Question

rigid and flexible pavement

A three-lane northbound section of interstate (with
the design lane conservatively designed) has rigid
pavement (PCC) and was designed with a 10-inch slab,
90% reliability, 700 lb/in2 concrete modulus of rupture,
4.5 million lb/in2 modulus of elasticity, 3.0 load transfer
coefficient, and an overall standard deviation of 0.35.
The initial PSI is 4.6 and the TSI is 2.5. The CBR is 2
with a drainage coefficient of 1.0. The road was
designed exclusively for trucks that have one 24-kip
tandem axle and one 12-kip single axle. It is known
from weigh-in-motion scales that there have been 13
million 18-kip–equivalent single-axle loads in the entire
northbound direction of this freeway so far. If a section
of flexible pavement is used to replace a section of the
PCC that was removed for utility work, what structural
number should be used so that the PCC and flexible
pavements have the same life expectancy (the new life
of the flexible pavement and the remaining life of the
PCC)?

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
rigid and flexible pavement
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 2- A roadway design company is designing a rigid pavement for a four-lane northbound section of...

    2- A roadway design company is designing a rigid pavement for a four-lane northbound section of interstate. This pavement was designed with an 8-inch slab, 95% reliability, a 800 lb/in2 concrete modulus of rupture, a 5 million lb/in2 modulus of elasticity, a 3.0 load transfer coefficient, and an overall standard deviation of 0.25. The initial PSI is 4.6 and the TSI is 2.5. The pavement was conservatively designed (assuming the upper limit of the W18 design lane load) to last...

  • (18%) A roadway design company is designing a rigid pavement for a four-lane northbound section of...

    (18%) A roadway design company is designing a rigid pavement for a four-lane northbound section of interstate. This pavement was designed with an 8-inch slab, 95% reliability, a 800 lb/in2 concrete modulus of rupture, a 5 million lb/in2 modulus of elasticity, a 3.0 load transfer coefficient, and an overall standard deviation of 0.25. The initial PSI is 4.6 and the TSI is 2.5. The pavement was conservatively designed (assuming the upper limit of the W18 design lane load) to last...

  • (18%) A roadway design company is designing a rigid pavement for a four-lane northbound section of...

    (18%) A roadway design company is designing a rigid pavement for a four-lane northbound section of interstate. This pavement was designed with an 8-inch slab, 95% reliability, a 800 lb/in2 concrete modulus of rupture, a 5 million 1b/in2 modulus of elasticity, a 3.0 load transfer coefficient, and an overall standard deviation of 0.25. The initial PSI is 4.6 and the TSI is 2.5. The pavement was conservatively designed (assuming the upper limit of the W18 design lane load) to last...

  • 2- (18%) A roadway design company is designing a rigid pavement for a four-lane northbound section...

    2- (18%) A roadway design company is designing a rigid pavement for a four-lane northbound section of interstate. This pavement was designed with an 8-inch slab, 95% reliability, a 800 lb/in2 concrete modulus of rupture, a 5 million lb/in2 modulus of elasticity, a 3.0 load transfer coefficient, and an overall standard deviation of 0.25. The initial PSI is 4.6 and the TSI is 2.5. The pavement was conservatively designed (assuming the upper limit of the W18 design lane load) to...

  • 2- (18%) A roadway design company is designing a rigid pavement for a four-lane northbound section...

    2- (18%) A roadway design company is designing a rigid pavement for a four-lane northbound section of interstate. This pavement was designed with an 8-inch slab, 95% reliability, a 800 lb/in2 concrete modulus of rupture, a 5 million lb/in2 modulus of elasticity, a 3.0 load transfer coefficient, and an overall standard deviation of 0.25. The initial PSI is 4.6 and the TSI is 2.5. The pavement was conservatively designed (assuming the upper limit of the W18 design lane load) to...

  • 2- (18%) A roadway design company is designing a rigid pavement for a four-lane northbound section...

    2- (18%) A roadway design company is designing a rigid pavement for a four-lane northbound section of interstate. This pavement was designed with an 8-inch slab, 95% reliability, a 800 lb/in2 concrete modulus of rupture, a 5 million lb/in2 modulus of elasticity, a 3.0 load transfer coefficient, and an overall standard deviation of 0.25. The initial PSI is 4.6 and the TSI is 2.5. The pavement was conservatively designed (assuming the upper limit of the W18 design lane load) to...

  • 2- (18%) A roadway design company is designing a rigid pavement for a four-lane northbound section...

    2- (18%) A roadway design company is designing a rigid pavement for a four-lane northbound section of interstate. This pavement was designed with an 8-inch slab, 95% reliability, a 800 lb/in2 concrete modulus of rupture, a 5 million lb/in2 modulus of elasticity, a 3.0 load transfer coefficient, and an overall standard deviation of 0.25. The initial PSI is 4.6 and the TSI is 2.5. The pavement was conservatively designed (assuming the upper limit of the W18 design lane load) to...

  • rigid and flexible pavement

    A rigid pavement is on a highway with two lanesin one direction, and the pavement is conservativelydesigned. The pavement has an 11-inch slab with amodulus of elasticity of 5,000,000 lb/in2 and a concretemodulus of rupture of 700 lb/in2, and it is on a soil witha CBR of 25. The design drainage coefficient is 1.0, theoverall standard deviation is 0.3, and the load transfercoefficient is 3.0. The pavement was designed to last 20years (initial PSI of 4.7 and a final PSI...

  • 2- (18%) A roadway design company is designing a rigid pavement for a four-lane northbound section...

    2- (18%) A roadway design company is designing a rigid pavement for a four-lane northbound section of interstate. This pavement was designed with an 8-inch slab, 95% reliability, a 800 lb/in2 concrete modulus of rupture, a 5 million 1b/in2 modulus of elasticity, a 3.0 load transfer coefficient, and an overall standard deviation of 0.25. The initial PSI is 4.6 and the TSI is 2.5. The pavement was conservatively designed (assuming the upper limit of the W18 design lane load) to...

  • please provide detailed soln. time sensitive (A roadway design company is designing a rigid pavement for...

    please provide detailed soln. time sensitive (A roadway design company is designing a rigid pavement for a four-lane northbound section of interstate. This pavement was designed with an 8-inch slab, 95% reliability, a 800 lb/in2 concrete modulus of rupture, a 5 million lb/in2 modulus of elasticity, a 3.0 load transfer coefficient, and an overall standard deviation of 0.25. The initial PSI is 4.6 and the TSI is 2.5. The pavement was conservatively designed (assuming the upper limit of the W18...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT