ROP = DAILY DEMAND * LEAD TIME
= 1064 * 5 = 5320 UNITS
** Leaving a thumbs-up would really help me out. Let me know if you face any problems.
Questions Lead time for one of Montegut Manufacturing's fastest moving products is 5 days. Demand during...
Lead time for one of Chang Manufacturing's fastest moving products is 5 days. Demand during this period averages 1,127 units per day. What would be an appropriate reorder point? Excel Access
QUESTION 16 Lead time for one of Chang Manufacturing's fastest moving products is 4 days. Demand during this period averages 1.106 units per day. What would be an appropriate reorder point? Excel Access
Lead time for one of your fastest-moving products is 24 days. Demand during this period averages 105 units per day a) What would be an appropriate reorder point? units (enter your response as a whole number).
Question 26 3 points Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants to use 15 kanbans how many computers should each one hold? lead time daily demand safety stock number of kanbans Excel Access 5 days 25 units per day 5 units 15
Lead time for computers is 5 days with daily demand of 25 and safety of comme use 10 kanbans how many computers should each one ho? lead time 5 days daily demand 25 units per day safety stock 5 units number of kanbans 10 Excel Access
Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants to use 11 kanbans how many computers should each one hold? lead time 5 days daily demand 25 units per day safety stock 5 units number of kanbans 11 Excel Access
QUESTION 30 Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants to use 18 kanbans how many computers should each one hold? lead time 5 days daily demand 25 units per day safety stock 5 units number of kanbans 18 Excel Access
please read before solving thanks A products with an annual demand of 1000 units has EOQ (Economic Order Quantity)- 80. The demand during the lead time follows a normal probability distribution with u- 25 and s-5 during the reorder period. a How much safety stock is required, if the firm desires at most a 2% probability of a 4. stockout on any given order cycle? b. If a manager sets the reorder point at 30, what is the probability of...
) The demand during the lead time is normally distributed with a méan of 40 and a standard deviation of 4. If they have calculated a reorder point of 46.60 units, what service level are they assuming? 9505 Service leve 2) The annual demand for a product has been projected at 2,000 units. This demand is assumed constant throughout the year. The ordering cost is $20 per order, and the holding cost is 20 percent purchase cost. The purchase cost...
The reorder point is defined as the lead-time demand for an item. In cases of long lead times, the lead-time demand and thus the reorder point may exceed the economic order quantity Q*. In such cases, the inventory position will not equal the inventory on hand when an order is placed, and the reorder point may be expressed in terms of either the inventory position or the inventory on hand. Consider the economic order quantity model with D = 9,000,...