Question

03-Consider the product structure tree shown below: D(2) C(3) A(2) E(3) B(2) E(3) A(3) With a beginning inventory of zero for all components and finished items, how many assembly Es are needed to produce 25 product Xs? A) 125 B) 375 C) 400 D) 250 Q4-Livernonions Industries uses a Kanban system to manage production of the BR-549 subassembly. In an eight-hour day, they use 900 units and use containers that can hold 30 units each. It takes 120 minutes to fill and move a container of parts to the right place on the BR-549 line that is currently rated at a 15% safety factor. How many production hours of inventory are needed? A) 7.6 B) 4.3 C) 18.4 D) 2.4

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. Option B 375 E's

1. Produce one product of X we need 2 product of D and 3 products of C. Each product of D required 3 materials of E and Each Product of C required 3 Materials of E

One Product of X required = 3 * 3 + 2 * 3 = 15 Metrails of E

Thus to Produce 25 Product of X = 25 * 15 = 375 E's

2. Option D. 2.4 Hours

Number of Hours in a day * Safety Factor * Number of Hours to Fill and Use

8 * 15% * 2

= 2.4 Hours

Add a comment
Know the answer?
Add Answer to:
03-Consider the product structure tree shown below: D(2) C(3) A(2) E(3) B(2) E(3) A(3) With a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT