Question

1)Jay Co. is a contract manufacturer that produces two products, Prod A and Prod B; and...

1)Jay Co. is a contract manufacturer that produces two products, Prod A and Prod B; and supply the two products to various retailers. The numbers of units for Prod A and Prod B that Jay Co is contracted to supply for next four months are given in the following table:

Month 1 Month 2 Month 3 Month 4
PROD A 1000 4000 1000 3000
PROD B 500 1500 250 1500


The production processes for Prod A and Prod B are quite labour intensive. It takes two hours direct labour to produce one unit of Prod A and six hours of direct labour to produce one unit of Prod B. One factory worker gets paid $4000 per month. Each factory worker works up to 200 hours per month as regular working hours. If a factory worker works more than 200 hours per month, those “over-time” portion will get compensated at the rate of $30 per hour. However, due to the agreement made with the labour union, total hours of overtime work cannot exceed 10% of regular working hours.

Currently, the industry suffers from labour shortage. As such, every newly hired factory worker receives two-month salary as a signing bonus. On the other hand, every worker made being redundant (i.e. fired) by the company receives a half-month salary as a severance payment.

Another cost element that Jay Co must consider is the inventory holding cost. The monthly inventory holding cost for Prod A is $5 per unit and the monthly inventory holding cost for Prod B is $20 per unit.

Due to its labour intensive nature of production processes, Jay Co does not consider any other production related costs. Their main concerns are manpower cost and inventory holding cost.

Every single contracted unit of Prod A or Prod B must be delivered. Due to the severe penalty Jay Co must pay to the retailers, it is not an option for Jay Co not to meet the contracted units.

(a) Apply linear programming model to develop a formulation for Jay Co’s decision problem. Describe any assumptions you made for your formulation

(b) Use Microsoft Excel to solve the formulation in Question 1(a). Your answer must include the sensitivity report.

(c) Interpret the sensitivity report you obtained in Question 1(b) and answer the following questions.
Ci)After reading your sensitivity report, your production manager wants to renegotiate with the labour union on “over-time” clause. She would like to talk to the labour union whether they can agree to work more than 10% of regular working time as over-time. Discuss the reason(s) why she wants to have more overtime working.

cii)It turns out the labour union is quite open to the idea of allowing more over-time hours. They willing to increase the “10% cap” into 20% of regular working hours. However, they demander-time working hours will be paid at the rate of $40 per hour. Examine whether the request of the labour union is acceptable to Jay Co.


ciii) Suppose the labour shortage situation has improved a little bit. Now, Jay Co only needs to pay one-month salary as a signing bonus to newly hired workers. Analyse how it will affect your optimal solution.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

(a)

Assumptions

  • We already have 50 workers with us before the start of the first month.
  • We don't have any beginning inventory (for both A and B) at the start of the first month.
  • Inventory carrying cost is levied on ending inventory and not on the average inventory of a month.

Let Hj, Lj, Raj, Rbj, Oaj, Obj, Eaj, Ebj are defined as the decision variables such that -

Hj = # workers hired in the month-j
Lj = # workers laid off in the month-j
Raj = Regular production hours for product A in the month-j
Rbj = Regular production hours for product B in the month-j
Oaj = Overtime production hours for product A in the month-j
Obj = Overtime production hours for product B in the month-j
Eaj = Ending Inventory (in labor hours) for product A in the month-j
Ebj = Ending Inventory (in labor hours) for product B in the month-j; j=1,2,3,4

Also, define Daj = Demand for product A (in labor hours) in the month-j. Daj: [2000; 8000; 2000; 6000]
Dbj = Demand for product A (in labor hours) in the month-j. Dbj: [3000; 9000; 1500; 9000]

Objective Function: Minimize Z = total cost
Subject to, 1. Production balance constraints Regular Capacity Constraints 2. Raj Roj s 200*Wj; j-1,2,3,4 Here Wj stands for

(b)

Ending Inv. (A) Month Demand A Demand B # of workers o/T hrs. o/Thrs. EndingReg. hrs. Inv. (B) Hire Layoff Reg. hrs. (hrs. (h

Set Objective SKS12 Max Value Of: By Changing aiable Cells: SFS4:SMS7 Subject to the Constraints: SCS13:SDS16 SES13:SFS16 SIS

Final Result

Month Demand A Demand B #of Hire Layoff o/Thrs.o/Thrs.Ending Ending Reg. hrs. Reg. hrs. (hrs.) (hrs Workers Inv. (A)v. B (A)

(c)

Sensitivity Report

Variable Cells
Final Reduced Objective Allowable Allowable
Cell Name Value Cost Coefficient Increase Decrease
$F$4 Hire 0 0 24000 9450 5450
$G$4 Layoff 0 10000 -14000 1E+30 10000
$H$4 O/T hrs. (A) 0 3.55271E-15 30 1E+30 3.55271E-15
$I$4 O/T hrs. (B) 1000 0 30 3.55271E-15 327.5
$J$4 Ending Inv. (A) 6000 0 2.5 0.833333333 29.77272727
$K$4 Ending Inv. (B) 0 0.833333333 3.333333333 1E+30 0.833333333
$L$4 Reg. hrs. (A) 8000 0 0 3.55271E-15 29.77272727
$M$4 Reg. hrs. (B) 2000 0 0 327.5 3.55271E-15
$F$5 Hire 0 4725 20000 1E+30 4725
$G$5 Layoff 0 5275 -10000 1E+30 5275
$H$5 O/T hrs. (A) 1000 0 30 0 272.5
$I$5 O/T hrs. (B) 0 0 30 1E+30 0
$J$5 Ending Inv. (A) 0 33.63636364 2.5 1E+30 33.63636364
$K$5 Ending Inv. (B) 0 34.46969697 3.333333333 1E+30 34.46969697
$L$5 Reg. hrs. (A) 1000 0 0 52.75 0
$M$5 Reg. hrs. (B) 9000 0 0 0 34.46969697
$F$6 Hire 0 10000 16000 1E+30 10000
$G$6 Layoff 3.75 0 -6000 2500 5450
$H$6 O/T hrs. (A) 0 16.25 30 1E+30 16.25
$I$6 O/T hrs. (B) 0 16.25 30 1E+30 16.25
$J$6 Ending Inv. (A) 5750 0 2.5 0.833333333 12.5
$K$6 Ending Inv. (B) 0 0.833333333 3.333333333 1E+30 0.833333333
$L$6 Reg. hrs. (A) 7750 0 0 0.833333333 12.5
$M$6 Reg. hrs. (B) 1500 0 0 16.25 0.833333333
$F$7 Hire 0 8750 12000 1E+30 8750
$G$7 Layoff 0 1250 -2000 1E+30 1250
$H$7 O/T hrs. (A) 0 13.75 30 1E+30 13.75
$I$7 O/T hrs. (B) 0 13.75 30 1E+30 13.75
$J$7 Ending Inv. (A) 0 18.75 2.5 1E+30 18.75
$K$7 Ending Inv. (B) 0 19.58333333 3.333333333 1E+30 19.58333333
$L$7 Reg. hrs. (A) 250 0 0 12.5 0.833333333
$M$7 Reg. hrs. (B) 9000 0 0 0.833333333 19.58333333
Constraints
Final Shadow Constraint Allowable Allowable
Cell Name Value Price R.H. Side Increase Decrease
$C$13 Total Regular 10000 -43.625 0 5.32907E-13 10909.09091
$D$13 Total O/T 1000 -12.38636364 0 5.86198E-13 1047.619048
$C$14 Total Regular 10000 -46.375 0 5.32907E-13 2000
$D$14 Total O/T 1000 -14.88636364 0 5.86198E-13 1047.619048
$C$15 Total Regular 9250 -13.75 0 500 1500
$D$15 Total O/T 0 0 0 1E+30 925
$C$16 Total Regular 9250 -16.25 0 11500 500
$D$16 Total O/T 0 0 0 1E+30 925
$I$13 Output - (E.I - B.I.) -A 2000 42.38636364 2000 12000 5.86198E-13
$J$13 Output - (E.I - B.I.) -B 3000 42.38636364 3000 12000 5.86198E-13
$I$14 Output - (E.I - B.I.) -A 8000 44.88636364 8000 44000 5.86198E-13
$J$14 Output - (E.I - B.I.) -B 9000 44.88636364 9000 1833.333333 5.86198E-13
$I$15 Output - (E.I - B.I.) -A 2000 13.75 2000 1500 500
$J$15 Output - (E.I - B.I.) -B 1500 13.75 1500 1500 500
$I$16 Output - (E.I - B.I.) -A 6000 16.25 6000 1500 500
$J$16 Output - (E.I - B.I.) -B 9000 16.25 9000 500 9000
  • The overtime capacity constraint shows negative shadow price. So, if we increase the overtime %, there is a chance that the total cost can further be reduced. This is the reason, she wants to have more overtime working.
  • The shadow prices for the four months are -12.4, -14.9, 0, and 0 per hour. So, the total cost can reduce to 1000*(-12.4)+1000*(-14.9) = -27,300 and the rate increase is ($40 - $30)=$10 per hour. So, extra cost incurred will be 4000*10 = 40,000. So, this offer may not be worth considering.
  • The decrease is $8,000 - $4,000 = $4,000. The allowable decrease is, however, $5,450. So, there should be any effect is the optimal solution.
Add a comment
Know the answer?
Add Answer to:
1)Jay Co. is a contract manufacturer that produces two products, Prod A and Prod B; and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • E8-17 Calculating factory overhead: two variances Munoz Manufacturing Co. normally produces 10,000 units of prod- uct...

    E8-17 Calculating factory overhead: two variances Munoz Manufacturing Co. normally produces 10,000 units of prod- uct X each month. Each unit requires 2 hours of direct labor, and factory overhead is applied on a direct labor hour basis. Fixed costs and variable costs in factory overhead at the normal capacity are $2.50 and $1.50 per direct labor hour, respectively. Cost and production data for May follow: Production for the month... 9,000 units Direct labor hours used ..... 18,500 hours Factory...

  • 1 pts Question 12 Now Juice, Inc. produces bottled pickle juice. A planner has developed an...

    1 pts Question 12 Now Juice, Inc. produces bottled pickle juice. A planner has developed an aggregate forecast for demand (in cases) for the next four months. Use the following information to develop an aggregate plan using the LEVEL strategy. Inventory holding cost is $1 per month per case and backlog cost is $5 per month per case. Beginning inventory is zero. Month May June July August Forecast 701 627 550 434 Cost Per Unit 16.67 1.5 x Regular Prod...

  • Medisan Inc. has just signed a contract to supply walky-talkiesto the Turkish Armed Forces. Durin...

    Medisan Inc. has just signed a contract to supply walky-talkiesto the Turkish Armed Forces. During the next four months, the firm must deliver 150 in December, 160 in January, 225 in February and 180 in March. Medisan’s factory in Temelli can produce walky-talkies at a cost of $20 per unit (labor cost is not included). To produce a walky-talky 10 hours of labor are required and there are 10 workers available at the plant at the beginning of December. Each...

  • AGGREGATE PLANNING Garden Hub makes a single product, a garden tool that sells for $40. Garden Hub starts with 1000 of these tools in inventory and is expected to end with at least 500 in stock. Garde...

    AGGREGATE PLANNING Garden Hub makes a single product, a garden tool that sells for $40. Garden Hub starts with 1000 of these tools in inventory and is expected to end with at least 500 in stock. Garden Hub can temporarily backlog demand for a cost, but at the end of the time horizon, they require their backlog to be zero – This is an important constraint to remember- if we forget it, we will get strange results . Production costs...

  • 02 Consuelo Chua, Inc., is a disk drive manufacturer in need of an aggregate plan for...

    02 Consuelo Chua, Inc., is a disk drive manufacturer in need of an aggregate plan for July through December. The com- pany has gathered the following data: COSTS Holding cost $8/disk/month Subcontracting 580/disk Regular-time labor $12 hour Overtime labor $18 hour for hours above 8 hours/workerday Hiring cost $4000/ worker Layoff cost $8000/worker DEMAND Note: In this problem (and Q3) the production cost should be computed based on the labor cost OTHER DATA Current worden 8 people Labor hours disk...

  • please full calculation and explanation. 1 точистограЫсстат с Fantasy Budget Co. makes two products, basic saddles...

    please full calculation and explanation. 1 точистограЫсстат с Fantasy Budget Co. makes two products, basic saddles and deluxe saddles. Data for the month on November of the current year are as follow: Budgeted Sales Production Information Basic Deluxe Basic Deluxe Units 9,250 6,200 Leather 5 m2 10 m2 340 420 Padding 10 kg 4 kg Direct Labour 3 hours 2 hours Price Units m Inputs Leather Padding Direct Labour Cost per unit- Upcoming month 14.75 2.00 22.00 Cost per unit...

  • A manufacturer wants to develop a production plan for the month of February through June. The...

    A manufacturer wants to develop a production plan for the month of February through June. The forecasted demand for those months are 2500, 3700, 3900, 5000, and 2000 units, respectively. The regular-time production capacity in February and March are 3000 units and 2500 units, respectively. The overtime production capacity in February and March are 600 units and 500 units, respectively. The regular production cost is $30 per unit and the overtime production cost is $45 per unit. The cost of...

  • Alpha Assemblies produces a wide variety of products in their central Nebraska facility. Many of these products fit with...

    Alpha Assemblies produces a wide variety of products in their central Nebraska facility. Many of these products fit within a line of standard truck and trailer parts. Within this is a set of hitches that can be made in two sizes (1-1/4 and 2) and three strengths (light duty, medium duty, and heavy duty). All of the hitches in this line have "natural" finishes so no additional steps are necessary after they are cast. The machine used to cast these...

  • Please show the steps clearly 1. A company is involved in the production of two items...

    Please show the steps clearly 1. A company is involved in the production of two items (X and Y). The resources need to produce X and Y are twofold, namely machine time for automatic processing and craftsman time for hand finishing. The table below gives the number of minutes required for each item: Table 1: Minutes required for each item Item Machine time Crafstman time Item X 13 20 Item Y 19 29 The company has 40 hours of machine...

  • Problem 1 (Aggregate planning): Martin Trailers (MT) is a manufacturer of small camping and snowmobile trailers...

    Problem 1 (Aggregate planning): Martin Trailers (MT) is a manufacturer of small camping and snowmobile trailers in Ontario (lvey case #9A82D006). The demand for the camping trailers occurs between Jan and Jun of each year (mostly in Apr and May). Aggregate demand (in units) is: Jan 450 Feb 525 Mar 675 Apr 1005 May 1,125 Jun. 600 MT employs 40 permanent workers who are paid $20 per hour and each worker works 150 hours per month. Together they make approx....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT