Annual cost saving for the Purchase option ($) = 50,000 x (5.8 - 4.3) = 50,000 x 1.5 = 75,000
Maximum price ($) = PV of annual cost saving + PV of salvage value
= 75,000 x P/A(10%, 5) + 200,000 x P/F(10%, 5)
= 75,000 x 3.7908 + 200,000 x 0.6209
= 284,310 + 124,180
= 408,490
Question 1 A construction company signed a contract to build a highway. The duration of the...
A construction company signed a contract to build a highway. The duration of the project is five years. Based on project's schedule, the company will require 50,000 m² of aggregate each year. The aggregate can be obtained from a nearby query for $5.80 per m². However, the project manager is studying buying the query. If so, the cost of the aggregate would be only $4.30 per m3. Also, the manager thinks that the quarry can be sold at the end...
1) A highway construction company is under contract to build a new roadway through a scenic area and two rural towns in Colorado. The road is expected to cost $18,000,000, with annual upkeep estimated at S150,000 per year. Additional income from tourist (Benefits) of $900,000 per year is estimated. The road is expected to have a useful commercial life of 20 years. Determine if the highway should be constructed at a discount rate of 6% per year, applying the Conventional...
A highway construction company is under contract to build a new roadway through a scenic area and two rural towns in Colorado. The road is expected to cost $10,000,000, with annual upkeep estimated at $150,000 per year. Additional income from tourist (Benefits) of $900,000 per year is estimated. The road is expected to have a useful commercial life of 15 years. The discount rate to evaluate this project is 6% per year. Hint: Disbenefits = $0 and Annual Upkeep is...
General Construction Company General Construction Company has a contract to build three lower‐income apartment buildings for the city of Santa Fe, New Mexico. During construction of the first building, the Project Manager formed an auditing team to audit the construction process for each building. He asked the team to develop a list of minimum requirements for the projects and use this as a baseline in the audit. While reviewing the contract documents, one of the audit team members found a...
Construction company X signed a contract to build a hotel for Donald at the price of HKD 720 million. The cost of the construction at the time of signing the contract was expected to be HKD 900 million with 20% probability, HKD 800 million with 30% probability, HKD 600 million with 30% probability, and HKD 500 million with 20% probability. Donald values the hotel at HKD 850 million. How much should X pay to Donald in case of a breach...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2018, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2019, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2019 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,120,000 were incurred, with estimated costs of $4,120,000 yet to be incurred. Billings of $2,644,000 were sent, and cash collected was $2,370,000. In 2022, costs incurred were $2,644,000 with remaining costs estimated to be $3,780,000. 2022 billings were $2,894,000, and $2,595,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,150,000. During 2021, costs of $2,060,000 were incurred, with estimated costs of $4,060,000 yet to be incurred. Billings of $2,572,000 were sent, and cash collected was $2,310,000. In 2022, costs incurred were $2,572,000 with remaining costs estimated to be $3,690,000. 2022 billings were $2,822,000, and $2,535,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2021, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,400,000. During 2021, costs of $2,160,000 were incurred, with estimated costs of $4,160,000 yet to be incurred. Billings of $2,692,000 were sent, and cash collected was $2,410,000. In 2022, costs incurred were $2,692,000 with remaining costs estimated to be $3,840,000. 2022 billings were $2,942,000, and $2,635,000 cash was collected. The project was completed in 2023 after additional costs of...