QUESTION 30 Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants to
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

Information provided is as under:

L = Lead time

5

day

d = Average Demand during the lead time = Daily Demand =

25

units

N = Number of kanbans =

18

S = Safety stock =

5

units

C = Kanban size

?

units

Kanban size = Number of computers each kanban hold= C =[(d*L) + S]/N = ((25*5)+5)/18 = 7.22 unit of computer

Kanban size **This can be rounded as per requirement.

Add a comment
Know the answer?
Add Answer to:
QUESTION 30 Lead time for computers is 5 days with daily demand of 25 and safety...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT