Question

Miles Wilder, project manager for the Cybersonic project, considers himself a “project manager’s project manager.” He...

Miles Wilder, project manager for the Cybersonic project, considers himself a “project manager’s project manager.” He claims to use the principles of good project management, starting with having a plan and using it to carefully track the project. He announces to his team leaders that status meetings will be held on alternate Mondays throughout the expected year-long project. All 18 project team leaders must attend and give rundowns of the tasks they are currently working on.All the team leaders show up for the first status meeting. Seven are currently managing work for the project and are scheduled to give reports; the other 11 are not yet working on the project (as specified by the project schedule) but attend because Miles wants them to stay informed about project progress. The meeting is scheduled for 3 hours; the team leaders are to report on whatever they think important. After 4 hours of reports by five of the leaders, Miles ends the meeting. Several major problems are reported that he tries to resolve at the meeting. Specific actions to resolve some of them are decided, and Miles schedules another meeting for 2 days later to address the other problems and hear the remaining two reports. Some of the team leaders are miffed because they’ll have to change their schedules to attend the meeting.Miles arrives an hour late at the next meeting, which, after 3 hours, allows enough time to resolve all the problems but not enough for the two leaders to give reports. Miles asks them if they are facing any major issues or problems. When they respond “no,” he lets them skip the reports but promises to start with them at the next meeting 2 weeks later. A few of the team leaders are assigned actions to address current problems. Some of the attendees feel the meeting was a waste of time.Before the next meeting, some of the leaders inform Miles they cannot attend and will send representatives. This meeting becomes awkward for three reasons. First, several new problems about the project are raised and, again, the ensuing discussion drags out and there is insufficient time for everyone to give a status report; only six of a scheduled eight team leaders give their reports. Second, some of the leaders disagree with Miles about actions assigned at the previous meeting. Because no minutes had been taken at that meeting, each leader had followed his/her own notes about actions to take, some of which conflict with Miles’ expectations. Third, people at the meeting who are “representatives” are not fully aware of what happened at the previous meetings, do not have sufficient information to give complete reports or answer questions, and are hesitant to commit to action without their team leaders’ approval.The next several meetings follow the same pattern: they run over schedule; fewer team leaders and more representatives attend; status reports are given because of inadequate time; people disagree over problems identified and actions to be taken. The project falls behind schedule because problems are not addressed adequately or quickly enough.Miles feels that too much time is being wasted on resolving problems at the meetings and that many problems should, instead, be resolved entirely by the team leaders. He instructs the leaders to work out solutions and changes on their own, and to report at status meetings only the results. This reduces the length of the meetings but creates other complications: some team leaders take actions and make changes that ignore project dependencies and conflict with other leaders’ work tasks. Everyone is working overtime, but the Cybersonic project falls further behind schedule.

QuESTionS1. Why is Miles’ approach to tracking and controlling the Cybersonic project ineffective?

2. If you were in charge, what would you do?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:-

1)

Miles' approach to tracking and controlling the Cybersonic project is ineffective in light of the fact that he had not made arrangements for the gathering early and simply educated each project head about the gathering just to determine the progressing project related issues.

As he had not educated project pioneers before, they felt despondent in light of the fact that they needed to change their calendars to go to the gathering. From the start, the group heads are not relegated any undertaking to chip away at it, they are simply approached to submit reports. Masterminding extended periods of time of meeting, not ready to take care of everyone's issues on schedule, absence of reliability, all these lead to postpone in project accommodation and tumult among the project directors.

An expert and capable director, as Mile claims himself must sort out the gathering without upsetting timetables of all project chiefs and he should resolve all the issues of individual pioneers in an expert way rather than extended periods of meeting. Because of inappropriate arranging, a portion of the project heads found that going to meeting is an exercise in futility. Because of inadequate time a portion of the project chiefs are disregarded to take care of issues according to their own level, this makes clashes among the project heads. Some of them are not happy with Miles' method of directing the gathering.

Because of ill-advised gathering plans, a portion of the project heads send their agents which made another issue, i.e., absence of attention to what occurred at the past gatherings, because of deficient data they couldn't finish the reports and additionally waver to make any move without their pioneers' authorization. So inappropriate calendar, nearness of less group pioneers and more agents, accommodation of status reports are not on schedule, issues are not tackled rapidly enough and conflicts of supposition, all these lead to defer in project culmination.

2)

On the off chance that I were in charge, I would follow a methodical method of directing gatherings, work with plan as indicated by the prerequisite that suits the calendars of project pioneers. Handle the issues in a progressively proficient way, attempt to take care of the considerable number of issues inside the predefined plan, listen each project heads' supposition and work on it.

I would keep the gathering short and pay significance to correct focuses just and help every pioneer in booking time and taking care of issues. I would oversee groups as opposed to disregarding them on their own which lead to clashes among them.

Please please like the answer.........

Add a comment
Know the answer?
Add Answer to:
Miles Wilder, project manager for the Cybersonic project, considers himself a “project manager’s project manager.” He...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A Case Study on Conflict Management Shirley and Abdul both work for a software development company....

    A Case Study on Conflict Management Shirley and Abdul both work for a software development company. The manager of the new product division was originally the leader of the project team for which she interviewed and hired Abdul. Shirley, another project team member, also interviewed Abdul, but strongly opposed hiring him for the project because she thought he was not competent to do the job. Seven months after Abdul was hired, the manager left the project to start joint project...

  • Please read the following additional details regarding the Recreation and Wellness Intranet project: Several people on...

    Please read the following additional details regarding the Recreation and Wellness Intranet project: Several people on the Recreation and Wellness Project are confused about who needs to do what for the testing portion of the project. Recall that the team members include you, a programmer analyst and aspiring project manager; Patrick, a network specialist; Nancy, a business analyst; and Bonnie, another programmer analyst. John Prince is the project manager, and he has been working with managers in other departments to...

  • Ali Nasser is the new content & media Manager at the Museum of Heritage & Arts....

    Ali Nasser is the new content & media Manager at the Museum of Heritage & Arts. He is working on the biggest assignment of his career: heading the event and developing the website for the museum's forthcoming new show "Images & Exhibits of Medieval & Contemporary Oman." Ministry of Heritage is underwriting (guaranteeing payment in case of loss/damage) the exhibit, and museum curator (one who manages or oversees, as the administrative director of a museum collection) Basma Said has told...

  • In this exercise, we will re-visit the case study “A day in the life” at the...

    In this exercise, we will re-visit the case study “A day in the life” at the end of Chapter 1. Answer these questions: 1- Based on the information provided in the case, what kind of project management structure you think this organization uses? 2- What conclusions can you draw about the organization culture? Use dimensions introduced in Chapter 3 to support your answer. Case study: A Day in the Life Rachel The project manager of a large information systems project...

  • Communication in the management of a project flows downward, upward, horizontally, and to outside receivers, such...

    Communication in the management of a project flows downward, upward, horizontally, and to outside receivers, such as stakeholders. Project information is distributed through a variety of means such as project meetings, hard copy document distribution, shared access to networked electronic databases, fax, electronic mail, voice mail, videoconferencing, and individual and group discussions. Project management communications are also carried out through software, such as correspondence, memos, reports, and documents describing a project’s planning, organization, evaluation and control strategy, and progress. A...

  • CASE STUDY – THE RELUCTANT PROJECT TEAM JJ Okocha started a new job 6 months ago....

    CASE STUDY – THE RELUCTANT PROJECT TEAM JJ Okocha started a new job 6 months ago. His new position was project manager. At first, he had starts in his eyes about becoming the best project manager that his company had ever seen. Now he is not sure if project management is worth the effort. He made an appointment to see Phil Davies the director of project management. JJ Okocha: “Phil I am a little unhappy with the way things are...

  • Ethics in Action Chris is a project manager at a technology firm. For months he has...

    Ethics in Action Chris is a project manager at a technology firm. For months he has been working on integrating a new management software program and finally the time has arrived for all of the computers in his building to be updated. While Chris is responsible for making the software integration happen, he needs the help of Jack, the lead technical support staff, to make it happen. To ensure the transition goes as smoothly as possible, Chris needs the new...

  • Project management Zeus Project-A You are Donald Tuck, the project manager in charge of the Zeus...

    Project management Zeus Project-A You are Donald Tuck, the project manager in charge of the Zeus project. Zeus was the code name given to the development of a virtual electronic medical reference guide. Zeus would be designed for emergency medical technicians and paramedics who need a quick reference guide to use in emergency situations, even in offline mode. Donald and his project team were developing a project plan aimed at producing 30 working models in time for InterMedCON 2018, the...

  • (Use the case of “Global Treps”) You have been selected as the project manager for the Global Tre...

    (Use the case of “Global Treps”) You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths...

  • Conflict and Negotiation. Paul, 33 years of age graduated with a Master’s degree in Geology from...

    Conflict and Negotiation. Paul, 33 years of age graduated with a Master’s degree in Geology from McGill University in 2002. Since graduation he had worked for a small oil exploration company in Newfoundland. He enjoyed the work, his boss and peers but there was limited opportunity for advancement. He was recently married to a girl from Ontario and just discovered he was about to be a father. Paul decided it was time to explore new employment opportunities. A short time...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT