Number of kanbans = (daily demand*lead time + safety stock)/size in kanban
N = (d*L + S)/C
Here,
N = 11
d = 25
L = 5 days
S = 5
C = (d*L + S)/N
= (25*5 + 5)/11
= (130)/11
= 11.82
Answer is: 11.82 (if rounded, then 12)
********
IF YOU HAVE ANY DOUBT, KINDLY COMMENT. I WOULD LOVE TO HELP YOU!!!
IF YOU LIKE THE ANSWER, PLEASE GIVE AN UP-VOTE OR THUMB UP. THIS WILL ENCOURAGE ME TO ANSWER MORE!!
Lead time for computers is 5 days with daily demand of 25 and safety stock of...
QUESTION 30 Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants to use 18 kanbans how many computers should each one hold? lead time 5 days daily demand 25 units per day safety stock 5 units number of kanbans 18 Excel Access
Question 26 3 points Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants to use 15 kanbans how many computers should each one hold? lead time daily demand safety stock number of kanbans Excel Access 5 days 25 units per day 5 units 15
Lead time for computers is 5 days with daily demand of 25 and safety of comme use 10 kanbans how many computers should each one ho? lead time 5 days daily demand 25 units per day safety stock 5 units number of kanbans 10 Excel Access
Question 2 (1 point) Lead time for computers is 7 days with daily demand of 7 computers and a safety stock of 1 day. Each kanban holds 8 computers. What is the correct number of kanbans? O not enough information
Lead time for one of Chang Manufacturing's fastest moving products is 5 days. Demand during this period averages 1,127 units per day. What would be an appropriate reorder point? Excel Access
JIT /Lean - Kanban: Daily demand for a product is 200 units. The production lead time (wait time + production time) for a container is 2 days. A 1-day safety stock is kept. How many kanban containers will be needed if each container holds 50 units? [Show calculations.]
Dayton Electronics demands a part at a daily rate of 47 units. The lead time for replenishment is 7 days for this item. The standard deviation of demand during the lead time is 11. Dayton Electronics prides itself on having a high level of customer service and strives to achieve a service level of 90% (with the corresponding z-value of 1.28). How much safety stock should Dayton Electronics hold for this item? A) 14 units B) 19 units C) 27...
Questions Lead time for one of Montegut Manufacturing's fastest moving products is 5 days. Demand during this period averages 1,064 unides per day. What would be an appropriata reorder point? 3 points Excel Access
JL.61 A producer of refrigerator compressors wants to implement a just-in-time production line to support demand from a neighboring appliance manufacturer. Demand from the appliance manufacturer is for 285 compressors a day. The production lead time is 4 days and the producer wants to have a 18% safety stock factor. This producer has also cut setup costs such that the optimal production quantity is 93 units. How many kanbans does this producer of compressors require? (Display your answer to the...
QUESTION 16 Lead time for one of Chang Manufacturing's fastest moving products is 4 days. Demand during this period averages 1.106 units per day. What would be an appropriate reorder point? Excel Access