c)
Expected time of path A-E-G-H-J = 10.17+9.83+3.00+4.67+5.17 = 32.83
Variance of path A-E-G-H-J = 0.25+0.69+0.44+1.00+0.69 = 3.08
Standard deviation = sqrt(3.08) = 1.76
z = (36-32.83)/1.76 = 1.80
P(z) = NORMSDIST(1.80) = 0.9643
Probability that path A-E-G-H-J will exceed the expected project duration = 1 - 0.9643 = 0.0357
The project manager of Good Public Relations gathered the data shown in the following table for...
PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....
H m Problem 21 Question Help Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project (shown below to the right). In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following table: Time Estimates (days) Most Likely Activity Optimistic Pessimistic A 4 8 12 5 12...
The table below gives the optimistic, most-likely, and pessimistic time estimates (in weeks) for all activities in a project. (Statistical tables are available in appendix I) Activ Predecessor totm t 2.0 5.0 8.0 3.0 4.0 5.0 4.06.08.0 5.0 6.0 7.0 3.0 6.0 9.0 D, E (i) Calculate the estimated time and variance for each task (ii) Draw the AON diagram and identify the critical path. (iii) What is the expected critical path duration and estimate a standard deviation for the...
5. A project has critical path activities A, B, and C. A is the predecessor of B. B is the predecessor of C. The duration estimate for activity A, B and C is shown in the following table. Fill the table with mean duration, standard deviation, and variance for activities and the whole project (critical path). Determine what is the probability of completing this project within 80 days? (10 points) Activity Optimistic Pessimistic Most likely Mean Standard Variance deviation duration...
Consider the office renovation project data in the following table. A "zero" time estimate means that the activity could take a very small amount of time and should be treated as a numeric zero in the analysis. a. Based on the critical path, find the probability of completing the office renovation project by 38 days. Refer to the standard normal table. (Make sure to round all intermediate calculations for te and variance to two decimal places.) Time Estimates (days) Activity...
You are responsible for managing a project with the following activities (all times are given in weeks): Optimistic Most Likely Pessimistic Immediate Time Predecessor(s) Time Activity Time 4 C, D D, E 12 4 8 6 4 What is the expected time of completion of the project? (weeks) (Include 1 decimal place, e.g.,3.1.) abs What is the probability that the project will be completed in 24 weeks or less? (Provide ab 2 decimal places, no 90 sign, e.g., 2.12 for...
1. Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. ActivityTime (weeks)a m bImmediatePredecessor(s) Activity aTime (weeks)m bImmediatePredecessor(s)A4810—G234C, EB2824AH222FC81216AI666FD4610AJ4612D, G, HE123BK223I, JF6820C, E a) The expected (estimated) time for activity C is weeks. (Round your response to two decimal places.) b) The variance for activity C is weeks. (Round your response to two decimal places.) c) Based on the calculation of the estimated times, the critical path...
1- Consider the table shown below: Task Predecessor Time (weeks) Expected time Variance of time Optimistic Most likely Pessimistic A - 1 3 5 B A 2 6 10 C B 4 7 10 D B, C 1 2 9 E D 2 4 6 F D,E 4 7 10 G F 1 3 5 a) Calculate expected time and variance for each task. b) Find the critical path and expected project competition time? c) What is the probability of...
Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...
(50 points) Data regarding the activities for a project are presented below. The times are in weeks The critical path for this project is A-D-H-I-J-K 2. Pessimistic Time Most Likely Time y Optimistic Time 8 16 10 8 10 12 8 14 5 6 2 a. Determine the standard deviation of the critical path. b. Determine the probability of completing the project in 38 weeks or less c What is the probability of completing the project in 32 weeks or...