Problem 13-7 A manager receives a forecast for next year. Demand is projected to be 600 units for the first half of the year
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer a= For period 1-6 months=

Demand =600/6=100 units

EOQ= (2*100*55/2)^0.5=74.16 units =74 units

For period 7-12 months=

Demand =930/6=155 units

EOQ= (2*155*55/2)^0.5=92.33 units =92 units

Answer b=

For period 1-6 months=

TC when the order is placed for 50 units = (100/50)*55+(50/2)*2 =160

TC when the order is placed for 100 units = (100/100)*55+(100/2)*2 =155

TC when the order is placed for 150 units = (100/150)*55+(150/2)*2 =186.67

So TC is less for 100 units so 100 units should be ordered.

For period 7-12 months=

TC when the order is placed for 50 units = (155/50)*55+(50/2)*2 =220.5

TC when the order is placed for 100 units = (155/100)*55+(100/2)*2 =185.25

TC when the order is placed for 150 units = (155/150)*55+(150/2)*2 =206.83

So TC is less for 100 units so 100 units should be ordered.

Add a comment
Know the answer?
Add Answer to:
Problem 13-7 A manager receives a forecast for next year. Demand is projected to be 600...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A manager receives a forecast for next year. Demand is projected to be 528 units for...

    A manager receives a forecast for next year. Demand is projected to be 528 units for the first half of the year and 1,020 units for the second half. The monthly holding cost is $2 per unit, and it costs an estimated $55 to process an order. a. Assuming that monthly demand will be level during each of the six-month periods covered by the forecast (e.g., 88 per month for each of the first six months), determine an order size...

  • A manager receives a forecast for next year. Demand is projected to be 530 units for...

    A manager receives a forecast for next year. Demand is projected to be 530 units for the first half of the year and 1,000 units for the second half. The monthly holding cost is $2 per unit, and it costs an estimated $55 to process an order. a. Assuming that monthly demand will be level during each of the six-month periods covered by the forecast (e.g., 100 per month for each of the first six months), determine an order size...

  • task: 1. Develop a forecast for the next 12 months. 2. Develop an ordering strategy for...

    task: 1. Develop a forecast for the next 12 months. 2. Develop an ordering strategy for the next 12 months. METRO HOSPITAL You are the materials manager at Metro Hospital. Approximately one year ago, the hospital began stocking a new drug (Ziloene) that helps the healing process for wounds and sutures. It is your responsibility to forecast and order the monthly supply of Ziloene The goal is to minimize the combined cost of overstocking and understocking the drug Orders are...

  • A manager has projected demand for the next six months (below). Given this information, prepare a...

    A manager has projected demand for the next six months (below). Given this information, prepare a LEVEL aggregate plan for production. Assume maximum regular time production is 350 units per month. Overtime is limited to 75 units per month. The limit for subcontracting is 400 per month. The company has a zero beginning inventory and cannot have ending inventory or a backlog at the end of the 6th period. Unit costs are as noted below. Regular Time Cost: $10/unit Overtime...

  • Problem 3. After plotting demand for four periods, an emergency room manager has concluded that a...

    Problem 3. After plotting demand for four periods, an emergency room manager has concluded that a trend- adjusted exponential smoothing model is appropriate to predict future demand. The initial estimate of trend is based on the net change of 30 for the three periods from 1 to 4, for an average of +10 units. Use α-Sand β,4, and TAF of 250 for period 5. Obtain forecasts for periods 6 through 10. Period Actual 210 224 229 240 255 Period Actual...

  • sisas (19-21). A manager has prepared a forecast of expected aggregate demand for the nest s perods Develop an aggregate plan to meet this demand given these additional information . A level produ...

    sisas (19-21). A manager has prepared a forecast of expected aggregate demand for the nest s perods Develop an aggregate plan to meet this demand given these additional information . A level production rate of 300 units per month will be used Period 6 Total Forecast 200 200 300 400 500100 Output Regular time Overtime Sabcontract Inventory Outpet- Forecast leventory Backig 19. What is the anding inventory for period 5? A. 0 B. 100 C. -100 D. 200 E -200...

  • Kangaroo P/L has the following demand forecast next year, expressed in six bimonthly (2-month) periods: Period...

    Kangaroo P/L has the following demand forecast next year, expressed in six bimonthly (2-month) periods: Period Forecast Demand (Standard U nits of Work) 1 400 2 380 3 470 4 530 5 610 6 500 The following costing data have been obtained: Each employee works 176 regular working hours per month Each unit requires 20 standard hours to produce The labour costs are $6 per normal hour and $9 per overtime hour It costs $3 per month to hold an...

  • A manager has been using a certain technique to forecast demand for project management software at...

    A manager has been using a certain technique to forecast demand for project management software at her store. Actual demand and her corresponding predictions are shown below: MonthActual Demand Manager's Forecast March4545April4250May3445June4840July3845 a. What was the manager's forecast error for each month?b. What is the mean error (ME), the mean squared error (MSE), the mean absolute deviation (MAD), and the tracking signal for these five months of forecasting?c. If the manager had used a 3-month moving average instead of her technique, what would have...

  • A local firm manufactures children's toys. The projected demand over the next four months for one...

    A local firm manufactures children's toys. The projected demand over the next four months for one particular model of toy robot is as follows: MONTH---------------WORKDAYS------------FORECAST DEMAND (IN AGGREGATE UNITS) July 23 3825 August   16 7245 September 20 2770 October 22 4440 Assume that the normal workday is 8 hours. Hiring costs are $350 per worker and firing costs (including severance pay) are $850 per worker. Holding costs are $4 per aggregate unit held per month. Assume that it requires an...

  • please showing working.. formulas 10. A company produces sofas. The manager wants to prepare a 0. am for the next si...

    please showing working.. formulas 10. A company produces sofas. The manager wants to prepare a 0. am for the next six months using the following information: plan Month 2 3 456 160 150 160 180 170 140 recast demand For Cost Per Unit Regular time $100 Overtime $150 Part-time $120 Inventory, per month $10 Back order, per month $50 There are five workers, each making 30 sofas a month. The maximum number of sofas produced during overtime is 30 per...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT