The gross requirement of E = 80 units
Week | 1 | 2 | 3 | 4 | 5 | 6 | ||
Item - E | Gross requirements | 0 | 0 | 0 | 0 | 0 | 80 | |
OH = 0 | Scheduled receipts | 0 | 0 | 0 | 0 | 0 | 0 | |
LT = 2 | Projected on-hand | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
SS = 0 | Net requirements | 0 | 0 | 0 | 0 | 0 | 80 | |
Q = L4L | Planned order receipts | 0 | 0 | 0 | 0 | 0 | 80 | |
Planned order releases | 0 | 0 | 0 | 80 | 0 | 0 | ||
Week | 1 | 2 | 3 | 4 | 5 | 6 | ||
Item - B | Gross requirements | 0 | 0 | 0 | 160 | 0 | 0 | |
OH = 60 | Scheduled receipts | 0 | 0 | 0 | 0 | 0 | 0 | |
LT = 2 | Projected on-hand | 60 | 60 | 60 | 60 | 0 | 0 | 0 |
SS = 0 | Net requirements | 0 | 0 | 0 | 100 | 0 | 0 | |
Q = L4L | Planned order receipts | 0 | 0 | 0 | 100 | 0 | 0 | |
Planned order releases | 0 | 100 | 0 | 0 | 0 | 0 | ||
Week | 1 | 2 | 3 | 4 | 5 | 6 | ||
Item - F | Gross requirements | 0 | 200 | 0 | 0 | 0 | 0 | |
OH = 20 | Scheduled receipts | 0 | 30 | 0 | 0 | 0 | 0 | |
LT = 1 | Projected on-hand | 20 | 20 | 0 | 0 | 0 | 0 | 0 |
SS = 0 | Net requirements | 0 | 150 | 0 | 0 | 0 | 0 | |
Q = L4L | Planned order receipts | 0 | 150 | 0 | 0 | 0 | 0 | |
Planned order releases | 150 | 0 | 0 | 0 | 0 | 0 |
F should be released at the start of week 1
QUESTION 16 The following is a list of components required to produce one unit of end...
Eighty units of end item X are needed at the beginning of week 6, and another 30 units are needed at the beginning of week 8 B(2) D(3) D(2) F(2) Prepare a material requirements plan for component D. D can only be ordered in whole cases (50 units per case). One case of D is automatically received every other week, beginning in week 1 (i.e., weeks 1, 3, 5, 7). Also, there are 30 units of B and 20 units...
Problem 12-18 Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the start of week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are in production and will be completed by the start of week 2. (Leave no cells...
One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time...
One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...
One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of...
One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. End H Item LT (W) Amount on hand 1 B 3 10 с 4 9 D 4 25 E 2 11 F 1 26 G 2 7 1 0 o End Item B12) с D (3) E (2) F (3) G 21 E (2) H14) E (2) a. If 24 units of the end item are to be assembled, how many additional...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand L12), c(1),x(3) B(2), 33) G(2), 8(2) H(4), B(2) 13 16 21 29 a. f 43 unts of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan) Additional units b. An order for the end item is scheduled to be shipped at the start of week...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...