Question

A flooring subcontractor has to install 2,600sq ft of carpet for an existing building for unit...

A flooring subcontractor has to install 2,600sq ft of carpet for an existing building for unit cost of $2.30 per sq ft. The subcontractor was given 10 days to finish all the work. Four days after the start of the work, he found out 1,500sq ft of the carpet is installed and its actual cost was $3,150 to that date. Perform EV (earned value) analysis on the task above

Q1- What is the % complete?

Q2-What is BCWP?

Q3- What is BCWP?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans: = 2600 X 9.30 Budget cost for work scheduled (BCWS) $5980 Actual cost of work performed CAC WP) = $ 3150 Q1) Percentage

Add a comment
Know the answer?
Add Answer to:
A flooring subcontractor has to install 2,600sq ft of carpet for an existing building for unit...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A flooring subcontractor has to install 2,600sq ft of carpet for an existing building for unit...

    A flooring subcontractor has to install 2,600sq ft of carpet for an existing building for unit cost of $2.30 per sq ft. The subcontractor was given 10 days to finish all the work. Four days after the start of the work, he found out 1,500sq ft of the carpet is installed and its actual cost was $3,150 to that date. Perform EV (earned value) analysis on the task above Q1- What is the BCWS? Q2-What is the CV? Q3-What is...

  • Aflooring subcontractor has to install 2,600sq ft of carpet for an existing building for unit cost...

    Aflooring subcontractor has to install 2,600sq ft of carpet for an existing building for unit cost of $2.30 per sq ft. The subcontractor was given 10 days to finish all the work. Four days after the start of the work, he found out 1,500sqft of the carpet is installed and its actual cost was $3,150 to that date. Perform EV (earned value) analysis on the task above and answer Questions 1-11 Next → Question 1 5 pts What is the...

  • what is the % complete? what is the BCWP? what is the ACWP? what is the...

    what is the % complete? what is the BCWP? what is the ACWP? what is the BCWS? what is the CV? what is the SV? what is the CPI? what is the SPI? what is the FCV? what is the FSV? A flooring subcontractor has to install 2,600sqft of carpet for an existing building for unit cost of $2.30 per sq ft. The subcontractor was given 10 days to finish all the work. Four days after the start of the...

  • Your company was hired as a subcontractor for a client's "Destiny project and awarded two main work packages within that project. Your company refers to this project internally using the cost...

    Your company was hired as a subcontractor for a client's "Destiny project and awarded two main work packages within that project. Your company refers to this project internally using the cost code "P2 2019". You're given the table below that lists the work packages, their cost code, their budget, and their scheduled start day and end day (as agreed upon with the main contractor). The start and end days are measured in working days after the main project's start. So,...

  • can you please answer question 1 and 3 please ABC General Contractors ABC General Contractors was...

    can you please answer question 1 and 3 please ABC General Contractors ABC General Contractors was an established construction company handling small-to medium- sized commercial and industrial construction projects. Some recent projects that the company had completed were a 20,000-square-foot factory building, a four-story office building, and a water filtration plant. TELEVISION TOWER BID The company was now in the process of preparing a bid for a television station for the erection of a 225-foot-high television antenna tower and the...

  • i have the case study question with the answers but i need help to re-write the...

    i have the case study question with the answers but i need help to re-write the answers. please see the attached files Case Study Analysis (CSF3003) Assessment Description and Requirements CLO1: Case Study 1 Ahmad lef home to study master and PhD in Australia. He has fees for the first semester only. After he arrived to Sydney and settled down, he start looking for a part-time job to save money for the next term. Ahmad has some experience on making...

  • Select two of the discussion questions and analyze the case study using project management principles. Apply...

    Select two of the discussion questions and analyze the case study using project management principles. Apply your knowledge of project management to the facts presented in the case study to describe how you would proceed. We only need to answer one of the questions. A thorough answer will probably require 300 to 500 words for each question.   Feel free to use text bullets, tables, or graphics to summarize your points. Questions Q1: Make or Buy decision – Describe the make...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT