Question

A construction company signed a contract to build a highway. The duration of the project is five years. Based on projects sc

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Pls see table below for calculations, without considering the purchase price of the quarry.

The savings from buying the quarry on the unit price of aggregate is $5.8 - 4.3 = $1.5 per m3. Hence annual savings are: $1.5 * 50,000 = $75,000.

Total CF / (1.1^Time)
Time Savings on aggregate Salvage value of quarry Total CF PV (Total CF)
1 75000 75000 68181.818
2 75000 75000 61983.471
3 75000 75000 56348.61
4 75000 75000 51226.009
5 75000 200000 275000 170753.36
Total 408493.27

An amount of $408493.27 can be paid for the quarry.

Add a comment
Know the answer?
Add Answer to:
A construction company signed a contract to build a highway. The duration of the project is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 1 A construction company signed a contract to build a highway. The duration of the...

    Question 1 A construction company signed a contract to build a highway. The duration of the project is five years. Based on project's schedule, the company will require 50,000 m² of aggregate each year. The aggregate can be obtained from a nearby query for $5.80 per mº. However, the project manager is studying buying the query. If so, the cost of the aggregate would be only $4.30 per mº. Also, the manager thinks that the quarry can be sold at...

  • 1) A highway construction company is under contract to build a new roadway through a scenic area ...

    1) A highway construction company is under contract to build a new roadway through a scenic area and two rural towns in Colorado. The road is expected to cost $18,000,000, with annual upkeep estimated at S150,000 per year. Additional income from tourist (Benefits) of $900,000 per year is estimated. The road is expected to have a useful commercial life of 20 years. Determine if the highway should be constructed at a discount rate of 6% per year, applying the Conventional...

  • A highway construction company is under contract to build a new roadway through a scenic area...

    A highway construction company is under contract to build a new roadway through a scenic area and two rural towns in Colorado. The road is expected to cost $10,000,000, with annual upkeep estimated at $150,000 per year. Additional income from tourist (Benefits) of $900,000 per year is estimated. The road is expected to have a useful commercial life of 15 years. The discount rate to evaluate this project is 6% per year. Hint: Disbenefits = $0 and Annual Upkeep is...

  • A construction company is negotiating on a construction project with a three-month duration. On the last...

    A construction company is negotiating on a construction project with a three-month duration. On the last day of each month the construction company may bill the owner for the work completed during the month. The owner pays the monthly bills one month after they are received. Final payment is expected one month after completion of the project and will include the retention. The construction company pays material suppliers in full when they receive payment from the owner. The construction company...

  • General Construction Company General Construction Company has a contract to build three lower‐income apartment buildings for...

    General Construction Company General Construction Company has a contract to build three lower‐income apartment buildings for the city of Santa Fe, New Mexico. During construction of the first building, the Project Manager formed an auditing team to audit the construction process for each building. He asked the team to develop a list of minimum requirements for the projects and use this as a baseline in the audit. While reviewing the contract documents, one of the audit team members found a...

  • The city of Ottawa is considering to build a new toll highway that spans from Orleans...

    The city of Ottawa is considering to build a new toll highway that spans from Orleans to Kanata, the project cost is estimated to be $90,000,000 and is to be paid in 3 equal payments (Payment 1 before commencement, Payment 2 at the end of the 1st year and Payment 3 at the end of 2nd year when the construction is done). The feasibility assessment of this project is 25 years after construction. This highway benefits the city a total...

  • Question 2 (30%) The city of Ottawa is considering to build a new toll highway that spans from Orleans to Kanata, the p...

    Question 2 (30%) The city of Ottawa is considering to build a new toll highway that spans from Orleans to Kanata, the project cost is estimated to be $90,000,000 and is to be paid in 3 equal payments (Payment 1 before commencement, Payment 2 at the end of the 1st year and Payment 3 at the end of 2nd year when the construction is done). The feasibility assessment of this project is 25 years after construction. This highway benefits the...

  • Construction company X signed a contract to build a hotel for Donald at the price of...

    Construction company X signed a contract to build a hotel for Donald at the price of HKD 720 million. The cost of the construction at the time of signing the contract was expected to be HKD 900 million with 20% probability, HKD 800 million with 30% probability, HKD 600 million with 30% probability, and HKD 500 million with 20% probability. Donald values the hotel at HKD 850 million. How much should X pay to Donald in case of a breach...

  • In 2020, Dixon Construction Company was awarded a contract to construct an interchange on Highway 30...

    In 2020, Dixon Construction Company was awarded a contract to construct an interchange on Highway 30 at a total contract price of $15,000,000. Construction is expected to take two years to complete. The estimated total costs of the project are $12,000,000. Dixon uses the percentage-of-completion method to account for long-term contracts. During the first year cost of construction totaled $7,200,000 and the total estimated costs for the project are unchanged. a)   Prepare the entry to record 2020 construction costs of...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2018, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2019, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2019 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2020 after additional costs of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT