Question

is an iterative planning technique for projects. O meetings O decomposition O rolling wave planning all of the above
The schedule management plan can establish O a. availabilty O b. level of accuracy O c. skills O d. all of the above
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer: Rolling Wave Planning

Rolling wave arranging is an iterative arranging procedure where work further, later on, is arranged at a more elevated level. is a type of Progressive elaboration arranging. In this procedure venture group plans for the not so distant future as small as could reasonably be expected, while the work far, later on, stays anticipated an elevated level.

Answer: All of above

The Schedule Management Plan characterizes how the undertaking plan is supervised all through the venture lifecycle. The arrangement gives direction and sets desires to extend plan strategies and methodology for arranging, creating, overseeing, executing, and controlling the venture plan.

Add a comment
Know the answer?
Add Answer to:
is an iterative planning technique for projects. O meetings O decomposition O rolling wave planning all...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 5. All of the following are true about projects and operations EXCEPT: A Operations are ongoing...

    5. All of the following are true about projects and operations EXCEPT: A Operations are ongoing endeavours that produce repetitive outputs, with resources assigned to do basically the same set of tasks according to the standards institutionalzed in a product life cycle, whereas projects are temporary endeavours Projects require project management activities and skill sets, whereas operations require business process management, operations management activities, and skill sets. Projects can intersect with operations at various points during the product life cycle....

  • Answers Question 1 2 3 4 5 6 7 8 9 10 Answer 1) What are...

    Answers Question 1 2 3 4 5 6 7 8 9 10 Answer 1) What are excuses used by PMs to avoid adequate project planning? a) PMs say planning takes too much time. b) PMs say customers don't know what they want. c) PMs say that if they commit, they will be held accountable. d) All of the above e) None of the above 2) What is the primary purpose of planning? a) Telling the project team exactly what must...

  • Sample Questions (Midterm Exam) Chapter 5 Initiating and Planning Systems Development Projects 1) Who is typically...

    Sample Questions (Midterm Exam) Chapter 5 Initiating and Planning Systems Development Projects 1) Who is typically responsible for performing the PIP process? A) Managers B) Users C) Systems analyst D) The basiness unit 2) What is an example of a project assumption? A) Size B) Potential problems C) Soope D) Complexity Answer: B Difficulty: Difficult AACSB: Information Technology LO: 5.1 Deseribe the steps involved in the project initiation and planning process Classification: Concept 3) What is the tem that describes...

  • Answer ALL questions (100 marks) 1 (a) Describe briefly the factors to be considered in planning...

    Answer ALL questions (100 marks) 1 (a) Describe briefly the factors to be considered in planning a good site layout in the most effective and efficient manner (6 marks) (b) Provide the definition of the following terms in the British Standard Glossary of terms in Work Study under BS 3138:- Method Study (m) Work Measurement (4 marks (c) Describe briefly the benefits of work study to the organization (5 marks) Page 2 of 10- (d) List any Five 15 principles...

  • 29. A major difference between facilities planning and scheduling is that: A. Facilities planning...

    29. A major difference between facilities planning and scheduling is that: A. Facilities planning refers to long-range capacity plan and scheduling refers to short-range capacity plan. B. Facilities planning is concerned with allocating available resources and scheduling with the acquisition of resources. C. Facilities planning refers to medium-range resource requirement and scheduling refers to long-range capacity requirement. D. None of the above. 30. Suppose the cost of not having adequate capacity is very high. What type of capacity cushion strategy...

  • 29. A major difference between facilities planning and scheduling is that: A. Facilities planning refers to...

    29. A major difference between facilities planning and scheduling is that: A. Facilities planning refers to long-range capacity plan and scheduling refers to short-range capacity plan. B. Facilities planning is concerned with allocating available resources and scheduling with the acquisition of resources. C. Facilities planning refers to medium-range resource requirement and scheduling refers to long-range capacity requirement. D. None of the above. 30. Suppose the cost of not having adequate capacity is very high. What type of capacity cushion strategy...

  • 1. What type of wave is shown below? O A. Transverse wave O B. Longitudinal wave...

    1. What type of wave is shown below? O A. Transverse wave O B. Longitudinal wave O c. Combined wave O D. Sound wave 2. What is the amplitude and wavelength of the wave shown below? y (cm) 40 30 20 10 x (cm) 200 20 40 80 100 40 160 180 10 -20 -30 -40 O A. Amplitude: 30 cm: wavelength: 60 cm O B. Amplitude: 30 cm, wavelength: 110 cm O C. Amplitude: 60 cm; wavelength: 60 cm...

  • Your management team has decided that all orders will be treated as projects and that project...

    Your management team has decided that all orders will be treated as projects and that project managers will be used to update orders daily, to resolve issues, and to ensure the customer formally accepts the product within 30 days of completion. Revenue from the individual orders can vary from $100 to $150,000. The project manager will not be required to perform planning or provide documentation other than daily status. How would you define this situation? A. Because each individual order...

  • a. Supply chain management includes the planning and management of all activities involved in sourcing and...

    a. Supply chain management includes the planning and management of all activities involved in sourcing and procurement, conversion, and all logistics management activities. It also includes: Group of answer choices human resources and job design. coordination and collaboration with supply chain partners. selling and marketing products All of the above. b.One of the key downsides (for the manufacturer) in using the CHASE AGGREGATE PLANNING strategy is _____________ Group of answer choices higher inventory levels. employee discontent. customer dissatisfaction. higher consumer...

  • Aggregate Planning

    A While the demand for regular fabric has declined, the demand for medical-grade fabric has been surging in the market. In response, the management at Fabric Mills quickly bumped up the regular output of medical-grade fabric by reassigning workers from the production of regular fabric and rehiring retired workers. Table 2 shows the demand forecast and capacity for medical-grade fabric. Note that overtime is limited to 20% of the regular capacity. The availability of subcontract is also limited due to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT