Let us evaluate the Total time in each step and implied utilization of each step=
Cut = 0.75* (25+15+10) = 37.5; Implied Utilization =37.5/60=0.625
Grill = 1.4*(25+15) = 56; Implied Utilization =56/60=0.933
Slice = 3*10 = 30; Implied Utilization =30/60=0.5
Toast = 3*0.5*(25+15+10)= 75; Implied Utilization =75/60=1.25
Wrap = 0.5*(25+15+10)= 25. Implied Utilization =25/60=0.0833
As the longest time is taken by Toast so it is the bottleneck and its corresponding implied utilization is 1.25
so the answer is 1.25
KINDLY RATE THE ANSWER AS THUMBS UP. THANKS A LOT
Question 2 0.6 points Save Anse Panini, a popular sandwich shop, offers 3 types of sandwiches:...
Question Completion Status: Question 1 11 points Save Answer The School of Dentistry at Penn provides general dental care to residents of Philadelphia on a walk-in basis. Upon arrival, customers first provide health- relevant information such as personal health records and insurance provider to a receptionist who enters the information into a computer system for the dentist to see. This step takes 4 minutes on average. A dental assistant then takes an X-ray of the patient. This step takes 15...