Question

A methods and measurements analyst for Timepiece, Inc., needs to develop a time standard for the...

A methods and measurements analyst for Timepiece, Inc., needs to develop a time standard for the task of attaching a watch to a wristband. In a preliminary study, he observed one of his workers perform this task five times, with the following results:

Observation 1 2 3 4 5
Time (secs) 27 19 27 25 21

What is the standard time for this task if the employee worked at a 15 percent faster pace than average, and an allowance of 23 percent of job time is used?

(Keep two decimal places in your answer)

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
A methods and measurements analyst for Timepiece, Inc., needs to develop a time standard for the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT