Question

When you are calculating the percent complete for an entire project, more than one answer might...

When you are calculating the percent complete for an entire project, more than
one answer might be possible. The project manager says the percent complete is
about 60%, the cost engineer says it is 65%, the computer program says it is 57%,
and the owner says it should be 50% (according to her representative’s feedback).
You calculate it on the basis of how much time has elapsed and how much time
is given in the contract; your result is 70%. Can you explain these confusing and
“conflicting” numbers?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The conflict numbur because hauld ck nana uatch the actisted and dunation, Comhut puggram tells loccording it to less than th3. 3 142 8 bl iote 3. 091

Add a comment
Know the answer?
Add Answer to:
When you are calculating the percent complete for an entire project, more than one answer might...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Match the type of schedule listed with the description following. Schedule types may be used more than once a. Activity on arrow (AOA) b. Activity on node (AON) C. Matrix d. Bar chart 40 Grap...

    Match the type of schedule listed with the description following. Schedule types may be used more than once a. Activity on arrow (AOA) b. Activity on node (AON) C. Matrix d. Bar chart 40 Graphically the simplest Graphic style makes it adaptable to high-rise construction 42.Utilizes i-j notation 43 Could also be termed precedent notation Would be used for a summary report to the owner Questions 45-49 Match the terms listed with their description. Terms may be used only once...

  • Dear Sir/Madam, could you answer all the question below. I appreciate if u can answer all....

    Dear Sir/Madam, could you answer all the question below. I appreciate if u can answer all. Thank You :) A (Bad?) Day in the Life of a Project Manager Frank Mills is a Site Agent for McMurray Concrete Ltd which specialises in building concrete structures on industrial sites. His present site is a large chemical plant, Agrochem Ltd that manufactures farm fertilisers. The project he is currently working on is part of a large contract being managed by Design Solutions...

  • I have homework i was answered it .. but i need you to complete my answer...

    I have homework i was answered it .. but i need you to complete my answer to become 1000 words // i need 1000 words please use your own words, don't copy and paste, don't use handwriting, please. i need your references URL Link please** Book: Marketing Management ________________ Q: DEVELOP A CREATIVE BRIEF A creative brief is a structured document whose purpose is to communicate quickly and concisely to anyone who might be involved in the creation of promotional...

  • Please help writing a well structured document using the below Agile Runbook - Our Overall Delivery Process How do we initiate a Project? Any project is a response to a pain point or desire expresse...

    Please help writing a well structured document using the below Agile Runbook - Our Overall Delivery Process How do we initiate a Project? Any project is a response to a pain point or desire expressed by either customers, internal stakeholders, employees, or regulatory authorities. In short, a project is a time bound and specific goal oriented task-system that is born out of an ask from any stakeholder. Project initiation is laying down a new project by defining its goals, objectives,...

  • A project is meant to be a practical exercise that tests the knowledge and skills you...

    A project is meant to be a practical exercise that tests the knowledge and skills you have acquired from the book in a problem setting that resembles the real world more closely than a text book exercise. It is naturally more elaborate than any text book exercise and takes a little more time to do than a homework exercise. The recommended practice is to read and understand the description of the problem, and this may require reading the relevant sections...

  • Listed next are several terms. Complete the following statements with one of these terms. You may use a term more than​...

    Listed next are several terms. Complete the following statements with one of these terms. You may use a term more than​ once, and some terms may not be used at all. Master budget Participative budgeting Operating budgets Production budget Zero-based budgeting Strategic planning Financial budgets Slack Budget committees Rolling budget Safety stock Variance a. ▼ Budget committee Financial budgets Master budget Operating budgets Participative budgeting Production budget Rolling budget Safety stock Slack Strategic planning Variance Zero-based budgeting is a budget...

  • Read the attached article. Do you feel one style of banking control is more stable than...

    Read the attached article. Do you feel one style of banking control is more stable than the other? Why? Does one banking method minimize market volatility and risk better or is it just packaged differently? Do you feel the US (Western) Banking system can better control the patterns of behavior going forward that have caused economic damage in the past? Should the Fed continue its stimulus policy, reduce it or abandon it entirely (Google some recent articles to research this)?  (Please...

  • Please answer these questions! they all are linked to one another! thank you in advance! Bob...

    Please answer these questions! they all are linked to one another! thank you in advance! Bob Beamon's long jump at the 1968 Olympics was literally "like nothing seen before. As you will see in the upcoming video he broke the world record by 57 cm (we will probably be converting that to inches in the Exercise). He would have won the 2012 Olympics long jump by a 55 cm! Bob Beamon's historic leap. Chap 6 Quiz Q1 Homework Unanswered In...

  • Select two of the discussion questions and analyze the case study using project management principles. Apply...

    Select two of the discussion questions and analyze the case study using project management principles. Apply your knowledge of project management to the facts presented in the case study to describe how you would proceed. We only need to answer one of the questions. A thorough answer will probably require 300 to 500 words for each question.   Feel free to use text bullets, tables, or graphics to summarize your points. Questions Q1: Make or Buy decision – Describe the make...

  • RADICO’S CHALLENGE The executive staff at Radico Corporation was quite pleased with the one-day training program...

    RADICO’S CHALLENGE The executive staff at Radico Corporation was quite pleased with the one-day training program they attended on the benefits of using agile and Scrum on some of their projects. Radico provided products and services to both public and private sector clients, almost all of it through competitive bidding. IT was not required for any of the products and services Radico provided. Agile and Scrum had proven to be successful on internal IT projects, but there were some concerns...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT