A local firm manufactures children's toys. The projected demand over the next four months for one particular model of toy robot is as follows:

MONTH---------------WORKDAYS------------FORECAST DEMAND (IN AGGREGATE UNITS)

July 23 3825

August   16 7245

September 20 2770

October 22 4440

Assume that the normal workday is 8 hours. Hiring costs are $350 per worker and firing costs (including severance pay) are $850 per worker. Holding costs are $4 per aggregate unit held per month. Assume that it requires an average of 1 hour 40 min for one worker to assemble one toy. Shortages are not allowed. Assume that the ending inventory for June was 600 of these toys and the manager wishes to have at least 800 units on hand at the end of October. Assume that the current workforce level is 35 workers.

a. Find the minimum constant workforce plan for the four month and the total hiring, firing, and holding cost of that plan.

b. determine the plan that changes the workforce level each month to most closely match the demand and the cost of that plan.

solve it using manual tables and calculations. NOT EXCEL OR LINEAR PROGRAMMING

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Given data-

Normal Workday time-8 hrs.

Hiring cost per worker-$ 350

Firing Cost per Worker( Including severance pay)-$ 850

Holding Cost per Aggregate unit per month-$ 4

Time taken assembling one toy by one worker-1 hr 40 min

Ending Inventory for june-600 units

Current workforce-35 workers

In hand inventory Required in October end-800 units

Month Workdays Forcast Demand ( in Aggregate units)
July 23 3825
August 16 7245
September 20 2770
October 22 4440

(a) Min constant workforce plan for four months-

let us have min constant 35 workers for four months.

for July-

Toys inventory in hand-600 toys.

toy produced by one worker in one day=8 hrs/1hr 40 min

=480 minutes/100 minutes=4.8 toys

Toy produced by 35 workers in 1 day=35*4.8=168 toys

toy produced in 23 days=168*23=3864 toys

Now total toys available=3864+600=4464 toys

toy Dispatched in month of july=3825 toys

Closing toys inventory in July=639 toys

For August-

Toys Inventory in hand-639 toys.

Toys demand-7245 Toys.

Toys can be Produced with 35 workers in 16 days=35*4.8*16=2688 toys

Toys required after adjusting previous inventory=3918 toys

more workers required to complete this order in 16 days=3918/4.8*16=51 workers

With these workers we will produce toys in 16 days=51*4.8*16=3916 toys

Now total toys in august-3916+3918=7834 toys

Closing toy inventory in august=7834-7245=589 toys.

Hiring cost of workers=51*350=$ 17850

firing cost after august=51*850=$ 43350

For September-

Opening inventory-589 toys

Toy will produce in 20 days by 35 workers=35*20*4.8=3360 toys

Closing inventory after dispatching 2770 toys=3360-2770=590 toys

For October-

Opening inventory=590 toys

Toy will produce by 35 workers in 22 days=35*22*4.8=3696 toys.

we require 9 more workers to fulfil the condition of 800 units at the oct end.

hiring cost of 9 workers=9*350=$ 3150

firing cost of 9 workers=9*850=$7650

(b)

for july-

we require only 30 workers for this month order

opening inventory=600 toys.

30 workers will produce in 23 days=30*4.8*23=3312 toys.

closing inventory after dispatching this order=3912-3825=87 toys

firing cost of 5 employees=5* 850=$ 4250

For august-

here we need 63 more employees to complete the order

hiring cost of 63 employees=63*350=$ 22050

Firing cost of 63 employees=63*850=$ 53550

For Sep-

30 workers will produce in 20 days=30*20*4.8=2880 toys

Add a comment
Know the answer?
Add Answer to:
A local firm manufactures children's toys. The projected demand over the next four months for one...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The current aggregate demand requirements for a firm are shown below for the next six months:...

    The current aggregate demand requirements for a firm are shown below for the next six months: Month May June July Aug Sept Oct Demand 270 250 250 250 280 300 The firm always plans to meet all demand. The firm currently has 270 workers capable of producing 270 units in a month (1 unit/worker). The workforce can be increased (at a cost of $700 per worker) or decreased (at a cost of $1,400 per worker). Inventory holding cost is $175...

  • Check The current aggregate demand requirements for a firm are shown below for the next six...

    Check The current aggregate demand requirements for a firm are shown below for the next six months: Month May June July Aug Sept Oct 230 Demand 210 210 210 240 260 Click here for the Excel Data File The firm always plans to meet all demand. The firm currently has 230 workers capable of producing 230 units in a month (1 unit/worker). The workforce can be increased (at a cost of $500 per worker) or decreased (at a cost of...

  • The current aggregate demand requirements for a firm are shown below for the next six months:...

    The current aggregate demand requirements for a firm are shown below for the next six months: Month May June July Aug Sept Oct Demand 230 210 210 210 240 260 PpictureClick here for the Excel Data File ped The firm always plans to meet all demand. The firm currently has 230 workers capable of producing 230 units in a month (1 unit/worker). The workforce can be increased (at a cost of $500 per worker) or decreased (at a cost of...

  • Problem 13-4 The current aggregate demand requirements for a firm are shown below for the next...

    Problem 13-4 The current aggregate demand requirements for a firm are shown below for the next six months MonthMay June July Aug Sept Oct Demand 260 240 240 240 270 290 The firm always plans to meet all demand. The firm currently has 260 workers capable of producing 260 units in a month (1 unit/worker). The workforce can be increased (at a cost of $650 (at a cost of $1,300 per worker). Inventory holding cost is $150 per unit per...

  • Mr. Meadows Cookie Company (MCC) makes a variety of chocolate chip cookies in a certain plant....

    Mr. Meadows Cookie Company (MCC) makes a variety of chocolate chip cookies in a certain plant. Based on orders received and forecasts of buying habits, it is estimated that the demand for the next four months is 850, 1260, 510, and 980, expressed in thousands of cookies. During a 46-day period when there were 120 workers, the company produced 1.7 million cookies. Assume that the number of workdays over the four months is respectively 26, 24, 20, and 16. There...

  • The Mr. Meadows Cookie Company can obtain accurate forecasts for 12 months based on firm orders....

    The Mr. Meadows Cookie Company can obtain accurate forecasts for 12 months based on firm orders. These forecasts and the number of workdays per month are as follows: Month Workdays Demand Forecast in thousands of cookies 850 1260 436 980 770 850 1050 1550 1350 1000 970 680 26 24 20 18 4 23 21 23 24 21 13 12 During a 46-day period when there were 120 workers, the firm produced 1,700,000 cookies. Assume that there are 100 workers...

  • 1) (25pts) An engineer is making aggregate planning for the next 4 months. Demand forecasts in...

    1) (25pts) An engineer is making aggregate planning for the next 4 months. Demand forecasts in aggregate items are 600, 350, 400, 700 for months 1 to 4. The company has an initial workforce of 80 and capacity can be adjusted by hiring (at a cost of 150 liras per worker) or firing (at a cost of 900 liras per worker). Each worker is capable of producing 0.2 aggregate items in one workday. The available workdays are given as 25,...

  • 36. The Yeasty Brewing Company produces a popular local beer known as Iron Stomach. Beer sales...

    36. The Yeasty Brewing Company produces a popular local beer known as Iron Stomach. Beer sales are somewhat seasonal, and Yeasty is planning its production and workforce levels on March 31 for the next six months. The demand forecasts are as follows: Production Days Forecasted Demand (in hundreds of cases) 85 Month April May June July August September 122 176 140 20 63 As of March 31, Yeasty had 86 workers on the payroll. Over a period of 26 work-...

  • How would you modify the workforce to reduce cost? What would be the cost of the...

    How would you modify the workforce to reduce cost? What would be the cost of the 46-worker production plan? Assume the following costs: • Holding Cost (per unit per month): $8.50 • Hiring Cost per worker: $800 • Firing Cost per worker: $1,250 • Payroll Cost: $75/worker/day Shortage Cost: $50 unit short/month • Assume that the work force at end of Dec was 40. • How many did you have to hire? Starting inver Ending invent 200 100 K= 0.342105263...

  • A firm must plan production for the next six months. Each unit costs $430 to produce...

    A firm must plan production for the next six months. Each unit costs $430 to produce and it has an inventory holding cost of $15 per unit per month based on ending inventory levels. The cost to hire a worker is $280, and the cost to fire a worker is $560 per worker. Each worker produces 10 units per month. There are 20 persons on the payroll at the beginning of the first month. The company currently has 150 units...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT