Question

Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants to use 11 kanb
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Number of kanbans = (daily demand*lead time + safety stock)/size in kanban

N = (d*L + S)/C

Here,

N = 11

d = 25

L = 5 days

S = 5

C = (d*L + S)/N

= (25*5 + 5)/11

= (130)/11

= 11.82

Answer is: 11.82 (if rounded, then 12)

********

IF YOU HAVE ANY DOUBT, KINDLY COMMENT. I WOULD LOVE TO HELP YOU!!!

IF YOU LIKE THE ANSWER, PLEASE GIVE AN UP-VOTE OR THUMB UP. THIS WILL ENCOURAGE ME TO ANSWER MORE!!

Add a comment
Know the answer?
Add Answer to:
Lead time for computers is 5 days with daily demand of 25 and safety stock of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT