Daily demand (d) = 7 computers
Lead time(L) = 7 days
Demand during lead time = d × L = 7 × 7 = 49 computers
Safety stock = 1 day
Safety stock level = d × 1 = 7 × 1 = 7 computers
Kanban Container size = 8 computers
Numbers of Kanban needed = (demand during lead time + safety stock level)/container size
= (49+7)/8
= 56/8
= 7
So the answer is 7
Question 2 (1 point) Lead time for computers is 7 days with daily demand of 7...
QUESTION 30 Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants to use 18 kanbans how many computers should each one hold? lead time 5 days daily demand 25 units per day safety stock 5 units number of kanbans 18 Excel Access
Question 26 3 points Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants to use 15 kanbans how many computers should each one hold? lead time daily demand safety stock number of kanbans Excel Access 5 days 25 units per day 5 units 15
Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants to use 11 kanbans how many computers should each one hold? lead time 5 days daily demand 25 units per day safety stock 5 units number of kanbans 11 Excel Access
Lead time for computers is 5 days with daily demand of 25 and safety of comme use 10 kanbans how many computers should each one ho? lead time 5 days daily demand 25 units per day safety stock 5 units number of kanbans 10 Excel Access
JIT /Lean - Kanban: Daily demand for a product is 200 units. The production lead time (wait time + production time) for a container is 2 days. A 1-day safety stock is kept. How many kanban containers will be needed if each container holds 50 units? [Show calculations.]
A hinge manufacturing company employs a Kanban system for a component part. The daily demand is 870 hinges. Each container has a waiting time of 0.07 days and a processing time of 0.28 days. The container size is 58 hinges, and the safety factor (α) is 12 percent. Given this data, the number of Kanbans necessary for the system is: a. less than or equal to 4 Kanbans. b. more than 4 but less than or equal to 8 Kanbans....
Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of the kanban for the mainshaft assembly and the number of kanbans needed. Setup cost $20 Annual holding cost $220 per mainshaft Daily production 320 mainshafts/day Annual usage 20,000 (50 weeks 5 days each x daily usage of 80 mainshafts) Lead time 4 days Safety stock 0.50 days' production Kanban container size = 60mainshafts (round your response to the nearest whole number). Number of kanbans...
Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of the kanban for the mainshaft assembly and the number of kanbans needed. Setup cost $20 Annual holding cost $200 per mainshaft Daily production 360 mainshafts/day Annual usage 25,000 (50 weeks x 5 days each x daily usage of 100 mainshafts) Lead time 3 days Safety stock 1.00 days' production Kanban container size = mainshafts (round your response to the nearest whole number).
A customer has an average daily demand of 40 parts. Your company creates Kanbans with a 15% safety factor. The replenishment time once a signal has been received is 8 hours and you have 8 hours available per day. There are four kanban containers in process. Calculate the number of units per kanban container A) 12 B) 10 C) 11 D) 13
Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of the kanban for the mainshaft assembly and the number of kanbans needed Setup cost Annual holding cost $400 per mainshaft $20 320 mainshafts/day Daily production Annual usage 20,000 (50 weeks x5 days each x daily usage of 80 mainshafts) 3 days Lead time 1.00 days' production Safety stock Kanban container size = 52 mainshafts (round your response to the nearest whole number) Number of...