Question

Quasar Exports Ltd, a fictional Turkish manufacturer of glass, wants to use a c-chart to monitor...

Quasar Exports Ltd, a fictional Turkish manufacturer of glass, wants to use a c-chart to monitor the number of defects in the sheets of glass it produces. The company wants to use the chart to address the production problems it is experiencing and use it on an ongoing basis as a monitoring tool. To construct the chart, the company collected data over 5 days by inspecting 30 sheets of glass and recording the number defects per sheet. The data are as follows:

Sample Defects per Sheet Sample Defects per Sheet Sample Defects per Sheet
1 7 11 5 21 8
2 11 12 8 22 12
3 5 13 1 23 7
4 12 14 11 24 4
5 3 15 14 25 9
6 14 16 8 26 3
7 6 17 9 27 13
8 8 18 5 28 5
9 10 19 3 29 9
10 9 20 4 30 4
  1. Using the data in the table, construct a c-chart using control limits. Why did the company choose a c-chart to monitor this process?
      

    The defects are being counted over a consistent window of opportunity.

    The defects are being counted over 5 days.

    The defects per sample are being counted.

    The defects are being counted over an inconsistent window of opportunity.

    The defects are being counted for a set sample size.

  2. After making quality improvements to the process and concluding that it is in control in the current week, the quality control manager of Quasar collected data on the number of defects per sheet for the following week using 20 glass sheets. The defects per sheet were as follows: 2, 7, 4, 5, 6, 4, 8, 1, 5, 3, 4, 4, 7, 2, 10, 3, 5, 6, 4, and 3. Plot the data on the c-chart, and determine whether the process is in control.
      

    The process is in control.

    The process is not in control.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

c-bar = average(7,11,5,12,3,14,6,8,10,9,5,8,1,11,14,8,9,5,3,4,8,12,7,4,9,3,13,5,9,4) = 7.566666667

UCL = c-bar + z*sqrt(c-bar) = 7.566666667+3*sqrt(7.566666667) = 15.81893908
LCL = c-bar - z*sqrt(c-bar) = 7.566666667-3*sqrt(7.566666667) = -0.685605747 = 0 (Adjusted)

Correct answer is The defects are being counted over a consistent window of opportunity.

C-chart 1 2 10 18 19 20 3 4 - 5 6 7 8 Defects per sheet 9 — 11 LCL 12 — 13 14 C-bar 15 — 16 17 UCL

We can see the process is in control

Graph Data

Defects per sheet LCL C-bar UCL
2 0 7.566667 15.81894
7 0 7.566667 15.81894
4 0 7.566667 15.81894
5 0 7.566667 15.81894
6 0 7.566667 15.81894
4 0 7.566667 15.81894
8 0 7.566667 15.81894
1 0 7.566667 15.81894
5 0 7.566667 15.81894
3 0 7.566667 15.81894
4 0 7.566667 15.81894
4 0 7.566667 15.81894
7 0 7.566667 15.81894
2 0 7.566667 15.81894
10 0 7.566667 15.81894
3 0 7.566667 15.81894
5 0 7.566667 15.81894
6 0 7.566667 15.81894
4 0 7.566667 15.81894
3 0 7.566667 15.81894
Add a comment
Know the answer?
Add Answer to:
Quasar Exports Ltd, a fictional Turkish manufacturer of glass, wants to use a c-chart to monitor...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT