Question

Software Engineering Testing stage of a project cost $977000 and took 8 months to complete. Estimate...

Software Engineering

Testing stage of a project cost $977000 and took 8 months to complete. Estimate the overall project cost, the cost per year, its manpower, and the total number of LOC and the cost of each of the three remaining major effort allocations for the project. Assume the typical $k 100/year per average engineer. Check using COCOMO if these numbers are within reason.

Requirements is 24%

Design is 16%

Coding is 12%

Testing is 48%

0 0
Add a comment Improve this question Transcribed image text
Answer #1

`Hey,

Note: Brother if you have any queries related the answer please do comment. I would be very happy to resolve all your queries.

Since testing is the well known 48% of the total, then

Project Total Cost = 977000/0.48 = $ 2035416.67

Project Total Time = 8/0.48 = 16.67 months.

the rest of the money and time is divided as per those % we learned in class!

Lifecycle Stage %  Cost [$] Time [months]

Requirements  24  488500.0008  4.0008

Design   16  325666.6672  2.6672

Coding 12 244250.0004  2.0004

Testing  48 977,000 8.00

TOTALS           100 2035416.67   16.67

But this cost is the total for 16.67 months.

Cost Per Year = 2035416.67*(12/16.67) = $ 1465206.961008

We divide this amount by 3.0 to look at real salaries: 1465206.961008/3 = $ 488402.320336

and this looks like just 488402.320336/100,000 = 4.884023 reasonably well paid Engineers!!!

4.884023 engineers at 1000 LOC/month produce = 4,884 LOC/month

[5 pts] Total LOCs in 2 (12% of 16.67) months: 4,884*2= 9768 LOC = 9.768 KLOC.

COCOMO verification:

The project has 4.884023 persons for 16.67 months =81.416663 (pm)

E = a(9.77)b = 3.6(9.77)1.20 = 55.485

Then 55.485/81.416663 = 68.14%. For a 70% estimate we need 55.485/.7 = 79.264,

79.264/16.67 = 4.75 engineers instead of 4.44 … QUITE GOOD! Our engineers are making just a bit more than the 100K$

Kindly revert for any queries

Thanks.

Add a comment
Know the answer?
Add Answer to:
Software Engineering Testing stage of a project cost $977000 and took 8 months to complete. Estimate...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Q: Complete the following "Reason column" for your software engineering risk analysis project. Please Note that...

    Q: Complete the following "Reason column" for your software engineering risk analysis project. Please Note that there is a sample for filling the reason column please see it. Risk Probability Effects Reason Organizational financial problems force reductions in the project budget (7). Low Catastrophic It is impossible to recruit staff with the skills required for the project (3). High Catastrophic Key staff are ill at critical times in the project (4). Moderate Serious Faults in reusable software components have to...

  • Cost benefit analysis for the Long Engineering Company        The Long Engineering Company (LEC) has decided...

    Cost benefit analysis for the Long Engineering Company        The Long Engineering Company (LEC) has decided to install a network system to help their technical support engineers (five of them who earn an average of $100,000 each per year) to deliver better customer service including: mail out sales and other literature, answer phone calls for technical assistance and log and forward repair requests using an alpha-numeric paging system that will be part of the new network system. Currently all company...

  • Case Study 12: Hong Kong Police’s Project Management B Chuah Background In the 1990’s, Hong Kong...

    Case Study 12: Hong Kong Police’s Project Management B Chuah Background In the 1990’s, Hong Kong Police (HKP) was responsible for the public safety and internal security of Hong Kong. She came under the umbrella of the Security Bureau of the Government of Hong Kong. It had more than 34,000 employees, of these, over 26,000 were disciplinary staff. This was the largest department within the hierarchy of the Government of Hong Kong. The organization structure of HKP was rather complicated....

  • The ABC Software company has been in the market place for over 20 years. While some...

    The ABC Software company has been in the market place for over 20 years. While some of the development team members have changed over time, there was a firmly established culture using the Waterfall method. The typical process involved setting product requirements up front, some generated directly from customers and others determined by employees (developers and product managers, for example) who attempted to gauge the customer's needs indirectly. Once requirements were determined, specification documents would be written with varying details...

  • WhitePearl Berhad: Project Evaluation It has been three months since you took a position as an...

    WhitePearl Berhad: Project Evaluation It has been three months since you took a position as an assistant financial analyst at WhitePearl Berhad. Although your boss has been pleased with your work, he is still a bit hesitant about unleashing you without supervision. Your next assignment involves both the calculation of the cash flows associated with a new investment under consideration and the evaluation of several mutually exclusive projects. Given your lack of tenure at WhitePearl Berhad, you have been asked...

  • The purpose of this project is to give students more exposure to object oriented design and...

    The purpose of this project is to give students more exposure to object oriented design and programming using classes and polymorphism in a realistic application that involves arrays of objects and sorting arrays containing objects A large veterinarian services many pets and their owners. As new pets are added to the population of pets being serviced, their information is entered into a flat text file. Each month the vet requests and updates listing of all pets sorted by their "outstanding...

  • This is the question , honestly , you could skip the garbage at first and jump...

    This is the question , honestly , you could skip the garbage at first and jump to the Question section. below is my excel sheet , I need to do the 4 requirements under the Question section. to make your life easier you could copy the numbers from my sheet but i dont know how the function work exactly , as the professor is the one who sets it up. IEN 363 Spring 2019 Fnancial Analys1S Assignment ost benefit analysis...

  • In mid-2005 Gunawan Wiboto (Gunawan), an ethnic Chinese Indonesian entrepreneur and founder of the Ramayana Group,...

    In mid-2005 Gunawan Wiboto (Gunawan), an ethnic Chinese Indonesian entrepreneur and founder of the Ramayana Group, decided to build a steel mill incorporated as a new company: PT Hanuman Steel. His team began the search for an experienced engineering consultant for the project. The company approached several consulting firms reputed for their engineering services. The difficulty, as they quickly discovered, was finding a consultant who believed they could do it their way and be successful. The required services fell into...

  • Outsourcing Vendor, SaaS Client Optimizing the allocation of resources for IT services sometimes creates unexpected situations....

    Outsourcing Vendor, SaaS Client Optimizing the allocation of resources for IT services sometimes creates unexpected situations. This is a story of a leading vendor of IT outsourcing that decided to outsource one of its own IT functions. More accurately, it relies on software as a service. Siemens AG is a German-based global corporation and one of the world's largest firms. It specializes in electronics and engineering. It employs 475,000 people in 190 countries, and reported revenue of $107.4 billion in...

  • CASE STUDY 13.3 “Dear Mr. President—Please cancel our project!”: The Honolulu Elevated Rail Project Speaking on...

    CASE STUDY 13.3 “Dear Mr. President—Please cancel our project!”: The Honolulu Elevated Rail Project Speaking on the status of Honolulu’s Elevated Rail public transport system, former Hawaii Governor Benjamin Cayetano had an interesting message for President Trump: “As a lifelong Democrat and former governor of Hawaii, I opposed your candidacy. I must admit, however, that you are on the right track scrutinizing wasteful spending on pork barrel projects.” The admission by former governor Cayetano was prompted by the latest details...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT