Hello, I'm working on Case 7.1 Removing Snow in Montreal (Chapter 7, Problem 1C) on the "Spreadsheet Modeling and Decision Analysis 7th Edition" textbook. But the questions are below(not same as text book questions):
Here is the full question
1) First ASsume that by contract each of the 10 sectors can only be assigned to one of the 5 disposal sites so that driver do not have to carry to multiple sites. however, each disposal site can take snow from multiple sectors, up to its capacity. Create a spreadsheet that Montreal Could use to determine the most efficient snow removal plan for the coming year. Assume it costs $0.035 to transport 1 cubic meter of snow for 1km (i.e. $35 per 1000 cubic meters per km)
1. The spreadsheet model and solution using Solver is following:
Formulas:
Cell | Formula | Copy to |
O3 | =SUM(J3:N3) | O3:O12 |
J13 | =SUM(J3:J12) | J13:N13 |
G17 | =SUM(B17:F17) | G17:G26 |
J17 | =B$13*B17-J3 | J17:N26 |
O28 | =SUMPRODUCT(J3:N12,B3:F12)*35 |
_____________________________________________
2. Optimal solution is determined as in part 1.
Lowest cost = $ 191,450
_____________________________________________
3. The revised model and solution is following:
The formulas remain the same. Only the constraint pertaining the condition is removed from the Solver parameter window.
The resulting cost = $ 167,471.5
_____________________________________________
4. The revised model with the objective of maximizing the amount of contaminant removed is following:
Formulas:
Cell | Formula | Copy to |
O3 | =SUM(J3:N3) | O3:O12 |
J13 | =SUM(J3:J12) | J13:N13 |
O16 | =SUMPRODUCT(J13:N13,J14:N14) |
Maximum contaminants that can be removed = 612.8 (1000 m3)
Hello, I'm working on Case 7.1 Removing Snow in Montreal (Chapter 7, Problem 1C) on the...