Question

Lead time for one of your fastest-moving products is 24 days. Demand during this period averages 105 units per day a) What wo
0 0
Add a comment Improve this question Transcribed image text
Answer #1

The reorder point is a threshold stock that any organization does not want to go below. It is calculated as follows:

Reorder point = daily usage/demand * Lead time .

In the given case, Lead time is 24 days and demand is average105 units per day. Therefore,

Reorder point = 105*24

=2,520

Therefore, the reorder point is 2,520.

Add a comment
Know the answer?
Add Answer to:
Lead time for one of your fastest-moving products is 24 days. Demand during this period averages...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT