Question

Given the following data and network, find answer the questions 18-20 if youre asked to finish this project 2 days earlier t
Question 18 What is the normal cost of this project? Previous
Question 19 What is the cost of the project after 2 days shortening? Previous Not saved MacBook Pro
240 min Question 20 What is the crashing cost per day for activity G? • Previous Not save
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer :

Path duration:

A-B-F-J-K =25 days (critical path)

A-B-E-H-K = 23 days

A-C-F-H-I-K = 24 days(sub critical path)

A-DG-J-K = 20 days

A-B-F-J-K = 23 days

18) Normal cost of the project = direct cost of all activities + overall cost of critical path

= 800+1000+300+400+100+500+1200+350+700+500+450+(200*25)

=6300+5000

So, Normal cost of the project = $11300

19)After calculating path slope ,we found slope I has least cost slope of 75 in path A-B-F-J-K.So,we will crash cost slope I by one day,

New Total cost = 11300+75-200 = $11175.

We have two critical bath(A-B-F-I-K and A-C-F-I-K).I has found common in both the paths

Boe,crash cost slope of I by one more day.

Now,Total cost = 11175+75-200 = $11050.

Hence,Cost of the project after 2 days shortening = $11050.

20) Crashing cost per day for activity G = Cost Slope of G = 1400-1200/8-4 = 50.

Crashing cost per day for activity G = $50.

Add a comment
Know the answer?
Add Answer to:
Given the following data and network, find answer the questions 18-20 if you're asked to finish...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 1: I)-What is the normal cost of this project? II)-What is the cost of the...

    Question 1: I)-What is the normal cost of this project? II)-What is the cost of the project after 2 days shortening? III)-What is the crashing cost per day for activity G? Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 3 1.8 12. 19 10,13 B 7 1,8 13.20 0,1 1,7 8.15 20,25 15.20 F...

  • what is the normal cost of this project? what is the cost of the project after...

    what is the normal cost of this project? what is the cost of the project after 2 days shortening? what is the crashing cost per day for avtivity G? Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 1.8 اليا 12.19 10.13 B 7 H 7 1.8 13, 20 0.1 1.7 8.15 20,25 15, 20...

  • Given the data table below develop the precedence network and perform the CPM calculations. Then, using...

    Given the data table below develop the precedence network and perform the CPM calculations. Then, using the proposed crashing strategy calculate the normal, least-cost, and crash duration for the project below. Calculate the cost associated with each duration. Indirect cost (overhead) is $120 per day. Activity IPA Duration Cost $ Normal Crash Normal Crash A 5 4 $770 $900 3 2 B C P 7 4 $660 $700 $800 $1,070 $1,000 $1,110 $800 $920 D AB 4 3 E B...

  • Question 16 4 points Save Answe The following provides information about a project, including a list...

    Question 16 4 points Save Answe The following provides information about a project, including a list of activities and precedence relationships, activity durations (normal and "crash" times), direct activity costs (normal and "crash"), indirect costs for the project, as well as calculated crash costs/day and the maximum amount that each activity can be shortened (crashed) by. There are no penalty costs for this project. Total project cost (using normal times), a network diagram, and the four paths and durations have...

  • hi need answers for this urgently thanks Question 2 (20 Marks) a) Given the following project...

    hi need answers for this urgently thanks Question 2 (20 Marks) a) Given the following project details, identify the project's critical path; Activity Predecessor A B Duration (Man Days) 5 10 12 8 6 15 D Ε F B, C GE CD G H 20 18 30 5 I,J к F, L M (10 Marks) Continued... b) Given the information below, identify how much it would cost for each day you crash the schedule. Determine the total cost for crashing...

  • Lecture Exercise #12 Critical Path Method Determine the early start, early finish, late start, late finish...

    Lecture Exercise #12 Critical Path Method Determine the early start, early finish, late start, late finish times for each activity Identify the critical path . Activity А Time (days) 6 7 3 Predecessor(s) None None B с A 2 A E 4 B F 6 B 10 C. E D. F H 7 Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 2 1 А B None None None с 1 1 Cost Normal Crash 1000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT