Question

1. Consider the following product structure: Each A consists of 2 Bs and 1 C. Each B consists of 3 Ds and 2 Es. Each C consists of 4 Ds and 2 Es. How many Ds are necessary to produce 400 As? a) 1600 b) 2400 c) 4000 d) 2000 e) 400 The XYZ Company has just hired you as Production Manager of their North American Fabrication Facility. Your first job is to use the MRP methodology to schedule production for the next nine weeks. The XYZ Company has given you the following information to work with Bill of Materials (Product Structure Diagram) urrent Inventory Records Leadtime (in weeks) Lotsize Inventory Currently On-hand Part Lot-for-Lot 125 100 Lot-for-Lot 55 50 875 900 ductio Weeks Part 100 0 500 0 500 100 0 95

1 0
Add a comment Improve this question Transcribed image text
Answer #1

1.(a)

[d] 2000

A = 200 => B = 400 and C = 200

So, D = 3 x 400 + 4 x 200 = 2000

For 2, 3, and 4

Weeks
A 1 2 3 4 5 6 7 8 9
Gross requirement 100 0 0 500 0 500 100 0 95
Scheduled receipt 0 0 0 0 0 0 0 0 0
Projected on-hand 125 25 25 25 0 0 0 0 0 0
Net requirement 0 0 0 475 0 500 100 0 95
Planned receipt 0 0 0 475 0 500 100 0 95
Planned release 0 0 475 0 500 100 0 95 0
Weeks
B 1 2 3 4 5 6 7 8 9
Gross requirement 0 0 475 0 500 100 0 95 0
Scheduled receipt 0 0 0 0 0 0 0 0 0
Projected on-hand 875 875 875 400 400 0 0 0 5 5
Net requirement 0 0 0 0 100 100 0 95 0
Planned receipt 0 0 0 0 100 100 0 100 0
Planned release 0 100 100 0 100 0 0 0 0
Weeks
C 1 2 3 4 5 6 7 8 9
Gross requirement 0 0 475 0 500 100 0 95 0
Scheduled receipt 0 0 0 0 0 0 0 0 0
Projected on-hand 55 55 55 0 0 0 0 0 0 0
Net requirement 0 0 420 0 500 100 0 95 0
Planned receipt 0 0 420 0 500 100 0 95 0
Planned release 420 0 500 100 0 95 0 0 0
Weeks
D 1 2 3 4 5 6 7 8 9
Gross requirement 420 0 500 100 0 95 0 0 0
Scheduled receipt 0 0 0 0 0 0 0 0 0
Projected on-hand 900 480 480 30 30 30 35 35 35 35
Net requirement 0 0 20 70 0 65 0 0 0
Planned receipt 0 0 50 100 0 100 0 0 0
Planned release 50 100 0 100 0 0 0 0 0

2.

[a] 0

3.

[b] 5

4.

[e] I, II, and III

5.

[a] 6 days

case cartridge label ink -6 -5 -4 -3 -1

6.

[b] II only

Level 0 Sandwich Level 1 American cheese slices Bread slices (2)

Add a comment
Know the answer?
Add Answer to:
1. Consider the following product structure: Each A consists of 2 B's and 1 C. Each...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • please solve clearly and show all steps 5. Williston Technologies wishes to use MRP methodology to developing a mat...

    please solve clearly and show all steps 5. Williston Technologies wishes to use MRP methodology to developing a material requirements plan for the next nine weeks. Williston Technologies has gathered the following information to work with: Bill of Materials: Current Inventory Records: Inventory Leadtime (in weeks) Currently Lotsize On-hand Lot-for-Lot 50 100 100 100 50 400 Master Production Schedule: -Weeks- Part 2 3 4 50 100 5 6 7 8 9 100 2500 2000 50 0 a. Using MRP methodology,...

  • Consider the following product structure: Each A consists of 2 B’s and 1 C. Each B...

    Consider the following product structure: Each A consists of 2 B’s and 1 C. Each B consists of 3 D’s and 2 E’s. Each C consists of 5 D’s and 3 E’s. How many D’s are necessary to produce 400 A’s?

  • 03-Consider the product structure tree shown below: D(2) C(3) A(2) E(3) B(2) E(3) A(3) With a...

    03-Consider the product structure tree shown below: D(2) C(3) A(2) E(3) B(2) E(3) A(3) With a beginning inventory of zero for all components and finished items, how many assembly E's are needed to produce 25 product X's? A) 125 B) 375 C) 400 D) 250 Q4-Livernonions Industries uses a Kanban system to manage production of the BR-549 subassembly. In an eight-hour day, they use 900 units and use containers that can hold 30 units each. It takes 120 minutes to...

  • MRP /ERP IN M 1) Each E subassembly is made up of two (2) G parts, four (5) H part, and One J par...

    MRP /ERP IN M 1) Each E subassembly is made up of two (2) G parts, four (5) H part, and One J part Draw the product structure tree diagram. the information provided below, complete the following MRP Record Transaction Processing for Part E and Part G only if the following information is provided (Do not order more quantity of any resources that is needed to maintain the production) sing the product structure free diagram and Subassembly Part Part Part...

  • Determine planned order releases for each part shown in the product structure tree. 180 units of...

    Determine planned order releases for each part shown in the product structure tree. 180 units of the finished product 565 are needed in week 6 (as shown in the master production schedule below). To figure out X43 material plan, look at planned order releases of both 565 and Y36. So, fill out X43 form after filling out 565 and Y36 plans. 565 X43 Y36(2) N78 J27(4) X43 Part Number On Hand Lot Size Lead Time 565 0 Lot-for-lot 1 week...

  • PLEASE PROVIDE STEP BY STEP CALCULATION PERFORMED IN EXCEL.

    Product XYZ is described as follows: Quantity of each assembly/component is in (brackets) XYZ are made up of assemblies A(3), B, & C(2) Assembly A contains D(2), E(2), & F(3) Assembly B contains part H(2) Assembly C contains parts G(2) & E(2) Inventory Lead- time and Lot Size Information: XYZABCDEFGHLead Time121112222Projected On Hand93125329252039160012568Lot SizeLFLLFL2010LFL10020010050Scheduled Receipts500000001000Safety Stock 105025 **Note** all scheduled receipts are in week 1 Create a product structure tree (Multilevel BOM):       (5 marks) Using Blank MRP sheets, Create a level loaded (discreet, with no remnants) plan    ...

  • Question #1 : The product structure tree of a round-top computer desk is given as follows....

    Question #1 : The product structure tree of a round-top computer desk is given as follows. On-hand inventory information is given in the Table 1 as follows. Level 0 Round-top computer desk (A) Level 1 B(4) C(2) Level 2 E(2) F(3) E(3) D(2) D(1) D(3) Level 3 Table 1: On-hand inventory Item On hand (units) Round-top com r desk 100 48 20 1) Determine number of units of each item required to satisfy a new order of 10 round-top computer...

  • supply chain question, please solve it anyone.

    There are two (2) Parts to this case.  The First part (Part 1) requires you to use the information to:1.    Build a Bill of Material (BOM) form the given information2.    Determine the Master Production Schedule (MPS) and3.    Complete the MRP for all parts including the product.   The Second Part (Part 2) will require you to use an indexed BOM to 1.    Create the correct MPS from the provided information2.    create the MRP for the unit and all of its assemblies/components Part 1:...

  • Given the following product tree, complete the MRP records for parts X, Y, and Z. Note...

    Given the following product tree, complete the MRP records for parts X, Y, and Z. Note that parts X and Y have specified order quantities. FILL IN THE BLANKS Note: *Gross Requirements & Net Requirements are shown as negative because demand represents withdrawals from inventory Scheduled Receipts & Planned Order Receipts are shown as positive because production represents additions to inventory 1 | 2 | 3 | 4 | 5 -15 -10 -15 -10 -15 20 71 Part X LT:...

  • provide step by step explanation of calculation. thanks

    Case #2 MGT2315  There are two (2) Parts to this case.  The First part (Part 1) requires you to use the information to:1.    Build a Bill of Material (BOM) form the given information2.    Determine the Master Production Schedule (MPS) and3.    Complete the MRP for all parts including the product.   The Second Part (Part 2) will require you to use an indexed BOM to 1.    Create the correct MPS from the provided information2.    create the MRP for the unit and all of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT