Question

Holliston Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at capacity. Under its cDetermine the formula to calculate the ST cost per test-hour and enter the amounts to calculate the rate. (Round the rate toTotal test-hours o Total test-hours (4) O O HT test-hours O Total HT costs Total overhead costs (5) O O ST test-hours Total o

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.

Cost Item Cost-type
a Direct Labor Output unit-level
b Equipment-related costs (rent, maintenance, energy, etc) Output unit-level
c Setup costs Batch-level
d Costs of designing tests Service-sustaining

Explanation:

Output unit -level costs:

a. Direct labor costs, $418,000. These costs can be directly traced to HT, $360,000 and ST, $58,000.

b. Equipment related costs (rent, maintenance, energy and so on), $340,000. These costs are allocated to HT and ST on the basis of test-hours.

These are classified as output unit-level costs because they ar incurred on each unit of materials tested, that is, specifically for every hour of testing.

Batch-level costs:

c. Setup costs, $396,00. These costs are allocated to HT and ST on the basis of the number of setup-hours required. HT requires 11,500 setup-hours and ST requirs 5,000 setups-hours.

These are classified as batch-level costs as they are incurred each time a batch of materials is set up for HT or ST, irrespective of the number of hours for which tests are subsequently run.

Service-sustaining costs:

d. Costs of designing tests, $270,000. These costs are allocated to HT and ST on the basis of the time required for designing the tests. HT requires 2,500 hours and ST requires 2,500 hours.

These are classified as Service-sustaining costs, as they are incurred to design HT and ST tests, irrespective of number of batches tested or number of hours of test time.

2.

Heat Testing Stress Testing
Total (1) Per hour (2) = (1)/ 60,000 Total (3) Per hour (4) = (3)/ 25,000
Direct labor costs (given) 360000 6 58000 2.32
Equipment-related costs
$4 per hour * 60,000 240000 4
$4 per hour * 25,000 100000 4
Setup costs
$24 per setup-hour * 11,500 setup hours 276000 4.6
$24 per setup-hour * 5000 setup hours 120000 4.8
Cost of designing tests
$54 per hour * 2500 hours 135000 2.25
$54 per hour * 2500 hours 135000 5.4
Total Costs 1011000 16.85 413000 16.52
Equipment-related costs 340000
Test hours 85000
per hour cost 4
setup cost 396000
setup -hours 16500
Per hour setup cost 24
Cost of designing tests 270000
designing tests hours 5000
per hour designing cost 54

At a cost per test-hour of $15, the simple costing system under costs heat testing ($16.85) and over costs stress testing ($11.12). The reason is that HT uses direct labor, setup and design resources per hour more intensively than ST. Heat tests are complex, tasks long time to setup and more tough to design. The simple costing system assumes that testing costs per hour are the same for HT and ST.

3. As seen above, HT incurs more costs than ST does. Charging costs under simple costing pushes up the cost of ST and leads to overcharging when it doesn't actually incur as much. ABC costing on the other hand charges amounts based on the actual usage. It gives a fairer allocation of costs. It is more complex than traditional method of simple costing, but more accurate. It considers the actual hours used by the test for setup, design, labor and equipment related activities and allocates costs based on these cost drivers which are a more accurate basis for allocation than total test hours of each tests.

The ABC system captures the resources needed for HT and ST in the best way as it identifies all the activities undertaken, when performing the test and recognize the levels of cost hierarchy at which costs differ. So, the ABC system produce more correct product costs. Hopinkton's management can use the information from the ABC system to make better pricing and product mix decisions.  

Add a comment
Know the answer?
Add Answer to:
Holliston Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Hopkinton Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at...

    Hopkinton Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at capacity. Under its current simple costing system, Hopkinton aggregates all operating costs of $1,200,000 into a single overhead cost pool. Hopkinton calculates a rate per test-hour of $16 ($1,200,000/75,000 total test-hours). HT uses 50,000 test-hours, and ST uses 25,000 test-hours. Gary O'Loughlin, Hopkinton's controller, believes that there is enough variation in test procedures and cost structures to establish separate costing and billing rates for...

  • Vineyard Test Laboratories does heat testing​ (HT) and stress testing​ (ST) on materials and operates at...

    Vineyard Test Laboratories does heat testing​ (HT) and stress testing​ (ST) on materials and operates at capacity. Under its current simple costing​ system, Vineyard aggregates all operating costs of $ 1 comma 190 comma 000 into a single overhead cost pool. Vineyard calculates a rate per​ test-hour of $ 17 ​($ 1 comma 190 comma 000 ​/ 70 comma 000 total​ test-hours). HT uses 40 comma 000 ​test-hours, and ST uses 30 comma 000 ​test-hours. Gary Maloney​, Vineyard​'s ​controller, believes...

  • Hopkinton Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at...

    Hopkinton Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at capacity. Under its current simple costing system, Hopkinton aggregates all operating costs of $1,200,000 into a single overhead cost pool. Hopkinton calculates a rate per test-hour of $16 ($1,200,000 / 75,000 total test-hours). HT uses 50,000 test-hours, and ST uses 25,000 test-hours. Gary Mahoney, Hopkinton's controller, believes that there is enough variation in test procedures and cost structures to establish separate costing and billing...

  • Hopkinton Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at...

    Hopkinton Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at capacity. Under its current simple frosting system. Hopkinton aggregates all operating costs of $1,300,000 into a single overhead cost pool. Hopkinton calculates a rate per two-hour of $13 (1,300,000/100,000 total test hours). HT uses 60,000 test hours, and ST uses 40,000 test hours. Gary O'Laughlin, Hopkinton's controller, believes that there is enough variation in test procedures and cost structures to establish separate costing and...

  • Milton Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at...

    Milton Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at capacity. Under its current simple costing system, Milton aggregates all operating costs of $1,360,000 into a single overhead cost pool. Milton calculates a rate per test-hour of $16 ($1,360,000 / 85,000 total test-hours). HT uses 55,000 test-hours, and ST uses 30,000 test-hours. Gary Daley, Milton's controller, believes that there is enough variation in test procedures and cost structures to establish separate costing and billing...

  • Hopkinton Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at...

    Hopkinton Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at capacity. Under its current simple costing system, Hopkinton aggregates all operating costs of $1,300,000 into a single overhead cost pool. Hopkinton calculates a rate per test-hour of S13 ($1,300,000 / 100,000 total test-hours). HT uses 60,000 test-hours, and ST uses 40,000 test-hours. Gary Celeste, Hopkinton's controller, believes that there is enough variation in test procedures and cost structures to establish separate costing and billing...

  • Ayer Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at...

    Ayer Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at capacity. Under its current simple costing system, Ayer aggregates all operating costs of $1,360,000 i 55,000 test-hours, and ST uses 30,000 test-hours. Gary Celeste, Ayer's controller, believes that there is enough variation in test procedures and cost structures to establish separate costing and billing mispricing of its services could cause Ayer to lose business. Celeste divides Ayer's costs into four activity-cost categories. (Click the...

  • Milton Test Laboratories does heat testing​(HT) and stress testing​ (ST) on materials and operates at capacity....

    Milton Test Laboratories does heat testing​(HT) and stress testing​ (ST) on materials and operates at capacity. Under its current simple costing​system, Milton aggregates all operating costs of $1,330,000 into a single overhead cost pool. Milton calculates a rate per​test-hour of $14 ($1,330,000 / 95,000 total test-hours). HT uses 63,000 test-hours, and ST uses 32,000 test-hours. Gary Savarese, Milton’s controller, believes that there is enough variation in test procedures and cost structures to establish separate costing and billing rates for HT...

  • %E5-19 (similar Vineyard Test Laboratories does heat testing (HT) and stress testing (ST) on materials and...

    %E5-19 (similar Vineyard Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at capacity. Under its current simple costing system, Vineyard aggregates all operating costs of $1,330,000 into a single overhead cost pool. Vineyard calculates a rate per test-hour of $14 (51,330,000/ 95,000 total test hours). HT uses 63.000 test-hours, and ST uses 32,000 test-hours. Gary Celeste, Vineyard's controller, believes that there is enough variation in test procedures and cost structures to establish separate costing...

  • Need help on this question! Hull Test Laboratories does heat testing (HT) and stress testing (ST)...

    Need help on this question! Hull Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at capacity. Under its current simple costing system, Hull aggregates all operating costs of $1,260,000 into a single overhead cost pool. Hull calculates a rate per test-hour of $14 ($1,260,000 / 90,000 total test-hours). HT uses 50,000 test-hours, and ST uses 40,000 test-hours. Gary O'Loughlin, Hull's controller, believes that there is enough variation in test procedures and cost structures to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT