The specifications for a plastic liner for a concrete highway project calls for thickness of 5.0mm...

The specifications for a plastic liner for a concrete highway project calls for thickness of 5.0mm +(with a minus sign or line under it) 0.12mm. The standard devaition of the process is estimated to be 0.02mm.

a. The upper specifcation limit for this product = (answer needed) mm (round to 3 decimal places)

b. The lower specification limit for this product = (answer needed) mm (round to 3 decimal places)

c. The process is known to operate at a mean thickness of 5.0mm. The process capability index (C (pk subscript)) =

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
The specifications for a plastic liner for a concrete highway project calls for thickness of 5.0mm...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • of the process is estimated to be 0.02 mm. The specifications for a plastic liner for...

    of the process is estimated to be 0.02 mm. The specifications for a plastic liner for a concrete highway project calls The upper specification limit for this product 5.1 mm (round your response to three decimal places. The lower specification limit for this product·4.9 mm (round your response to three decimal places) The process is known to operate at a mean thickness of 5.0 mm. The process capabilily index for thickness of 5.0 mm ± 0.10 mm. The standard deviation...

  • 4) The specification for a plastic liner for concrete highway projects calls for a thickness of...

    4) The specification for a plastic liner for concrete highway projects calls for a thickness of 6.0 mm 0.1 mm. The standard deviation of the process is estimated to be 0.02 mm. The process is known to operate at a mean thickness of 6.03 mm. Your manager has requested the process produce no more than 3.4 defects per 1 million produced. Calculate Cpk and then determine if the process is capable.

  • For a key joint, a precision machining process has a lower specification limit of a width...

    For a key joint, a precision machining process has a lower specification limit of a width of 0.99 mm and an upper specification limit of 1.01 mm. The standard deviation is 0.005 mm and the mean is 1 mm. (a) What is the process capability index for the bottle filling process? (Round the answer to 3 decimal places.) (b) The company now wants to reduce its defect probability and operate a “six sigma process.” To what level would they have...

  • Frank​ Pianki, the manager of an organic yogurt processing plant desires a quality specification with a...

    Frank​ Pianki, the manager of an organic yogurt processing plant desires a quality specification with a mean of 20.0 ounces, an upper specification limit of 20.5 ounces, and a lower specification limit of 19.5 ounces. The process has a mean of 20.0 ounces and a standard deviation of 1.25 ounce.   The process capability index (Upper C Subscript pkCpk​) ​= ? (round your response to three decimal​ places).

  • A company making tires for bikes is concerned about the exact width of their cyclocross tires....

    A company making tires for bikes is concerned about the exact width of their cyclocross tires. The company has a lower specification limit of 23 mm and an upper specification limit of 23.6 mm. The standard deviation is 0.2 mm and the mean is 23.3 mm Round your answer to 4 decimal places.) What is the process capability index for the process?

  • A company is making tires

    A company making tires for bikes is concerned about the exact width of its cyclocross tires. The company has a lower specification limit of 23.0 mm and an upper specification limit of 23.5 mm. The standard deviation is 0.17 mm and the mean is 23.2 mm.   What is the process capability index for the process.Round your answer to 4 decimal places. 

  • A company making tires for bikes is concerned about the exact width of their cyclocross tires....

    A company making tires for bikes is concerned about the exact width of their cyclocross tires. The company has a lower specification limit of 22.8 mm and an upper specification limit of 23.1 mm. The standard deviation is 0.19 mm and the mean is 22.95 mm. (Round your answer to 4 decimal places.) What is the process capability index for the process?

  • Frank Pianki, the manager of an organic yogurt processing plant desires a quality specification w...

    Frank Pianki, the manager of an organic yogurt processing plant desires a quality specification with a mean of 20.0 ounces, an upper specification limit of 20.5 ounces and a lower specification limit of 19.5 ounces. The process has a mean of 20.0 ounces and a standard deviation of 1.25 ounce The process capability index (Cpk)-「 (round your response to three decimal places) Frank Pianki, the manager of an organic yogurt processing plant desires a quality specification with a mean of...

  • Design specifications require that a key dimension on a product measure 101 ± 16 units. A...

    Design specifications require that a key dimension on a product measure 101 ± 16 units. A process being considered for producing this product has a standard deviation of five units. a. What can you say (quantitatively) regarding the process capability? Assume that the process is centered with respect to specifications. (Round your answer to 4 decimal places.) Process capability index  ???? b. Suppose the process average shifts to 96. Calculate the new process capability. (Round your answer to 4 decimal places.)...

  • The Money Pit Mortgage Company is interested in monitoring the performance of the mortgage process. Fifteen...

    The Money Pit Mortgage Company is interested in monitoring the performance of the mortgage process. Fifteen samples of five completed mortgage transactions each were taken during a period when the process was believed to be in control. The times to complete the transactions were measured. The Money Pit Mortgage Company made some changes to the process and undertook a process capability study. The following data were obtained for 15 samples of size 5. Based on the individual​ observations, management estimated...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT