1.(a)
[d] 2000
A = 200 => B = 400 and C = 200
So, D = 3 x 400 + 4 x 200 = 2000
For 2, 3, and 4
Weeks | ||||||||||
A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | |
Gross requirement | 100 | 0 | 0 | 500 | 0 | 500 | 100 | 0 | 95 | |
Scheduled receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Projected on-hand | 125 | 25 | 25 | 25 | 0 | 0 | 0 | 0 | 0 | 0 |
Net requirement | 0 | 0 | 0 | 475 | 0 | 500 | 100 | 0 | 95 | |
Planned receipt | 0 | 0 | 0 | 475 | 0 | 500 | 100 | 0 | 95 | |
Planned release | 0 | 0 | 475 | 0 | 500 | 100 | 0 | 95 | 0 | |
Weeks | ||||||||||
B | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | |
Gross requirement | 0 | 0 | 475 | 0 | 500 | 100 | 0 | 95 | 0 | |
Scheduled receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Projected on-hand | 875 | 875 | 875 | 400 | 400 | 0 | 0 | 0 | 5 | 5 |
Net requirement | 0 | 0 | 0 | 0 | 100 | 100 | 0 | 95 | 0 | |
Planned receipt | 0 | 0 | 0 | 0 | 100 | 100 | 0 | 100 | 0 | |
Planned release | 0 | 100 | 100 | 0 | 100 | 0 | 0 | 0 | 0 | |
Weeks | ||||||||||
C | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | |
Gross requirement | 0 | 0 | 475 | 0 | 500 | 100 | 0 | 95 | 0 | |
Scheduled receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Projected on-hand | 55 | 55 | 55 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Net requirement | 0 | 0 | 420 | 0 | 500 | 100 | 0 | 95 | 0 | |
Planned receipt | 0 | 0 | 420 | 0 | 500 | 100 | 0 | 95 | 0 | |
Planned release | 420 | 0 | 500 | 100 | 0 | 95 | 0 | 0 | 0 | |
Weeks | ||||||||||
D | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | |
Gross requirement | 420 | 0 | 500 | 100 | 0 | 95 | 0 | 0 | 0 | |
Scheduled receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Projected on-hand | 900 | 480 | 480 | 30 | 30 | 30 | 35 | 35 | 35 | 35 |
Net requirement | 0 | 0 | 20 | 70 | 0 | 65 | 0 | 0 | 0 | |
Planned receipt | 0 | 0 | 50 | 100 | 0 | 100 | 0 | 0 | 0 | |
Planned release | 50 | 100 | 0 | 100 | 0 | 0 | 0 | 0 | 0 |
2.
[a] 0
3.
[b] 5
4.
[e] I, II, and III
5.
[a] 6 days
6.
[b] II only
1. Consider the following product structure: Each A consists of 2 B's and 1 C. Each...
please solve clearly and show all steps 5. Williston Technologies wishes to use MRP methodology to developing a material requirements plan for the next nine weeks. Williston Technologies has gathered the following information to work with: Bill of Materials: Current Inventory Records: Inventory Leadtime (in weeks) Currently Lotsize On-hand Lot-for-Lot 50 100 100 100 50 400 Master Production Schedule: -Weeks- Part 2 3 4 50 100 5 6 7 8 9 100 2500 2000 50 0 a. Using MRP methodology,...
Consider the following product structure: Each A consists of 2 B’s and 1 C. Each B consists of 3 D’s and 2 E’s. Each C consists of 5 D’s and 3 E’s. How many D’s are necessary to produce 400 A’s?
03-Consider the product structure tree shown below: D(2) C(3) A(2) E(3) B(2) E(3) A(3) With a beginning inventory of zero for all components and finished items, how many assembly E's are needed to produce 25 product X's? A) 125 B) 375 C) 400 D) 250 Q4-Livernonions Industries uses a Kanban system to manage production of the BR-549 subassembly. In an eight-hour day, they use 900 units and use containers that can hold 30 units each. It takes 120 minutes to...
MRP /ERP IN M 1) Each E subassembly is made up of two (2) G parts, four (5) H part, and One J part Draw the product structure tree diagram. the information provided below, complete the following MRP Record Transaction Processing for Part E and Part G only if the following information is provided (Do not order more quantity of any resources that is needed to maintain the production) sing the product structure free diagram and Subassembly Part Part Part...
Determine planned order releases for each part shown in the product structure tree. 180 units of the finished product 565 are needed in week 6 (as shown in the master production schedule below). To figure out X43 material plan, look at planned order releases of both 565 and Y36. So, fill out X43 form after filling out 565 and Y36 plans. 565 X43 Y36(2) N78 J27(4) X43 Part Number On Hand Lot Size Lead Time 565 0 Lot-for-lot 1 week...
Product XYZ is described as follows: Quantity of each assembly/component is in (brackets) XYZ are made up of assemblies A(3), B, & C(2) Assembly A contains D(2), E(2), & F(3) Assembly B contains part H(2) Assembly C contains parts G(2) & E(2) Inventory Lead- time and Lot Size Information: XYZABCDEFGHLead Time121112222Projected On Hand93125329252039160012568Lot SizeLFLLFL2010LFL10020010050Scheduled Receipts500000001000Safety Stock 105025 **Note** all scheduled receipts are in week 1 Create a product structure tree (Multilevel BOM): (5 marks) Using Blank MRP sheets, Create a level loaded (discreet, with no remnants) plan ...
Question #1 : The product structure tree of a round-top computer desk is given as follows. On-hand inventory information is given in the Table 1 as follows. Level 0 Round-top computer desk (A) Level 1 B(4) C(2) Level 2 E(2) F(3) E(3) D(2) D(1) D(3) Level 3 Table 1: On-hand inventory Item On hand (units) Round-top com r desk 100 48 20 1) Determine number of units of each item required to satisfy a new order of 10 round-top computer...
There are two (2) Parts to this case. The First part (Part 1) requires you to use the information to:1. Build a Bill of Material (BOM) form the given information2. Determine the Master Production Schedule (MPS) and3. Complete the MRP for all parts including the product. The Second Part (Part 2) will require you to use an indexed BOM to 1. Create the correct MPS from the provided information2. create the MRP for the unit and all of its assemblies/components Part 1:...
Given the following product tree, complete the MRP records for parts X, Y, and Z. Note that parts X and Y have specified order quantities. FILL IN THE BLANKS Note: *Gross Requirements & Net Requirements are shown as negative because demand represents withdrawals from inventory Scheduled Receipts & Planned Order Receipts are shown as positive because production represents additions to inventory 1 | 2 | 3 | 4 | 5 -15 -10 -15 -10 -15 20 71 Part X LT:...
Case #2 MGT2315 There are two (2) Parts to this case. The First part (Part 1) requires you to use the information to:1. Build a Bill of Material (BOM) form the given information2. Determine the Master Production Schedule (MPS) and3. Complete the MRP for all parts including the product. The Second Part (Part 2) will require you to use an indexed BOM to 1. Create the correct MPS from the provided information2. create the MRP for the unit and all of...