Question

Lead time for one of Chang Manufacturings fastest moving products is 5 days. Demand during this period averages 1,127 units
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Lead time = L = 5 days

Daily Demand = d = 1127 units

Reorder point = d * L = 1127 * 5 = 5635 units

Answer: 5635

-----------------------------------------------------------------------------------------------------------------------

In case of any doubt, please ask through the comment section before Upvote/downvote.

If you liked the answer, please give an upvote. This will be quite encouraging for me, thank-you!!!

Add a comment
Know the answer?
Add Answer to:
Lead time for one of Chang Manufacturing's fastest moving products is 5 days. Demand during this...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT