Wayne Company begins operations on April 1. Information from job cost sheets shows the following.
Manufacturing Costs Assigned |
||||||||
Job |
|
|
|
Month |
||||
10 | $7,100 | $6,400 | May | |||||
11 | 5,900 | 5,900 | $3,300 | June | ||||
12 | 1,500 | April | ||||||
13 | 6,500 | 6,100 | June | |||||
14 | 6,800 | 4,000 | Not complete |
Job 12 was completed in April. Job 10 was completed in May. Jobs 11
and 13 were completed in June. Each job was sold for 25% above its
cost in the month following completion.
(a) What is the balance in Work in Process Inventory at the end of each month?
(b) What is the balance in Finished Goods Inventory at the end of each month?
(c) What is the gross profit for May, June and July?
Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks! |
Wayne | |||
Compilation of data | April | May | June |
Job 10 | 7,100.00 | 6,400.00 | - |
Job 11 | 5,900.00 | 5,900.00 | 3,300.00 |
Job 12 | 1,500.00 | - | - |
Job 13 | - | 6,500.00 | 6,100.00 |
Job 14 | - | 6,800.00 | 4,000.00 |
Answer a | April | May | June |
Job 10 | 7,100.00 | - | - |
Job 11 | 5,900.00 | 11,800.00 | - |
Job 12 | - | - | - |
Job 13 | - | 6,500.00 | |
Job 14 | - | 6,800.00 | 10,800.00 |
Work in Process Inventory | 13,000.00 | 25,100.00 | 10,800.00 |
Answer b | April | May | June |
Job 10 | - | 13,500.00 | - |
Job 11 | - | - | 15,100.00 |
Job 12 | 1,500.00 | - | - |
Job 13 | - | - | 12,600.00 |
Job 14 | - | - | - |
Finished Goods Inventory | 1,500.00 | 13,500.00 | 27,700.00 |
Answer c | May | June | July |
Job 10 | - | 13,500.00 | - |
Job 11 | - | - | 15,100.00 |
Job 12 | 1,500.00 | - | - |
Job 13 | - | - | 12,600.00 |
Job 14 | - | - | - |
Cost of Job | 1,500.00 | 13,500.00 | 27,700.00 |
Markup at 25% | 375.00 | 3,375.00 | 6,925.00 |
Gross Profit | 375.00 | 3,375.00 | 6,925.00 |
Wayne Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing...
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Number April May June Month Completed 10 $7,100 $6,400 May 11 5,900 5,900 $3,300 June 12 1,500 April 13 6,500 6,100 June 14 6,800 4,000 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion....
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Number April May June Month Completed 10 $6,300 $6,400 May 11 6,100 5,600 $3,200 June 12 1,900 April 13 6,500 6,100 June 14 6,800 4,600 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion....
Sheffield Company begins operations on April 1. Information from job cost sheets shows the following. Job Number © April $6,100 5,900 1,400 Manufacturing Costs Assigned Month May June Completed $6,200 May 5,800 $3,800 June April 5,100 5,600 June 6,800 4,600 Not complete NM + Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion. What is...
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Number Month Completed April May June $5,500 6,100 1,600 $5,400 4,100 $3,500 May June April June Not complete 6,400 6,300 4,600 4,200 Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion. What is the balance in...
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Number April May June Completed 10 $5,200 $4,400 May 11 4,100 3,900 $2,000 June 12 1,200 April 13 4,700 4,500 June 14 5,900 3,600 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion. Instructions...
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Job Number 10 April $5,700 5,800 1,500 Manufacturing Costs Assigned Month May June Completed $5,900 May 5,400 $3,000 June April 4,900 5,300 June 7,000 3.700 Not complete 11 12 13 14 Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion....
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Month Number April Complet May June $5,300 $4,800 May 10 6,100 4,900 $2,200 June 11 2,300 12 April 13 5,100 5,000 June 6,800 4,600 Not comp 14 Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion....
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Job Number 10 Manufacturing Costs Assigned Month April May June Completed $7,100 $4,900 May 4,300 5,100 $2,200 June 2,200 April 6,600 5,700 June 6,200 4,700 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion. (a) - Your answer...
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Month Number April MayJune Completed 10 $6,800 $5,000 11 6,000 5,300 $ 2.600 June 12 13 14 May 2,300 April 5,300 5,600 June 6,600 4,600 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion....
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Number April May June Month Completed 10 $ 5,700 $ 4,600 May 11 5,600 4,100 $ 2,200 June 12 1,700 April 13 4,900 5,200 June 14 6,400 4,300 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the...