The reorder point is a threshold stock that any organization does not want to go below. It is calculated as follows:
Reorder point = daily usage/demand * Lead time .
In the given case, Lead time is 24 days and demand is average105 units per day. Therefore,
Reorder point = 105*24
=2,520
Therefore, the reorder point is 2,520.
Lead time for one of your fastest-moving products is 24 days. Demand during this period averages...
Lead time for one of Chang Manufacturing's fastest moving products is 5 days. Demand during this period averages 1,127 units per day. What would be an appropriate reorder point? Excel Access
QUESTION 16 Lead time for one of Chang Manufacturing's fastest moving products is 4 days. Demand during this period averages 1.106 units per day. What would be an appropriate reorder point? Excel Access
Questions Lead time for one of Montegut Manufacturing's fastest moving products is 5 days. Demand during this period averages 1,064 unides per day. What would be an appropriata reorder point? 3 points Excel Access
Demand during lead time for one brand of TV is normally distributed with a mean of 36 TVs and a standard deviation of 15 TVs. What safety stock should be carried for 90% service level? What is the appropriate reorder point? Click the icon to view the normal table What safety stock should be carried for a 90% service level? Safety stock units (round your response to the nearest whole number).
Based on available information, lead time demand for PC jump drives averages 53 units (normally distributed), with a standard deviation of 5 drives. Management wants a 95% service level. Refer to the standard normal table for z-values. a) What value of Z should be applied? (1.04/1.28/2.06/1.65) b) How many drives should be carried as safety stock? __________ units (round your response to the nearest whole number). c) What is the appropriate reorder point? __________ units (round your response to the...
Stephanie Robbins is attempting to perform an inventory analysis on one of her most popular products Annual demand for this product is 5.000 units carrying costs $50 per unit per year, order costs for her company typically run nearly $30 per order and load time averages 10 days. Assume 250 working days per year.) a) The economic order quality is units fround your response to the nearest whole number). b) The average Inventory is units (round your response to the...
The reorder point r = dm is defined as the lead-time demand for an item. In cases of long lead times, the lead-time demand and thus the reorder point may exceed the economic order quantity Q*. In such cases, the inventory position will not equal the inventory on hand when an order is placed, and the reorder point may be expressed in terms of either the inventory position or the inventory on hand. Consider the economic order quantity model with...
Leaky Pipe, a local retailer of plumbing supplies, faces demand for one of its SKUs at a constant rate of 18 comma 700 units per year. It costs Leaky Pipe $35 to process an order to replenish stock and $6.00 per unit per year to carry the item in stock. Stock is received 12 working days after an order is placed. No backordering is allowed. Assume 250 working days a year. a. Leaky Pipe's optimal order quantity is 467 nothing...
please read before solving thanks A products with an annual demand of 1000 units has EOQ (Economic Order Quantity)- 80. The demand during the lead time follows a normal probability distribution with u- 25 and s-5 during the reorder period. a How much safety stock is required, if the firm desires at most a 2% probability of a 4. stockout on any given order cycle? b. If a manager sets the reorder point at 30, what is the probability of...
Given this information: Lead-time demand = 620 pounds Standard deviation of lead time demand = 50 pounds (Assume normality.) Acceptable stockout risk during lead time = 4 percent Use Table. a. What amount of safety stock is appropriate? (Round your answer to the nearest whole number.) Safety stock units b. When should this item be reordered? (Round your answer to the nearest whole number.) ROP units c. What risk of stockout would result from a decision not to have any...