Question

3. A production system requires four machines with the following productivity and layout:

A production system requires four machines with the following productivity and layout: 20 units/hr 18 units/ hr. В 15 units/

With the current system how long would it take to produce 300 units?

12 hours

20 hours

2 days 4 hours

5 days

0 0
Add a comment Improve this question Transcribed image text
Answer #1

20 hours

The overall capacity of the system would be = 15 units/hr

As, this is the capacity of the bottleneck process and is the lowest individual capacity.

Therefore in order to process 15 units, the time taken is 1 hour

In order to process 300 units, the time taken would be = (1/15)*300

= 20 hours

Add a comment
Know the answer?
Add Answer to:
3. A production system requires four machines with the following productivity and layout: With the current...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Continuous Flow vs. Departmental Manufacturing Gumbrecht Company has the following departmental manufacturing layout for one of...

    Continuous Flow vs. Departmental Manufacturing Gumbrecht Company has the following departmental manufacturing layout for one of its plants: 12 minutes 6 minutes Wait time - 10 minutes Move and wait time - 15 minutes Casting Grinding Move and wait time - 25 minutes 10 minutes 2 minutes Move and wait time - 20 minutes Drilling Finishing A consulting firm has recommended a value stream with the following manufacturing cell: 6 minutes 12 minutes Grinding Casting Drilling Finishing 10 minutes 2...

  • Dunder Mifflin Company has the following departmental manufacturing layout for one of its plants: Wait time...

    Dunder Mifflin Company has the following departmental manufacturing layout for one of its plants: Wait time – 10 minutes ------ Casting 12minutes Move and wait time – 15 minutes -------Grinding 6 minutes Move and wait time – 25 minutes ------- Drilling 10 minutes Move and wait time – 20 minutes -------Finishing 2 minutes A consulting firm has recommended a value stream with the following manufacturing cell: Casting 12 minutes ---- Grinding 6 minutes -----Drilling 10 minutes ----- Finishing 2 minutes...

  • Continuous Flow vs. Departmental Manufacturing Gumbrecht Company has the following departmental manufacturing layout for one of...

    Continuous Flow vs. Departmental Manufacturing Gumbrecht Company has the following departmental manufacturing layout for one of its plants: 12 minutes 6 minutes Wait time - 10 minutes Move and wait time - 15 minutes Casting Grinding Move and wait time - 25 minutes 10 minutes 2 minutes Move and wait time - 20 minutes Drilling Finishing A consulting firm has recommended a value stream with the following manufacturing cell: 6 minutes 12 minutes Grinding Casting Drilling Finishing 10 minutes 2...

  • Question 3. A hypothetical economy produces only four types of goods domestically; food, clothing, housing, machines....

    Question 3. A hypothetical economy produces only four types of goods domestically; food, clothing, housing, machines. The quantities produced and their respective prices are shown below for two different years, namely 2000 (base year) and 2002 (current year) Q(2000) P(2000) Q(2002) P(2002) Food 12 10 15 11 Clothing 15 15 18 18 Housing 14 20 20 28 Machines 20 25 25 28 A. Calculate the inflation rate over the period 2000-2002 based on the CPI measures of the price level....

  • 15. What is the production system that normally requires the most inventory of raw material items? A. Make-to-order B....

    15. What is the production system that normally requires the most inventory of raw material items? A. Make-to-order B. Assemble-to-order C. Engineer-to-order D. Make-to-stock 16. Inside the demand time fence, which of the following is true? A. It is easy to change the master production schedule (MPS) B. Available-to-promise (ATP) calculations ignore customer orders and forecast C. New customer orders can only occasionally be accepted D. Marketing and logistics people could make any changes 17. The expected demand in October...

  • What is the process time of the system? b) What is the bottleneck time of this...

    What is the process time of the system? b) What is the bottleneck time of this work cell? c)What is the process cycle time? d) If the firm operates 10 hours per day, 5 days per week, what is the weekly capacity of this work cell? The three-station work cell illustrated in the figure below has a product that must go through one of the two machines at station 1 (they are parallel) before proceeding to station 2. o Capacity:...

  • Fixit, Inc. operates 20 injection molding machines in the production of tool boxes of four different...

    Fixit, Inc. operates 20 injection molding machines in the production of tool boxes of four different sizes, named the Apprentice, the Handyman, the Journeyman, and the Professional. Classify each of the following costs as unit-level, batch-level, product-level, or facility-level. Level (a) (b) Activity Cost First-shift supervisor's salary, Powdered raw plastic Dies for casting plastic components. Depreciation on injection molding machines (assume units-of-activity depreciation), Changing dies on machines. Ic (d) le) Moving components to assembly department. Engineering design

  • QUESTION 23 Current challenges in operations Management include all of the following EXCEPT: lean operations increased...

    QUESTION 23 Current challenges in operations Management include all of the following EXCEPT: lean operations increased communication cost. rapid product development. sustainability mass customization how many hours would the plant have to work to produce 1000 parts? QUESTION 24 A small metal shop operates 10 hours each day, producing 100 parts/hour. If productivity were increased 20 between 9 and 10 hours between 2 and 6 hours less than 2 hours between 6 and 8 hours between 8 and 9 hours...

  • Case Problem 2 - PRODUCTION STRATEGY Better Fitness, Inc

    Case Problem 2 - PRODUCTION STRATEGYBetter Fitness, Inc. (BFI), manufactures exercise equipment at its plant in Freeport, Long Island. It recently designed two universal weight machines for the home exercise market. Both machines use BFI-patented technology that provides the user with an extremely wide range of motion capability for each type of exercise performed. Until now, such capabilities have been available only on expensive weight machines used primarily by physical therapist.At a recent trade show, demonstration of the machines resulted...

  • A company has five machines (1 lathe, 2 mills and 2 drills) arranged sequentially to produce a batch of 200 parts. The following table lists the setup and work cycle times per piece for the five...

    A company has five machines (1 lathe, 2 mills and 2 drills) arranged sequentially to produce a batch of 200 parts. The following table lists the setup and work cycle times per piece for the five machines. 1. Delay hr) 10 10 10 10 10 Machine Setup time (hr. 2.50 1.25 1.50 0.50 0.75 (min) 15 27 12 1. Lathe 2. Milling (V) 3. Milling (H) 4. Drill (i) 5. Drill (ii) Management wants to procure a multitasking machine to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT