie Final Operations Management Similar to 7-14:0 The Electrocomp Corporation manufactures two electrical products: air conditioners and large fans. The assembly process for each is similar in that both require a certain amount of wiring and driling. Each air conditioner takes 6 hours of wiring and 2 hours of drilling Each fan must go through 2 hours of wiring and 1 hours of drilling, During the next production period, 240 hours of wiring time are available and up...

  • Similar to 7-14 Electrocomp Corporation manufactures two electrical product ir tu The assembly process for each...

    Similar to 7-14 Electrocomp Corporation manufactures two electrical product ir tu The assembly process for each is similar in that both require a certain amount of wiring fans. and drilling Each air conditioner takes 6 hours of wiring and 2 hours of drilling. Each fan must so through 2 hours of wiring and 1 hours of drilling. During the next production period, 240 hours of wiring time are available and up to 100 hours of drilling time may be used....

  • The Electrotech Corporation manufactures two industrial-sized electrical devices: generators and alternators. Both of these products require...

    The Electrotech Corporation manufactures two industrial-sized electrical devices: generators and alternators. Both of these products require wiring and testing during the assembly process. Each generator requires 2 hours of wiring and 1 hour of testing and can be sold for a $250 profit. Each alternator requires 3 hours of wiring and 2 hours of testing and can be sold for a $150 profit. There are 260 hours of wiring time and 140 hours of testing time available in the next...

  • The Electrotech Corporation manufactures two industrial-sized electrical devices: generators and alternators. Both products require wiring and...

    The Electrotech Corporation manufactures two industrial-sized electrical devices: generators and alternators. Both products require wiring and testing during the assembly process. Each generator requires 2 hours of wiring and 1 hour of testing and can be sold for a $250 profit. Each alternator requires 3 hours of wiring and 2 hours of testing and can be sold for a $150 profit. There are 260 hours of wiring time and 140 hours of testing time available in the next production period,...

  • A company manufactures four products (1,2,3,4) on two machines (X and Y). The time (in minutes)...

    A company manufactures four products (1,2,3,4) on two machines (X and Y). The time (in minutes) to process one unit of each product on each machine is shown below:, Product 1 in X = 10 min , in Y= 27 min Product 2 in X = 12 min , in Y =19 min Product 3 in X =13 min,in Y =33 min Product 4 in X = 8 min,in Y =23 min The profit per unit for each product (1,2,3,4)...

  • how to graph this? is this correct? The aim of the objective function for Par Inc., should be to Maximize the objective value Objective function Max Z = 5S + 8D Subject to: (1/2)S + 1D <= 300 (C1)...

    how to graph this? is this correct? The aim of the objective function for Par Inc., should be to Maximize the objective value Objective function Max Z = 5S + 8D Subject to: (1/2)S + 1D <= 300 (C1) 1S + (2/3)D <= 420 (C2) a) The optimum solution is S = 330 D =135 b) Optimal solution value 'z' = 2730 Par, Inc., produces a standard golf bag and a deluxe golf bag on a weekly basis. Each golf...

  • QUESTION TWO Nectar company produces 3 products, X, Y and Z, details of which are shown...

    QUESTION TWO Nectar company produces 3 products, X, Y and Z, details of which are shown below:             X                    Y                    Z Selling price per unit (ZMW)                     130                  120                 110                 Direct material cost per unit (ZMW)        85                    60                   70                   Maximum demand (units)                        40,000          30,000         25,000    Time required on the bottleneck               3                      5                     4                     resource (hours per unit) There are 320,000 bottleneck hours available each month. Required Calculate...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT