Question

Problem 11-49 Complete Analysis of Cost Variances; Review of Chapters 10 and 11 (LO 11-5) Chillco Corporation produces contai
Required: Compute the following cost variances from the available data. (Indicate the effect of each variance by selecting F
1 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 10 more requests to produce the answer.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
Problem 11-49 Complete Analysis of Cost Variances; Review of Chapters 10 and 11 (LO 11-5) Chillco...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Compute the following cost variances from the available data.

    Problem 11-49 Complete Analysis of Cost Variances; Review of Chapters 10 and 11 (LO 11-5)Chillco Corporation produces containers of frozen food. During April, Chillco produced 785 cases of food and incurred the following actual costs. Variable overhead$6,900Fixed overhead10,500Actual labor cost (4,000 direct-labor hours)74,400Actual material cost (24,500 pounds purchased and used)51,450 Overhead is budgeted and applied using direct-labor hours in a standard costing system. Standard cost and annual budget information are as follows: Standard Costs per CaseDirect labor (4 hours at $18 per hour)$72.00Direct...

  • Exercise 11-22 Straightforward Computation of Overhead Variances (LO 11-5) Crystal Glassware Company has the following standards...

    Exercise 11-22 Straightforward Computation of Overhead Variances (LO 11-5) Crystal Glassware Company has the following standards and flexible-budget data.       Standard variable-overhead rate $ 7.00 per direct-labor hour Standard quantity of direct labor 3 hours per unit of output Budgeted fixed overhead $ 114,000 Budgeted output 19,000 units    Actual results for April are as follows:       Actual output 12,000 units Actual variable overhead $ 324,000 Actual fixed overhead $ 107,000 Actual direct labor 45,000 hours Required: Use...

  • Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come...

    Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...

  • Direct Material Variances Goldman, Inc. is a manufacturer of lead crystal glasses. The standard direct materials quantit...

    Direct Material Variances Goldman, Inc. is a manufacturer of lead crystal glasses. The standard direct materials quantity is 0.7 pounds per glass at the cost of $0.35 per pound. The actual result for one month’s production of 6,950 glasses was 1.3 pounds per glass, at the cost of $0.45 per pound. Calculate the direct materials cost variance and the direct materials efficiency variance. Direct Labour Variances Goldman, Inc. manufactures lead crystal glasses. The standard direct labor time is 0.5 hours...

  • Exercise 16-36 (Static) Variable Cost Variances (LO 16-5) Paynesville Corporation manufactures and sells a preservative used...

    Exercise 16-36 (Static) Variable Cost Variances (LO 16-5) Paynesville Corporation manufactures and sells a preservative used in food and drug manufacturing. The company carries no inventories. The master budget calls for the company to manufacture and sell 100,000 liters at a budgeted price of $75 per liter this year. The standard direct cost sheet for one liter of the preservative follows. Direct materials (2 pounds @ $4) $ 8 Direct labor (0.5 hours @ $24) 12 Variable overhead is applied...

  • Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come...

    Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...

  • Exercise 14-26 Direct Materials and Direct Labor Variances [LO 14-3] Assume that Schmidt Machinery Company had...

    Exercise 14-26 Direct Materials and Direct Labor Variances [LO 14-3] Assume that Schmidt Machinery Company had the standard costs reflected in Exhibit 14.5. In a given month, the company used 3,485 pounds of aluminum to manufacture 927 units. The company paid $29.20 per pound during the month to purchase aluminum. At the beginning of the month, the company had 57 pounds of aluminum on hand. At the end of the month, the company had only 37 pounds of aluminum in...

  • Choose the correct bolded choices to complete the sentences. The variable overhead cost variance is (favorable,...

    Choose the correct bolded choices to complete the sentences. The variable overhead cost variance is (favorable, unfavorable) because Longman actually spent (less, more) than budgeted. The variable overhead efficiency variance is (favorable, unfavorable) because the actual hours used was (more, less) than budgeted. The fixed overhead cost variance is (favorable, unfavorable) because Longman actually spent (less, more) than budgeted for fixed overhead. The fixed overhead volume variance is (favorable, unfavorable) because Longman allocated (more, less) overhead to jobs than the...

  • Direct Materials Variances Bellingham Company produces a product that requires 6 standard pounds per unit. The standard...

    Direct Materials Variances Bellingham Company produces a product that requires 6 standard pounds per unit. The standard price is $10 per pound. If 6,300 units required 36,300 pounds, which were purchased at $10.3 per pound, what is the direct materials (a) price variance, (b) quantity variance, and (c) total direct materials cost variance? Enter a favorable variance as negative number using a minus sign and an unfavorable variance as a positive number. 10,890 Unfavorable a. Direct materials price variance b....

  • Problem 11A-8 Applying Overhead; Overhead Variances [LO11-3, LO11-4] Lane Company manufactures a ...

    Problem 11A-8 Applying Overhead; Overhead Variances [LO11-3, LO11-4] Lane Company manufactures a single product that requires a great deal of hand labor. Overhead cost is applied on the basis of standard direct labor-hours. Variable manufacturing overhead should be $2.40 per standard direct labor-hour and fixed manufacturing overhead should be $384,000 per year. The company's product requires 4 pounds of material that has a standard cost of $4.00 per pound and 1.5 hours of direct labor time that has a standard...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT