Question

Check my work mode : This shows what is correct or incorrect for the work you have completed so far. It does not indicate com

1. what were the company's Predetermined OH rate in the Molding and fabrication department?

2. how much MOH was applied from the Molding Department to job P and how much was applied to job Q?

3. How much MOH was applied from the fabrication department to Job P and how much was applied to Job Q?

4. What was the total MOH cost assigned to Job P?

5. If Job P included 20 units, what was its unit product cost?

6. What was the total manufacturing cost assigned to Job Q?

7. If Job Q included 30 units, what was its unit product cost?

8. Assume that Sweeten Company used cost-plus pricing (and a markup percentage 80% of total of total manufacturing cost) to establish selling prices for all of its jobs. what selling price would the company have established for Jobs P and Q? What are the selling prices for both jobs when stated on a per unit basis?

9. What was Sweeten Company's COGS for March?

10. What was the Company's Plantwide POH rate?

11. How much MOH was applied to Job P and how much was applied to job Q?

12. If Job P included 20 units, what was its unit product cost?

13. If Job Q included 30 units, what was its unit product cost?

14. Assume that Sweeten Company used cost-plus pricing ( and a markup percentage of 80% of total Manufacturing cost) to establish selling prices for all of its jobs. What selling price would the company have established for Jobs P and Q? What are the selling rpices for both jobs when stated on a per unit basis?

15. What was Sweeten Company's COGS for March?

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks!
Sweeten
Answer 1 Molding Fabrication Note
Machine Hours        2,500.00        1,500.00 A
Fixed Manufacturing overhead      10,250.00      15,150.00 B
Fixed Manufacturing overhead rate                4.10              10.10 C=B/A
Variable OH Rate                1.50                2.30 D
Departmental predetermined OH Rate                5.60              12.40 E=C+D
Answer 2 Job P Job Q
Machine hours used- Molding        1,800.00            900.00 F
Departmental predetermined OH Rate                5.60                5.60 See E
Overhead applied     10,080.00        5,040.00 G=F*E
Answer 3 Job P Job Q
Machine hours used- Fabrication           700.00        1,000.00 H
Departmental predetermined OH Rate             12.40              12.40 See E
Overhead applied        8,680.00      12,400.00 I=H*E
Answer 4 Amount $ Note
Overhead applied- Molding      10,080.00 See G
Overhead applied- Fabrication        8,680.00 See I
Overhead applied to Job P     18,760.00 J
Answer 5 Amount $ Note
Direct Materials      14,000.00
Direct Labor      21,800.00
Overhead applied      18,760.00 See J
Manufacturing cost assigned to Job P     54,560.00 K
Number of units             20.00 L
Unit product cost for Job P        2,728.00 M=K/L
Answer 6 Amount $
Direct Materials        8,500.00
Direct Labor        7,900.00
Overhead applied- Molding        5,040.00 See G
Overhead applied- Fabrication      12,400.00 See I
Manufacturing cost assigned to Job Q     33,840.00 N
Answer 7 Amount $
Manufacturing cost assigned to Job Q      33,840.00 See N
Number of units             30.00 O
Unit product cost for Job Q        1,128.00 P=N/O
Answer 8 Job P Job Q Note
Manufacturing cost assigned      54,560.00      33,840.00 Q= See K, N
Markup at 80%      43,648.00      27,072.00 R=Q*80%
Selling price     98,208.00      60,912.00 S=Q+R
Number of units             20.00              30.00 T
Selling price per unit        4,910.40        2,030.40 U=S/T
Answer 9 Amount $ Note
Manufacturing cost assigned to Job P      54,560.00 See K
Manufacturing cost assigned to Job Q      33,840.00 See N
Cost of good sold     88,400.00
Answer 10
Plant wide predetermined OH Rate Molding Fabrication Total Note
Machine Hours        2,500.00        1,500.00                4,000.00 See A
Variable OH Rate                1.50                2.30 See D
Variable OH cost        3,750.00        3,450.00                7,200.00 V=A*D
Fixed Manufacturing overhead      10,250.00      15,150.00              25,400.00 See B
Total OH              32,600.00 W=V+B
Plant wide predetermined OH Rate                        8.15 X=W/A
Answer 11 Job P Job Q Note
Actual Machine hours        2,500.00        1,900.00 Y
Plant wide predetermined OH Rate                8.15                8.15 See X
Overhead applied     20,375.00      15,485.00 Z=Y*X
Answer 12
Know the answer?
Add Answer to:
1. what were the company's Predetermined OH rate in the Molding and fabrication department? 2. how...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 9. What were the company’s predetermined overhead rates in the Molding Department and the Fabrication Department?...

    9. What were the company’s predetermined overhead rates in the Molding Department and the Fabrication Department? 10. How much manufacturing overhead was applied from the Molding Department to Job P and how much was applied to Job Q? 11. How much manufacturing overhead was applied from the Fabrication Department to Job P and how much was applied to Job Q? 12. If Job P included 20 units, what was its unit product cost? 13. If Job Q included 30 units,...

  • 1. What were the company’s predetermined overhead rates in the Molding Department and the Fabrication Department?...

    1. What were the company’s predetermined overhead rates in the Molding Department and the Fabrication Department? (Round your answers to 2 decimal places.) 2. How much manufacturing overhead was applied from the Molding Department to Job P and how much was applied to Job Q? (Do not round intermediate calculations.) 3. How much manufacturing overhead was applied from the Fabrication Department to Job P and how much was applied to Job Q? (Do not round intermediate calculations.) 4. What was...

  • 1.What were the company’s predetermined overhead rates in the Molding Department and the Fabrication Department? (Round...

    1.What were the company’s predetermined overhead rates in the Molding Department and the Fabrication Department? (Round your answers to 2 decimal places.) 2.How much manufacturing overhead was applied from the Molding Department to Job P and how much was applied to Job Q? (Do not round intermediate calculations.) 3. How much manufacturing overhead was applied from the Fabrication Department to Job P and how much was applied to Job Q? (Do not round intermediate calculations.) 4. What was the total...

  • 1. what was the company's plant wide predetermined overhead rate? 2. How much manufacturing overhead was...

    1. what was the company's plant wide predetermined overhead rate? 2. How much manufacturing overhead was applied to Job P and how much was applied to Job Q? 3. What was the total manufacturing cost assigned to Job P? 4. If Job P included 20 units, what was its unit product cost? 5. What was the total manufacturing cost assigned to Job Q? 6. If Job Q included 30 units, what was its unit product cost? 7. Assume that Sweeten...

  • 9. What were the company’s predetermined overhead rates in the Molding Department and the Fabrication Department?...

    9. What were the company’s predetermined overhead rates in the Molding Department and the Fabrication Department? (Round your answers to 2 decimal places.) 10. How much manufacturing overhead was applied from the Molding Department to Job P and how much was applied to Job Q? (Do not round intermediate calculations.) 11. How much manufacturing overhead was applied from the Fabrication Department to Job P and how much was applied to Job Q? (Do not round intermediate calculations.) 12. If Job...

  • 9. What were the company’s predetermined overhead rates in the Molding Department and the Fabrication Department?...

    9. What were the company’s predetermined overhead rates in the Molding Department and the Fabrication Department? (Round your answers to 2 decimal places.) 10. How much manufacturing overhead was applied from the Molding Department to Job P and how much was applied to Job Q? (Do not round intermediate calculations.) 11. How much manufacturing overhead was applied from the Fabrication Department to Job P and how much was applied to Job Q? (Do not round intermediate calculations.) 12. If Job...

  • Questions: 1. What was the company’s plantwide predetermined overhead rate? 2. How much manufacturing overhead was...

    Questions: 1. What was the company’s plantwide predetermined overhead rate? 2. How much manufacturing overhead was applied to Job P and how much was applied to Job Q? 3. What was the total manufacturing cost assigned to Job P? 4. If Job P included 20 units, what was its unit product cost? 5. What was the total manufacturing cost assigned to Job Q? 6. If Job Q included 30 units, what was its unit product cost? 7. Assume that Sweeten...

  • please help me. thank you. please help Check my work mode : This shows what is...

    please help me. thank you. please help Check my work mode : This shows what is correct or incorrect for the work you have completed so far. It does not indicate comp Required information [The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT