Question

If capital budgeting projects are independent: a. A project accepted by IRR method will be rejected...

If capital budgeting projects are independent:

a. A project accepted by IRR method will be rejected by NPV

b.A project accepted by IRR will always be accepted by NPV

c.A project accepted by IRR may sometimes be accepted by NPV

d. a or b depending on the discount rate

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The correct answer is option c. A project accepted by IRR may sometimes be accepted by NPV

If the project that is accepted by IRR rule has an NPV greater than the rejected project based on IRR rule, then it is accepted by NPV rule as well.

If the project that is accepted by IRR rule has an NPV lower than the rejected project based on IRR rule, then it is rejected by NPV rule.

Option A is incorrect for the same reason.

Option b is incorrect because a project accepted by IRR rule may be rejected by NPV rule.

Can you please upvote? Thank You :-)

Add a comment
Know the answer?
Add Answer to:
If capital budgeting projects are independent: a. A project accepted by IRR method will be rejected...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • If the projects were independent, which project(s) would be accepted according to the IRR method? a)...

    If the projects were independent, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B The reason is a) TheNPV and IRR approaches use the same reinvestment rate assumption and so both approaches reach the same...

  • please explain! thank you 41 Capital Budgeting Exercises: Inree independent projects are under consideration for capital...

    please explain! thank you 41 Capital Budgeting Exercises: Inree independent projects are under consideration for capital budgeting purposes. Their respective initial investment, cost of capital, and cash flows are provided below. Use the following capital budgeting techniques to evaluate all three projects and indicate which project should be undertaken, assuming there is no budget constraint A. Payback period method Discounted payback period method Net present value method IRR method B. C. D. Project 1 Project 2 Project 3 Initial Investment...

  • Capital Budgeting Decision Criteria: IRR IRR A project's internal rate of return (IRR) is the -Select-compound...

    Capital Budgeting Decision Criteria: IRR IRR A project's internal rate of return (IRR) is the -Select-compound ratediscount raterisk-free rateCorrect 1 of Item 1 that forces the PV of its inflows to equal its cost. The IRR is an estimate of the project's rate of return, and it is comparable to the -Select-YTMcoupongainCorrect 2 of Item 1 on a bond. The equation for calculating the IRR is: CFt is the expected cash flow in Period t and cash outflows are treated...

  • 11.07 CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this...

    11.07 CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows:    0 1 2 3 4 5 Project M -$6,000 $2,000 $2,000 $2,000 $2,000 $2,000 Project N -$18,000 $5,600 $5,600 $5,600 $5,600 $5,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers...

  • CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's...

    CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 5 Project M Project N - $30,000 $10,000 $10,000 $10,000 $10,000 $10,000 $90,000 $28,000 $28,000 $28,000 $28,000 $28,000 a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers...

  • 1. A. Which of the following mutually exclusive projects should be accepted? Project NPV Payback IRR...

    1. A. Which of the following mutually exclusive projects should be accepted? Project NPV Payback IRR A +42,176 2 years, +$10,500 16.4% B +39,090 2 years, +9,670 15.8% C +41,894 3 years, +16,620 13.2% D +43,778 3 years, +11,625 14.9% E +38,952 2 years, +15,475 15.9% B. What is the Payback Period of a project with an initial cost of $75,000, Year 1 cash flow of $20,000 which increases by 5% each year? If the Payback cutoff is 3 years,...

  • (NPV, PI, and IRR calculations) You are considering two independent projects, project A and project B....

    (NPV, PI, and IRR calculations) You are considering two independent projects, project A and project B. The initial cash outlay associated with project A is $50,000 and the initial cash outlay associated with project B is $70,000. The required rate of return on both projects is 11 percent. The expected annual free cash inflows from each project are on the table below. Calculate the NPV, PI, and IRR for each project and indicate if the project should be accepted. Project...

  • (NPV, PI, and IRR calculations) You are considering two independent projects, project A and project B....

    (NPV, PI, and IRR calculations) You are considering two independent projects, project A and project B. The initial cash outlay associated with project A is $50,000 and the initial cash outlay associated with project B is $70,000. The required rate of return on both projects is 11 percent. The expected annual free cash inflows from each project are on the table below. Calculate the NPV, PI, and IRR for each project and indicate if the project should be accepted. Project...

  • KEY TERMS Define the following terms: a. Capital budgeting; strategic business plan b. Net present value...

    KEY TERMS Define the following terms: a. Capital budgeting; strategic business plan b. Net present value (NPV) c. Internal rate of return (IRR) d. NPV profile; crossover rate e. Mutually exclusive projects; independent projects f. Nonnormal cash flows; normal cash flows; multiple IRRS g. Modified internal rate of return (MIRR) h. Payback period; discounted payback CAPITAL BUDGETING CRITERIA You must analyze two projects, X and Y. Each project costs $10,000, and the firm's WACC is 12%. The expected cash flows...

  • Which of the following is NOT a disadvantage of the IRR method for capital​ budgeting? A....

    Which of the following is NOT a disadvantage of the IRR method for capital​ budgeting? A. IRR does not provide information for project scale B. May not be a single solution C. May lead to wrong ranking decisions D. Results are hard to interpret

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT