Question 26 3 points Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Number of kanban = (daily demand*lead time+safety stock)/container quantity

or, 15 = (25*5+5)/container quantity

or, container quantity = (25*5+5)/15 = 8.666666667

Number of computers each one should hold = 8.666666667

Add a comment
Know the answer?
Add Answer to:
Question 26 3 points Lead time for computers is 5 days with daily demand of 25...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT