Question

Job Order Costing Beller Valley Apparel Co. uses a job order cost system. The following data summarizes the production data for the month of May 31, 2020, which is the first month of operations.

Job Order Costing

Beller Valley Apparel Co. uses a job order cost system.  The following data summarizes the production data for the month of May 31, 2020, which is the first month of operations. 

                                               image.png

1.      What is the total cost of each job? – remember to list out each job # and show the cost of direct materials, direct labour and factory overhead.

2.      What are the total job costs for the job completed in May 2020 and moved into finished goods?

3.      What is the total cost of the jobs still in work in process? 

4.      What are the total jobs costs for the jobs sold to customers?   

5.      What is the total of the job costs for the finished goods ending?

HINT:  for each of #’s 1 to 5 above, remember to list out each job # and show the cost of direct materials, direct labour and factory overhead.


1 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 9 more requests to produce the answer.

1 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
Job Order Costing Beller Valley Apparel Co. uses a job order cost system. The following data summarizes the production data for the month of May 31, 2020, which is the first month of operations.
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the...

    Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,000, direct labour $15,000, and manufacturing overhead $20,000. As of January 1, Job No. 49 had been completed at a cost of $120,000 and was part of finished goods inventory. There...

  • Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the...

    Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,000, direct labour $15,200, and manufacturing overhead $20,200. As of January 1, Job No. 49 had been completed at a cost of $120,200 and was part of finished goods inventory. There...

  • Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the...

    Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,000, direct labour $15,200, and manufacturing overhead $20,200. As of January 1, Job No. 49 had been completed at a cost of $120,200 and was part of finished goods inventory. There...

  • Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the...

    Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,600, direct labour $15,300, and manufacturing overhead $20,800. As of January 1, Job No. 49 had been completed at a cost of $120,000 and was part of finished goods inventory. There...

  • Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the...

    Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,600, direct labour $15,300, and manufacturing overhead $20,800. As of January 1, Job No. 49 had been completed at a cost of $120,000 and was part of finished goods inventory. There...

  • Question 8 Red Fire Inc. produces fire trucks. The company uses a normal job-order costing system...

    Question 8 Red Fire Inc. produces fire trucks. The company uses a normal job-order costing system to calculate its cost of goods manufactured. The company’s policy is to price its job at cost plus 30% markup. On January 1, 2020, there was only one job in process, with the following costs: Questions Red Fire Inc. produces fire trucks. The company uses a normal job-order costing system to calculate its cost of goods manufactured. The company's policy is to price its...

  • Question 8 Red Fire Inc. produces fire trucks. The company uses a normal job-order costing system...

    Question 8 Red Fire Inc. produces fire trucks. The company uses a normal job-order costing system to calculate its cost of goods manufactured. The company's policy is to price its job at cost plus 30% markup. On January 1, 2020, there was only one job in process, with the following costs: Job 200 $13,600 Direct materials Direct labour Applied overhead Total 18,000 27,000 $58,600 The following balances were taken from the company's general ledger as of January 1, 2020: Direct...

  • Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the...

    Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,600, direct labour $15,300, and manufacturing overhead $20,800. As of January 1, Job No. 49 had been completed at a cost of $120,000 and was part of finished goods inventory. There...

  • Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the...

    Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,000, direct labour $15, and manufacturing overhead $20,200. As of January 1, Job No. 49 had been completed at a cost of $120,200 and was part of finished goods inventory. There...

  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,000, direct labor $12,000, and manufacturing overhead $16,000. As of January 1, Job 49 had been completed at a cost of $90,000 and was part of finished goods inventory. There was a $15,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT