Question

Which of the following is an element of (EOQ) inventory analysis? I. Theoretical cumulative probability distributions....

Which of the following is an element of (EOQ) inventory analysis?

I.

Theoretical cumulative probability distributions.

II.

Measures of operating time variability.

III.

Observed cumulative probability distributions.

IV.

Expected annual demand.

V.

Random number generators.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

iv)Expected annual demand.

If you think this helped do give a thumbs up else share your queries in comment section.

Add a comment
Know the answer?
Add Answer to:
Which of the following is an element of (EOQ) inventory analysis? I. Theoretical cumulative probability distributions....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In the Quantity Discount EOQ inventory model, which of the following items is NOT considered relevant...

    In the Quantity Discount EOQ inventory model, which of the following items is NOT considered relevant in determining the lowest cost order quantity? A. The cost of placing an order. B. The individual purchase price of an item of inventory. C. The cost of carrying an item in inventory. D. The variability of demand during lead time. E. The annual demand for the product.

  • Which of the following are considered relevant cash flows in the analysis of a project? I:...

    Which of the following are considered relevant cash flows in the analysis of a project? I: sunk costs II: opportunity costs III: negative side effects IV: financing costs V: taxes Group of answer choices III and IV II and III II, III and V II and IV I and II

  • 1.Which of the following distributions is widely used to describe the time between random events? Uniform...

    1.Which of the following distributions is widely used to describe the time between random events? Uniform distribution Exponential distribution Poisson distribution Normal distribution None of the answer choices is correct. 2. Which of the following distributions is not skewed? Normal distribution Uniform distribution Lognormal distribution Exponential distribution I only II only III only IV only Only I and II

  • Which of the following is true? [i] Kurtosis is a measure of the variability [ii] Kurtosis...

    Which of the following is true? [i] Kurtosis is a measure of the variability [ii] Kurtosis is a measure of the peakedness of a distribution [iii] Standard deviation is a measure of location [iv] Skewness is a measure of the degree of asymmetry of a frequency distribution [v] A symmetric distribution has zero skewness [vi] Variance is the difference between the largest and smallest values of a distribution. i, ii, iii, vi ii, iii, v ii, iv, v iii, iv,...

  • i) CHOOSE which of these probability distributions is most appropriate to describe a random variable X...

    i) CHOOSE which of these probability distributions is most appropriate to describe a random variable X defined as "the number of approved state-government construction contracts bid by the engineering firm in the recent year". * X~Poisson(8) X~Po(3.2) X~Binomial(8,0.4) X~Negative Binomial(8,0.4) X~Geometric(0.4)ii) Using the random variable X in question 1(i), which of the following mathematical expressions indicates: the probability that the engineering firm will not get any state-government construction contracts that they have bid in the recent year? * P(X=8) P(X...

  • a. Stock Moon and Noon have the following probability distributions of returns: Probability Returns Stock Moon...

    a. Stock Moon and Noon have the following probability distributions of returns: Probability Returns Stock Moon Stock Noon 20% 10% 12% 15% 2% 0.3 0.4 0.3 -2% From the above information, calculate for each stock: i) The expected rate of return. (3 Marks) ii) The standard deviation. (3 Marks) iii) The coefficient of variation. (2 Marks) iv) Based on your calculation in part (iii), decide on the stock that you should invest on. Justify your answer. (4 Marks) b. Suppose...

  • Which of the following is/are not a project's cash inflow(s)? Ignore any tax effects. I. equipment...

    Which of the following is/are not a project's cash inflow(s)? Ignore any tax effects. I. equipment acquisition II. decrease in inventory III. product development cost IV. decrease in accounts payable V. product marketability studying cost Multiple Choice 0 O I, III, IV and V only 0 I, II and III only 0 land Il only 0 O I Ill and only 0 Ill and V only We can apply the the dividend growth model to estimate the cost of equity...

  • a) What is the premise of ABC Analysis? What are the three steps in making ABC...

    a) What is the premise of ABC Analysis? What are the three steps in making ABC inventory analysis? b) State and describe with examples the three types of costs associated with inventory c) The annual demand of a Bottled Water Distribution company is 25,000 boxes, the ordering cost ¢40 per order, the carrying cost 15%, and the unit cost ¢15 per box. The order quantity is 500 units. Calculate the following; i). Annual ordering cost ii). Annual carrying cost iii)....

  • Which of the following is/are true for the average accounting return method of project analysis? 1....

    Which of the following is/are true for the average accounting return method of project analysis? 1. does not need a cutoff rate II. ignores time value of money III. is based on project's cash flows IV. easily obtainable information for computation Multiple Choice I and IV only II and IV only ooo Tonly I, II, III, and IV I, II, and IV only Which of the following statements related to annuities and perpetuities is/are correct? 1. Most loans are a...

  • b) As a contractor to Petronas, East Technology uses 4000 valves for repairing one of Petronas plant every year. These valves are purchased from a supplier 200 km away. The following information...

    b) As a contractor to Petronas, East Technology uses 4000 valves for repairing one of Petronas plant every year. These valves are purchased from a supplier 200 km away. The following information is known about the valves Table Q3b: Forecast demand for plastic product Annual demand 4000 Holding cost /valve/vear Order cost/ year RM 9 RM 25 s days Lead time Working days per year 250 Given the above information, calculate i) The economic order quantity (EOQ)? ii) The annual...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT