Question

Exercise 6-23 (Algo) Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Dear Student, Thanks for Using Chegg, Please find below the answer and give a thumbs up.

% of completion Completed Contract
Situation 2021 2022 2023 2021 2022 2023
1 293057 465751 251192 0 0 1010000
2 293057 -13057 280000 560000
3 293057 -585444 -297613 -590000
4 170000 1410000 0 1580000
5 170000 -170000 380000 380000
6 -22715 -181575 -455710 -660000

Working Notes:

Situation 1
2021 2022 2023
Contract Price 6800000 6800000 6800000
Actual Costs to date 1680000 4350000 5790000
Estimated costs to complete 4110000 1440000 0
Total estimated costs 5790000 5790000 5790000
Estimated Gross Profit 1010000 1010000 1010000
% of Completion 29.02% 75.13% 100.00%
Gross Profit 293057 758808 1010000
Gross profit Recognised in Previous Year 0 293057 758808
Gross profit to be recognised 293057 465751 251192
Situation 2
2021 2022 2023
Contract Price 6800000 6800000 6800000
Actual Costs to date 1680000 3120000 6240000
Estimated costs to complete 4110000 3120000 0
Total estimated costs 5790000 6240000 6240000
Estimated Gross Profit 1010000 560000 560000
% of Completion 29.02% 50.00% 100.00%
Gross Profit 293057 280000 560000
Gross profit Recognised in Previous Year 0 293057 280000
Gross profit to be recognised 293057 -13057 280000
Situation 3
2021 2022 2023
Contract Price 6800000 6800000 6800000
Actual Costs to date 1680000 4350000 7390000
Estimated costs to complete 4110000 2940000 0
Total estimated costs 5790000 7290000 7390000
Estimated Gross Profit 1010000 -490000 -590000
% of Completion 29.02% 59.67% 100.00%
Gross Profit 293057 -292387 -590000
Gross profit Recognised in Previous Year 0 293057 -292387
Gross profit to be recognised 293057 -585444 -297613
Situation 4
2021 2022 2023
Contract Price 6800000 6800000 6800000
Actual Costs to date 680000 3860000 5220000
Estimated costs to complete 4760000 965000 0
Total estimated costs 5440000 4825000 5220000
Estimated Gross Profit 1360000 1975000 1580000
% of Completion 12.50% 80.00% 100.00%
Gross Profit 170000 1580000 1580000
Gross profit Recognised in Previous Year 0 170000 1580000
Gross profit to be recognised 170000 1410000 0
Situation 5
2021 2022 2023
Contract Price 6800000 6800000 6800000
Actual Costs to date 680000 3860000 6420000
Estimated costs to complete 4760000 2940000 0
Total estimated costs 5440000 6800000 6420000
Estimated Gross Profit 1360000 0 380000
% of Completion 12.50% 56.76% 100.00%
Gross Profit 170000 0 380000
Gross profit Recognised in Previous Year 0 170000 0
Gross profit to be recognised 170000 -170000 380000
Situation 6
2021 2022 2023
Contract Price 6800000 6800000 6800000
Actual Costs to date 680000 3860000 7460000
Estimated costs to complete 6355000 3320000 0
Total estimated costs 7035000 7180000 7460000
Estimated Gross Profit -235000 -380000 -660000
% of Completion 9.67% 53.76% 100.00%
Gross Profit -22715 -204290 -660000
Gross profit Recognised in Previous Year 0 -22715 -204290
Gross profit to be recognised -22715 -181575 -455710
Add a comment
Know the answer?
Add Answer to:
Exercise 6-23 (Algo) Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 6-23 (Algo) Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion...

    Exercise 6-23 (Algo) Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO6-9] Brady Construction Company contracted to build an apartment complex for a price of $6,200,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Situation 1 2 3 4 5 6 Costs Incurred During Year 2021 2022 2023...

  • Exercise 6-23 (Static) Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion...

    Exercise 6-23 (Static) Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion [LO6-9] Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Situation 1 2 3 4 Costs Incurred During Year 2021 2022 2023 1,500 2,100...

  • Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion [LO5-9]...

    Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion [LO5-9] Brady Construction Company contracted to build an apartment complex for a price of $6,200,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars Estimated Costs to Complete (As of the End of the Year) Costs Incurred During Year...

  • Exercise 6-20 (Algo) Long-term contract; revenue recognition over time vs. upon project completion [LO6-9] On June...

    Exercise 6-20 (Algo) Long-term contract; revenue recognition over time vs. upon project completion [LO6-9] On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $390 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated...

  • Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project [LO6-9] On...

    Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project [LO6-9] On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000...

  • Exercise 6-22 (Algo) Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO6-8,...

    Exercise 6-22 (Algo) Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO6-8, 6-9] On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2021, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2022, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2022 billings...

  • Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9)...

    Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs Incurred During Year Situation 2018 2019 2020 1 1,630 2,520 1,290 2 1,630 1,290...

  • Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9)...

    Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs incurred During Year Situation 2018 2019 2020 1 1,630 2,520 1,290 2 1630 1,290...

  • 5-HW O Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project...

    5-HW O Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Year Estimated costs to Complete Costs incurred During (As of the End of...

  • Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project [LO6-9] On...

    Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project [LO6-9] On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2,130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2,630,000 with remaining costs estimated to be $3,795,000. 2022 billings were $2,880,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT