Question

This Question: 2 pts 3 of9 (5 complete) This Quiz: 10 pts possible MIt ally exclus e projects and N V You have been assigned
PROJECT A CASH FLOW PROJECT B CASH FLOW $110,000 YEAR -$110,000 35,000 35,000 35,000 35,000 35,000 2 4 5 210,000
0 0
Add a comment Improve this question Transcribed image text
Answer #1

NPV of project A = $26,137.79

NPV of project B = $26,485.59

Choose B because its NPV is higher.

Project A Project B PV of cash PV of cash cash flow cash flow flows of A flows of B 0110000-110000-110000.00 -110000.00 Year
Project A cash flow Project BPV of cash cash flow 110000 PV of cash flows of Year flows of A 110000 35000 35000 35000 35000 3

Please do rate me and mention doubts, if any, in the comments section.

Add a comment
Know the answer?
Add Answer to:
This Question: 2 pts 3 of9 (5 complete) This Quiz: 10 pts possible MIt ally exclus...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Thomas Company is considering two mutually exclusive projects. The firm has a 12% cost of capital....

    Thomas Company is considering two mutually exclusive projects. The firm has a 12% cost of capital. Cash inflows Initial investment Year 1 Year 2 Year 3 Year 4 Year 5 Project A Project B $130000 $85000 $25000 $35000 $45000 $50000 $55000 $40000 $35000 $30000 $10000 $5000 Evaluate and discuss the rankings of NPV and IRR of the two projects on the basis of your finding. O A Project B should be chosen because it has a higher IRR than Project...

  • Question 6 5 pts (Numbers in parentheses are negative) These two projects are independent. Year Cash...

    Question 6 5 pts (Numbers in parentheses are negative) These two projects are independent. Year Cash Flow of A Cash Flow of B 0 ($5000) ($2000) 1 $1000 $1000 2 $2000 $1000 3 $2000 $2000 4. $2000 $1000 5 $1000 ($1000) What is the approximate crossover point between the two projects if the required rate of return is 9.5%? 12.39% O 7.24% There is no crossover point in this case. 0 7.57% O 6.12% Question 7 5 pts (Numbers in...

  • Consider the following projects, X and Y where the firm can only choose one. Project X...

    Consider the following projects, X and Y where the firm can only choose one. Project X costs $1300 and has cash flows of $477, $111, $452, $268, $526 in each of the next 5 years. Project Y also costs $1300, and generates cash flows of $496, $293, $468, $378 for the next 4 years, respectively. WACC=7%. A) Draw the timelines for both projects: X and Y. B) Calculate the projects’ NPVs, IRRs, payback periods. C) If the two projects are...

  • Case Study 3--Capital Budgeting (Comprehensive Spreadsheet Problem 11-23, page 408) Your division is considering two projects....

    Case Study 3--Capital Budgeting (Comprehensive Spreadsheet Problem 11-23, page 408) Your division is considering two projects. Its WACC is 10%, and the projects' after-tax cash flows (in millions of dollars) would be as follows: Expected Cash Flows Time Project A Project B 0 ($30) ($30) 1 $5 $20 2 $10 $10 3 $15 $8 4 $20 $6 a.   Calculate the projects' NPVs, IRRs, MIRRs, regular paybacks, and discounted paybacks. WACC = 10% Use Excel's NPV function as explained in NPVA...

  • C This Question: 1 pt 5 of 5 (0 complete) This Quiz: 5 pts possible Present...

    C This Question: 1 pt 5 of 5 (0 complete) This Quiz: 5 pts possible Present value of an annuity Consider the following case. (Click on the foon here in order to copy the contents of the data table below into a spreadsheet.) Amount of annuity $53.000 Interest rate 7% Period (years) 15 a. Calculate the present value of the annuity assuming that it is (1) An ordinary annuity (2) An annuity due b. Compare your findings in parts (1)...

  • Question 24 1 pts You are considering the following two mutually exclusive projects. Which project(s) should...

    Question 24 1 pts You are considering the following two mutually exclusive projects. Which project(s) should be recommended? Project A Project B Year Cash Flow Year Cash Flow 0 $75,000 0 -$70,000 1 $19,000 1 $10,000 2 $48,000 2 $16,000 3 $12,000 3 $72,000 Required rate of return: 10 percent (for A) 13 percent (for B) O accept project B and reject project A. accept both project A and project B. O reject both project A and project B. O...

  • . NEED ANSWER ASAP / ANSWER NEVER USED BEFORE a.) NPV A project has an initial...

    . NEED ANSWER ASAP / ANSWER NEVER USED BEFORE a.) NPV A project has an initial cost of $60,000, expected net cash inflows of $11,000 per year for 9 years, and a cost of capital of 10%. What is the project's NPV? (Hint: Begin by constructing a time line.) Do not round intermediate calculations. Round your answer to the nearest cent. $   b.) NPVs and IRRs for Mutually Exclusive Projects Davis Industries must choose between a gas-powered and an electric-powered...

  • Question 9 5 pts Use the following after-tax cash flows for project A and B to...

    Question 9 5 pts Use the following after-tax cash flows for project A and B to answer the following question: (Numbers in parentheses are negative cash flows). These two projects are independent Year Cash Flow of A Cash Flow of B 0 ($2,400) ($4,500) 1 $999 $800 2 $950 $950 3 ($150) $950 4 $910 $800 5 $990 $900 6 ($500) $1980 Which project should be taken if the required rate of return is 10%? o Take both projects o...

  • CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's...

    CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 5 Project M Project N - $30,000 $10,000 $10,000 $10,000 $10,000 $10,000 $90,000 $28,000 $28,000 $28,000 $28,000 $28,000 a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers...

  • 5) (15 pts total) Consider the cash flows and Project B Section 2 Problems sider the...

    5) (15 pts total) Consider the cash flows and Project B Section 2 Problems sider the cash flows from two mutually exclusive projects, Project A Year Cash Flow (Proj A) -200 20 120 160 Cash Flow (Proj B) -200 140 100 40 a) (5 pts) Construct NPV profiles for each project and graph them (one graph - both profiles). b) (5 pts) Compute the crossover rate e (5 pts) Briefly explain the conflict that arises between the NPV and the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT