Question

The Silver Star Bicycle Company will be manufacturing both mens and womens models of its Easy-Pedal 10-speed bicycles durinb. If the company changed the constraints so that monthly labor increases and decreases could not exceed 50 hours, what wouldplease answer all of B and my answers for part A are correct.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer b: The optimal solution is to produce Mens model in month 1 201 Mens model in month 2 164 Womens model in month 1 9Minimize: LP model formulation Let: X11 = amount of mens model in month 1 X21 = amount of womens model in month 1 x12 = amoLP model formulation Minimize: 160x11 + 130x21 + 160x12 + 130x22 + 3.2s11 + 2.6s21 + 3.2s12 + 2.6s22 s.t. x11 - 511 = 130 SatEnter data>add formulas>go to datatab>solver>add constraints>solve B с - E D F G H J к L M N o Р Q R S Problem setup area X11Add Constraints Solver Parameters Х Set Objective: SMS121 1 To: Омах O Min O Value of: 0 By Changing Variable Cells: $B$25:51Formulas in excel A B с D E F G H J K L M N 16 Constraint 4 9 10 Data 11 12 Objective 10 13 Constraint 1 14 Constraint 2 15 C

Add a comment
Know the answer?
Add Answer to:
please answer all of B and my answers for part A are correct. The Silver Star...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 4-19 (Algorithmic) The Silver Star Bicycle Company will be manufacturing both men’s and women’s models...

    Problem 4-19 (Algorithmic) The Silver Star Bicycle Company will be manufacturing both men’s and women’s models of its Easy-Pedal 10-speed bicycles during the next two months. Management wants to develop a production schedule indicating how many bicycles of each model should be produced in each month. Current demand forecasts call for 150 men’s and 125 women’s models to be shipped during the first month and 220 men’s and 170 women’s models to be shipped during the second month. Additional data...

  • Please help and show work for all steps! Everything marked with a red X is incorrect....

    Please help and show work for all steps! Everything marked with a red X is incorrect. Problem 4-19 (Algorithmic) The Silver Star Bicycle Company will be manufacturing both men's and women's models of its Easy-Pedal 10-speed bicycles during the next two months. Management wants to develop a production schedule indicating how many bicycles of each model should be produced in each month. Current demand forecasts call for 160 men's and 135 women's models to be shipped during the first month...

  • The Silver Star Bicycle Company will be manufacturing both men’s and women’s models of its Easy-Pedal...

    The Silver Star Bicycle Company will be manufacturing both men’s and women’s models of its Easy-Pedal 10-speed bicycles during the next two months. Management wants to develop a production schedule indicating how many bicycles of each model should be produced in each month. Current demand forecasts call for 170 men’s and 145 women’s models to be shipped during the first month and 210 men’s and 160 women’s models to be shipped during the second month. Additional data are shown: Production...

  • The Silver Star Bicycle Company will manufacture both men's and women's models for its Easy-Pedal bicycles...

    The Silver Star Bicycle Company will manufacture both men's and women's models for its Easy-Pedal bicycles during the next two months. Management wants to develop a production schedule indicating how many bicycles of each model should be produced in each month. Current demand forecasts call for 150 men's and 125 women's models to be shipped during the first month and 200 men's and 150 women's models to be shipped during the second month. Additional data are shown: Labor Requirements (hours)...

  • The Silver Star Bicycle Company will manufacture both men's and women's models for its Easy-Pedal bicycles...

    The Silver Star Bicycle Company will manufacture both men's and women's models for its Easy-Pedal bicycles during the next two months. Management wants to develop a production schedule indicating how many bicycles of each model should be produced in each month. Current demand forecasts call for 150 men's and 125 women's models to be shipped during the first month and 200 men's and 150 women's models to be shipped during the second month. Additional data are shown: Labor Requirements (hours)...

  • Aside from selling yarn skeins, the Yarn Barn also plans to sell men’s and women’s hand-knit...

    Aside from selling yarn skeins, the Yarn Barn also plans to sell men’s and women’s hand-knit scarves during the next 2 months. The company wants to develop a production schedule indicating how many scarves of each type should be produced each month. Current demand forecasts show that 150 men’s and 125 women’s scarves are needed during the first month and 200 men’s and 150 women’s scarves are needed for the second month. Additional data are shown in Figure 2: Labour...

  • Also please solve by either using excel or R LP solvers The Magnetron Company manufactures and markets microwave ovens. Currently, the company produces two models: full-size and compact. Produc...

    Also please solve by either using excel or R LP solvers The Magnetron Company manufactures and markets microwave ovens. Currently, the company produces two models: full-size and compact. Production is limited by the amount of labor available in the general assembly and electronic assembly departments, as well as by the demand for each model. Each full-size oven requires 2 hours of general assembly and 2 hours of electronic assembly, whereas each compact oven requires 1 hour of general assembly and...

  • Help please! work i Check my work mode : This shows what is correct or incorrect...

    Help please! work i Check my work mode : This shows what is correct or incorrect for the work y Requirea 1 Requirea 2 ********************************* Prepare a schedule of cost of goods manufactured for the month. ...............................***. Primare Corporation Schedule of Cost of Goods Manufactured $ 12,000 30,000 42,000 18,000 24,000 5,000 ololololo Direct materials: Beginning raw materials inventory Add: Purchases of raw materials Total raw materials available Less: Ending raw materials inventory Raw materials used in production Less: Indirect...

  • Why are these answers wrong? Your answer is partially correct. The following information is available for...

    Why are these answers wrong? Your answer is partially correct. The following information is available for Tomlin Company. Raw materials inventory Work in process inventory April 1 $11,000 5,410 April 30 $14,300 3,660 Materials purchased in April Direct labor in April Manufacturing overhead in April $97,700 80,300 155,000 Prepare the cost of goods manufactured schedule for the month of April. TOMLIN COMPANY Cost of Goods Manufactured Schedule For the Month Ended April 30 Work in process, April 1 $ Direct...

  • The New England Cycle Company is planning next month’s production of its two bicycles: its B2...

    The New England Cycle Company is planning next month’s production of its two bicycles: its B2 tandem cycle built for two and its S10 single-rider 10-speed model. Both models use the same seats and tires. Management has been informed that 2000 seats, 1000 gear assemblies (only the S10 requires a gear assembly), and 2400 tires are available next month for production. On the average, it takes two hours to produce a B2 and three hours to produce a S10 bicycle....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT