Question

Operations ManagementAssignment #4 Page 2 Question 2.(Total 20 points): Refer to Question 1. Assume that unusually...

Operations ManagementAssignment #4 Page 2 Question 2.(Total 20 points): Refer to Question 1. Assume that unusually mild weather has caused a change in the quantity and timing of orders for golf carts. The revised plan calls for 100 golf carts at the start of week 6, 100 at the start of week 8, and 100 at the start of week 9.a)Determine the timing and quantities of orders for top and baseb)Assume that equipment problems have resulted in the manufacturer being able to assemble supports in lots of 100 and seats in lots of 50. Revise your material requirements plan for supports and seats to reflect this I need help with this question (2b) Question 1 reference is below: Operations ManagementAssignment #4 Page 1 OPERATIONS MANAGEMENT ASSIGNMENT # 4 (Total 100 points)Due Friday, July 31, 2020

Question 1. (Total 50 points) Information concerning the product structure, lead times and quantities on hand for an electric golf cart is shown in the following table. Use this information to do each of the following:a)Draw the product structure treeb)Develop the material requirements plan that will provide 200 golf carts at the start of week 8, assuming lot-for-lot ordering.Note: Template for MRP included here; print as many copies as necessaryParts List for Electric Golf CartLead Time Quantity on HandElectric Golf Cart10Top140Base120TopSupports (4)1200Cover10BaseMotor2300Body350Seats (2)2120BodyFrame135Controls10Wheels (4)1240

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Q1.

a) Draw the product structure tree

Golf Cart Top Base Support (4) Cover Motor Body Seats (2) Frame Controls Wheel Assembly (4)

b) Develop the material requirements plan that will provide 200 golf carts at the start of week 8, assuming lot-for-lot ordering

Steps to create the MRP table. 1) Enter the gross requirement as per Master Planning Schedule (MPS). Gross requirement of com

1 2 3 4 5 6 7 8 MRP TABLE Item Golf cart SOR = 0 0 0 0 0 0 200 0 0 0 0 0 0 0 0 0 Beg. Inv. Gross Requirement Scheduled Receip

Item 1 2 3 4 5 6 7 8 0 0 0 0 0 180 0 0 Motor SOR = 0 0 0 0 SS= Beg. Inv. Gross Requirement Scheduled Receipt Projected on Han

12 3 4 5 6 7 8 0 0 520 0 0 0 0 0 0 0 0 0 0 Item Beg. Inv. Wheel assembly Gross Requirement SOR = Scheduled Receipt SS= Projec

----------------------------------------------------------------

Q2.

Revised plan:  The revised plan calls for 100 golf carts at the start of week 6, 100 at the start of week 8, and 100 at the start of week 9

MRP based on revised plan is following:

1 2 3 4 5 6 7 8 9 MRP TABLE Item Golf cart SOR = SS= 0 0 0 0 0 100 0 100 0 0 0 Beg. Inv. Gross Requirement Scheduled Receipt

1 2 3 4 5 6 7 8 9 0 0 0 0 100 0 0 Item Cover SOR = SS= 60 0 0 Beg. Inv. Gross Requirement Scheduled Receipt Projected on Hand

Item 1 2 3 4 5 6 7 00 9 0 0 0 0 Frame SOR = 30 0 5 100 0 100 0 0 0 0 0 Beg. Inv. Gross Requirement Scheduled Receipt Projecte

-------------------------

Assume that equipment problems have resulted in the manufacturer being able to assemble supports in lots of 100 and seats in lots of 50. Revised material requirements plan for supports and seats is following:

Item 1 2 3 4 5 6 7 9 0 0 0 240 400 0 Support SOR = 400 0 0 0 0 0 0 0 Beg. Inv. Gross Requirement Scheduled Receipt Projected

Item 1 2 3 4. 5 6 7 9 0 0 0 160 200 0 Seats SOR = 200 0 0 0 0 0 0 0 Beg. Inv. Gross Requirement Scheduled Receipt Projected o

Add a comment
Know the answer?
Add Answer to:
Operations ManagementAssignment #4 Page 2 Question 2.(Total 20 points): Refer to Question 1. Assume that unusually...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • I need help with part B of this question. NOTE: THIS QUESTION WAS NOT ALREADY ANSWERED....

    I need help with part B of this question. NOTE: THIS QUESTION WAS NOT ALREADY ANSWERED. There is a difference, my questions is asking for Supports and Seats NOT Top and Bases. Lead Time Quantity on Hand 0 1 1 1 40 20 1 1 200 0 Parts List for Electric Golf Cart Electric Golf Cart Top Base Top Supports (4) Cover Base Motor Body Seats (2) Body Frame Controls Wheels (4) 2 3 300 50 120 2 1 35...

  • I need help with part B please. Lead Time Quantity on Hand 0 1 1 1...

    I need help with part B please. Lead Time Quantity on Hand 0 1 1 1 40 20 1 1 200 0 Parts List for Electric Golf Cart Electric Golf Cart Top Base Top Supports (4) Cover Base Motor Body Seats (2) Body Frame Controls Wheels (4) 2 3 300 50 120 2 1 35 0 240 1 Operations Management Assignment #4 Page 1 Question 2. (Total 20 points): Refer to Question 1. Assume that unusually mild weather has caused...

  • Please answer the following question for week #2: This is from page 495 of Managing Operations...

    Please answer the following question for week #2: This is from page 495 of Managing Operations Across the Supply Chain by author Morgan Swink 3. Complete the MRP record for a bicycle seat. MRP Record Part Name: Seat Lead time = 1 week On hand = 30 Safety stock = 20 Order quantity: FOQ = 100 Week Week Week Week Week Week Week Week 2 Gross Requirements 7050 7060 80 Scheduled Receipts Available Inventory Net Requirements Planned Order Receipts Planned...

  • - Data Table for Problems 14.17 through 14.19* Period 1 2 3 4 5 6 7 8 9 10 11 12 requirements 30 ...

    please answer 14.17 - Data Table for Problems 14.17 through 14.19* Period 1 2 3 4 5 6 7 8 9 10 11 12 requirements 30 40 30 70 20 10 80 50 8 "Holding cost $2.50/unit/week; setup cost $150; lead time 1 week; beginning n Gross inventory 40 m14.17 Develop a lot-for-lot solution and calculate total rel- s evant costs for the data in the table for Problems 14.17 through d 14.19. Px 14.18 Develop an EOQ solution and...

  • have to minimize the cost than $1050 CHAPTER 14 MATERIAL ... 14.18 Develop a lot-for-lot solution...

    have to minimize the cost than $1050 CHAPTER 14 MATERIAL ... 14.18 Develop a lot-for-lot solution and calculate total relevant costs for the data in the preceding table. CHAPTER 14 MATERIAL ... 14.18 Develop a lot-for-lot solution and calculate total relevant costs for the data in the preceding table. se 12 fo he datam the prece in Develop costs for the De our answers for the 19, and 14.20 LEAD 14.18, 14.10 de Koster, or Rene M. de ka ywn...

  • supply chain question, please solve it anyone.

    There are two (2) Parts to this case.  The First part (Part 1) requires you to use the information to:1.    Build a Bill of Material (BOM) form the given information2.    Determine the Master Production Schedule (MPS) and3.    Complete the MRP for all parts including the product.   The Second Part (Part 2) will require you to use an indexed BOM to 1.    Create the correct MPS from the provided information2.    create the MRP for the unit and all of its assemblies/components Part 1:...

  • provide step by step explanation of calculation. thanks

    Case #2 MGT2315  There are two (2) Parts to this case.  The First part (Part 1) requires you to use the information to:1.    Build a Bill of Material (BOM) form the given information2.    Determine the Master Production Schedule (MPS) and3.    Complete the MRP for all parts including the product.   The Second Part (Part 2) will require you to use an indexed BOM to 1.    Create the correct MPS from the provided information2.    create the MRP for the unit and all of...

  • Question 1 (5 points) Output (Q) 5 12 15 Fixed Cost (FC) Variable Cost (VC) Total...

    Question 1 (5 points) Output (Q) 5 12 15 Fixed Cost (FC) Variable Cost (VC) Total Cost (TC) $100 $0 $100 $100 $40 $140 $100 $80 $180 $100 $120 $220 View the following link and then answer the below questions, Week 10 Video Use the table at the top of this page to answer the following questions. 1) What is average fixed cost (AFC) when output (Q) is 12? (Round you answer to 2 decimals.) 2) What is average variable...

  • there is an assignment 2 this must be done with the given scenario 1:49 PO all...

    there is an assignment 2 this must be done with the given scenario 1:49 PO all 77% Comprehensive Operations Plan Individual Student Assignment Using the materials learned each week throughout this course, create a comprehensive operations plan for the selected scenario. Use the same scenario you selected for Assignment 01 The written report must be completed to a highly professional level which could be provided to business executives in any major firm. Clarity, appearance, content, spelling and grammar are all...

  • Materials Requirements Planning (MRP) Franklin Fan’s two most profitable products are the ceiling fan (CF151) and...

    Materials Requirements Planning (MRP) Franklin Fan’s two most profitable products are the ceiling fan (CF151) and the personal fan (PF032). With the rising popularity in home remodeling and personal comfort, Franklin Fan has enjoyed substantial demand for these two products. Last year, Kathryn Marley, the vice president of operations and supply chain management, approved the installation of a new MRP system. It is a first important step toward the eventual goal of a full-fledged ERP system. Marley worked closely with...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT