Reorder point = Demand * Lead time
= 1106 * 4 = 4,424 units
Leave a positive rating if you think this answer helped
QUESTION 16 Lead time for one of Chang Manufacturing's fastest moving products is 4 days. Demand...
Lead time for one of Chang Manufacturing's fastest moving products is 5 days. Demand during this period averages 1,127 units per day. What would be an appropriate reorder point? Excel Access
Questions Lead time for one of Montegut Manufacturing's fastest moving products is 5 days. Demand during this period averages 1,064 unides per day. What would be an appropriata reorder point? 3 points Excel Access
Lead time for one of your fastest-moving products is 24 days. Demand during this period averages 105 units per day a) What would be an appropriate reorder point? units (enter your response as a whole number).
QUESTION 30 Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants to use 18 kanbans how many computers should each one hold? lead time 5 days daily demand 25 units per day safety stock 5 units number of kanbans 18 Excel Access
Question 26 3 points Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants to use 15 kanbans how many computers should each one hold? lead time daily demand safety stock number of kanbans Excel Access 5 days 25 units per day 5 units 15
Lead time for computers is 5 days with daily demand of 25 and safety of comme use 10 kanbans how many computers should each one ho? lead time 5 days daily demand 25 units per day safety stock 5 units number of kanbans 10 Excel Access
Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants to use 11 kanbans how many computers should each one hold? lead time 5 days daily demand 25 units per day safety stock 5 units number of kanbans 11 Excel Access
Assume an inventory control system for an independent demand item where the Lead-time is 4 days and the Review Period is 15 days. The expected demand for the end-item is 20,000 units per year. Assume, further, that the manager wants to achieve a cycle service level of 95% in her Q system and she knows that the daily average demand is 10 units (demand is normally distributed). She has determined that her facility is open 250 days a year; her...
please read before solving thanks A products with an annual demand of 1000 units has EOQ (Economic Order Quantity)- 80. The demand during the lead time follows a normal probability distribution with u- 25 and s-5 during the reorder period. a How much safety stock is required, if the firm desires at most a 2% probability of a 4. stockout on any given order cycle? b. If a manager sets the reorder point at 30, what is the probability of...
) The demand during the lead time is normally distributed with a méan of 40 and a standard deviation of 4. If they have calculated a reorder point of 46.60 units, what service level are they assuming? 9505 Service leve 2) The annual demand for a product has been projected at 2,000 units. This demand is assumed constant throughout the year. The ordering cost is $20 per order, and the holding cost is 20 percent purchase cost. The purchase cost...