1.
Cost Item | Cost-type | |
a | Direct Labor | Output unit-level |
b | Equipment-related costs (rent, maintenance, energy, etc) | Output unit-level |
c | Setup costs | Batch-level |
d | Costs of designing tests | Service-sustaining |
Explanation:
Output unit -level costs:
a. Direct labor costs, $418,000. These costs can be directly traced to HT, $360,000 and ST, $58,000.
b. Equipment related costs (rent, maintenance, energy and so on), $340,000. These costs are allocated to HT and ST on the basis of test-hours.
These are classified as output unit-level costs because they ar incurred on each unit of materials tested, that is, specifically for every hour of testing.
Batch-level costs:
c. Setup costs, $396,00. These costs are allocated to HT and ST on the basis of the number of setup-hours required. HT requires 11,500 setup-hours and ST requirs 5,000 setups-hours.
These are classified as batch-level costs as they are incurred each time a batch of materials is set up for HT or ST, irrespective of the number of hours for which tests are subsequently run.
Service-sustaining costs:
d. Costs of designing tests, $270,000. These costs are allocated to HT and ST on the basis of the time required for designing the tests. HT requires 2,500 hours and ST requires 2,500 hours.
These are classified as Service-sustaining costs, as they are incurred to design HT and ST tests, irrespective of number of batches tested or number of hours of test time.
2.
Heat Testing | Stress Testing | |||
Total (1) | Per hour (2) = (1)/ 60,000 | Total (3) | Per hour (4) = (3)/ 25,000 | |
Direct labor costs (given) | 360000 | 6 | 58000 | 2.32 |
Equipment-related costs | ||||
$4 per hour * 60,000 | 240000 | 4 | ||
$4 per hour * 25,000 | 100000 | 4 | ||
Setup costs | ||||
$24 per setup-hour * 11,500 setup hours | 276000 | 4.6 | ||
$24 per setup-hour * 5000 setup hours | 120000 | 4.8 | ||
Cost of designing tests | ||||
$54 per hour * 2500 hours | 135000 | 2.25 | ||
$54 per hour * 2500 hours | 135000 | 5.4 | ||
Total Costs | 1011000 | 16.85 | 413000 | 16.52 |
Equipment-related costs | 340000 |
Test hours | 85000 |
per hour cost | 4 |
setup cost | 396000 |
setup -hours | 16500 |
Per hour setup cost | 24 |
Cost of designing tests | 270000 |
designing tests hours | 5000 |
per hour designing cost | 54 |
At a cost per test-hour of $15, the simple costing system under costs heat testing ($16.85) and over costs stress testing ($11.12). The reason is that HT uses direct labor, setup and design resources per hour more intensively than ST. Heat tests are complex, tasks long time to setup and more tough to design. The simple costing system assumes that testing costs per hour are the same for HT and ST.
3. As seen above, HT incurs more costs than ST does. Charging costs under simple costing pushes up the cost of ST and leads to overcharging when it doesn't actually incur as much. ABC costing on the other hand charges amounts based on the actual usage. It gives a fairer allocation of costs. It is more complex than traditional method of simple costing, but more accurate. It considers the actual hours used by the test for setup, design, labor and equipment related activities and allocates costs based on these cost drivers which are a more accurate basis for allocation than total test hours of each tests.
The ABC system captures the resources needed for HT and ST in the best way as it identifies all the activities undertaken, when performing the test and recognize the levels of cost hierarchy at which costs differ. So, the ABC system produce more correct product costs. Hopinkton's management can use the information from the ABC system to make better pricing and product mix decisions.
Holliston Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at...
Hopkinton Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at capacity. Under its current simple costing system, Hopkinton aggregates all operating costs of $1,200,000 into a single overhead cost pool. Hopkinton calculates a rate per test-hour of $16 ($1,200,000/75,000 total test-hours). HT uses 50,000 test-hours, and ST uses 25,000 test-hours. Gary O'Loughlin, Hopkinton's controller, believes that there is enough variation in test procedures and cost structures to establish separate costing and billing rates for...
Vineyard Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at capacity. Under its current simple costing system, Vineyard aggregates all operating costs of $ 1 comma 190 comma 000 into a single overhead cost pool. Vineyard calculates a rate per test-hour of $ 17 ($ 1 comma 190 comma 000 / 70 comma 000 total test-hours). HT uses 40 comma 000 test-hours, and ST uses 30 comma 000 test-hours. Gary Maloney, Vineyard's controller, believes...
Hopkinton Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at capacity. Under its current simple costing system, Hopkinton aggregates all operating costs of $1,200,000 into a single overhead cost pool. Hopkinton calculates a rate per test-hour of $16 ($1,200,000 / 75,000 total test-hours). HT uses 50,000 test-hours, and ST uses 25,000 test-hours. Gary Mahoney, Hopkinton's controller, believes that there is enough variation in test procedures and cost structures to establish separate costing and billing...
Hopkinton Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at capacity. Under its current simple frosting system. Hopkinton aggregates all operating costs of $1,300,000 into a single overhead cost pool. Hopkinton calculates a rate per two-hour of $13 (1,300,000/100,000 total test hours). HT uses 60,000 test hours, and ST uses 40,000 test hours. Gary O'Laughlin, Hopkinton's controller, believes that there is enough variation in test procedures and cost structures to establish separate costing and...
Milton Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at capacity. Under its current simple costing system, Milton aggregates all operating costs of $1,360,000 into a single overhead cost pool. Milton calculates a rate per test-hour of $16 ($1,360,000 / 85,000 total test-hours). HT uses 55,000 test-hours, and ST uses 30,000 test-hours. Gary Daley, Milton's controller, believes that there is enough variation in test procedures and cost structures to establish separate costing and billing...
Hopkinton Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at capacity. Under its current simple costing system, Hopkinton aggregates all operating costs of $1,300,000 into a single overhead cost pool. Hopkinton calculates a rate per test-hour of S13 ($1,300,000 / 100,000 total test-hours). HT uses 60,000 test-hours, and ST uses 40,000 test-hours. Gary Celeste, Hopkinton's controller, believes that there is enough variation in test procedures and cost structures to establish separate costing and billing...
Ayer Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at capacity. Under its current simple costing system, Ayer aggregates all operating costs of $1,360,000 i 55,000 test-hours, and ST uses 30,000 test-hours. Gary Celeste, Ayer's controller, believes that there is enough variation in test procedures and cost structures to establish separate costing and billing mispricing of its services could cause Ayer to lose business. Celeste divides Ayer's costs into four activity-cost categories. (Click the...
Milton Test Laboratories does heat testing(HT) and stress testing (ST) on materials and operates at capacity. Under its current simple costingsystem, Milton aggregates all operating costs of $1,330,000 into a single overhead cost pool. Milton calculates a rate pertest-hour of $14 ($1,330,000 / 95,000 total test-hours). HT uses 63,000 test-hours, and ST uses 32,000 test-hours. Gary Savarese, Milton’s controller, believes that there is enough variation in test procedures and cost structures to establish separate costing and billing rates for HT...
%E5-19 (similar Vineyard Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at capacity. Under its current simple costing system, Vineyard aggregates all operating costs of $1,330,000 into a single overhead cost pool. Vineyard calculates a rate per test-hour of $14 (51,330,000/ 95,000 total test hours). HT uses 63.000 test-hours, and ST uses 32,000 test-hours. Gary Celeste, Vineyard's controller, believes that there is enough variation in test procedures and cost structures to establish separate costing...
Need help on this question! Hull Test Laboratories does heat testing (HT) and stress testing (ST) on materials and operates at capacity. Under its current simple costing system, Hull aggregates all operating costs of $1,260,000 into a single overhead cost pool. Hull calculates a rate per test-hour of $14 ($1,260,000 / 90,000 total test-hours). HT uses 50,000 test-hours, and ST uses 40,000 test-hours. Gary O'Loughlin, Hull's controller, believes that there is enough variation in test procedures and cost structures to...