Net Requirement of A = 2*Requirement of X - On Hand Inventory of A
Net Requirement of A = 2*50 - 50 = 50 units
Net Requirement of B = 3*Requirement of X - On Hand Inventory of B
Net Requirement of B = 3*50 - 50 = 100 units
Net Requirement of C = 2*Net Requirement of B - On Hand Inventory of C
Net Requirement of C = 2*100 - 50 = 150 units
Net Requirement of D = 3*Net Requirement of B - On Hand Inventory of D
Net Requirement of D = 3*100 - 100 = 200 units
Net Requirement of E = 2*Net Requirement of D + 2*Net Requirement of A - On Hand Inventory of E
Net Requirement of E = 2*200 + 2*50 - 250 = 500 - 250 = 250 units
Given the product structure tree and the inventory on-hand shown in figure and table, determine the...
Question #1 : The product structure tree of a round-top computer desk is given as follows. On-hand inventory information is given in the Table 1 as follows. Level 0 Round-top computer desk (A) Level 1 B(4) C(2) Level 2 E(2) F(3) E(3) D(2) D(1) D(3) Level 3 Table 1: On-hand inventory Item On hand (units) Round-top com r desk 100 48 20 1) Determine number of units of each item required to satisfy a new order of 10 round-top computer...
Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...
03-Consider the product structure tree shown below: D(2) C(3) A(2) E(3) B(2) E(3) A(3) With a beginning inventory of zero for all components and finished items, how many assembly E's are needed to produce 25 product X's? A) 125 B) 375 C) 400 D) 250 Q4-Livernonions Industries uses a Kanban system to manage production of the BR-549 subassembly. In an eight-hour day, they use 900 units and use containers that can hold 30 units each. It takes 120 minutes to...
(b) Given the following tree (graph) as shown in Figure 2: Diberi pepohon (graf) seperti yang ditunjukkan dalam Rajah 2: Figure 2 Rajah 2 (i) Find the pre-order traversal of the tree. Cari penyusuran pepohon "pre-order". (8/100) (ii) Find the post-order traversal of the tree. Cari penyusuran pepohon "port-order". (8/100) (iii Using the ordering c, d, e, f, g, h, i, j, k, I, m, a, b, c and the depth-first search algorithm, find a spanning tree for the graph...
A structure tree of the components in a product, with a description and the quantity required to make each product is called a(n) D) Bill of Materials B) MRP system. A) ERP system E) Inventory Receipt C) Master production schedule.
A structure tree of the components in a product, with a description and the quantity required to make each product is called a(n) D) Bill of Materials B) MRP system. A) ERP system E) Inventory Receipt C) Master production schedule.
Given the data provided for product structure, component AC101, and the planned orders of parent AB 500 below, use the matrix for AC101 at the bottom to compute gross requirements, projected on hand, net requirements and planned orders. Suggestion: Start by filling out the MRP matrix for AC101 with the data given. AB500 LT=2 AC101 (2) LT=3 Notes: O signifies usage. FOQ = Fixed order quantity. Item On Hand MPS Scheduled Receipts 600: Week 6 Lot Size / Order Policy...
The bill of materials and the data from the inventory records for product A are shown in the figure to the right. Assume that the MPS start quantities for A are 100 units in weeks 1, 2, and 7. Derive an MRP plan for the components going into product A using the data in the table below Item Data Category L4L 2 weeks 100 (week 2) 350 L4L 1 week None 215 Lot-sizing rule Lead time Scheduled receipts Beginning inventory...
Please provide equation for each box
4.5. Given the following product tree, explode, offset, and determine the gross and net requirements. All lead times are 1 week, and the quantities required are shown in parentheses. The master production schedule calls for 100 Asto be available in week 5. There are 20 Bs available. All other on-hand balances =0. B(2) B (1) D(1) (1) D(2) RI) Part Number Week 3 1 2 4 5 100 Part Number Quantity B 2 D...
Determine planned order releases for each part shown in the product structure tree. 180 units of the finished product 565 are needed in week 6 (as shown in the master production schedule below). To figure out X43 material plan, look at planned order releases of both 565 and Y36. So, fill out X43 form after filling out 565 and Y36 plans. 565 X43 Y36(2) N78 J27(4) X43 Part Number On Hand Lot Size Lead Time 565 0 Lot-for-lot 1 week...