8500
In order to produce one A, the number of C required is 2
Therefore, in order to produce 500 A, the number of C required is 2*500
= 1000
In order to produce one A, the number of B required is 3
Therefore, in order to produce 500 A, the number of B required is 3*500
= 1500
In order to produce one B, the number of C required is 5
Therefore, in order to produce 1500 B, the number of C required is 5*1500
= 7500
Total C required = 1000+7500
= 8500
In an MRP problem, A is an MPS item. Every A requires 3 B's and 2...
Extra Credit MRP Exercise (15 Points) Given: Indented Bill of Material Master Production Schedule (MPS) and Material Requirements Planning (MRP) Tables Bill of Material (QPA) A =Finished Good LT=1 B (1 LT-3 C(2) LT=2 D(1) LT 2 LT-2 F (2) LT-2 G (1) LT=1 Answer the following questions: 1). Fill in MPS/MRP tables provided 2). For Part Number B: What is the first period in which there is a net requirement ?:_AND, What is the net requirement Quantity (in the...
MRP /ERP IN M 1) Each E subassembly is made up of two (2) G parts, four (5) H part, and One J part Draw the product structure tree diagram. the information provided below, complete the following MRP Record Transaction Processing for Part E and Part G only if the following information is provided (Do not order more quantity of any resources that is needed to maintain the production) sing the product structure free diagram and Subassembly Part Part Part...
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) 1 0 34 WEEK NUMBER 2 3 4 47 ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 5 71 - 4 Item J LT = 1 Q = L4L Period Gross...
Fill in the blanks In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER 0 4 50 5 70 75 40 ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 75 50 70 Period Gross requirements Item J Scheduled receipts...
12. (25 points) Complete the MRP calculations for the simple product shown below. Numbers next to each item identify the usage rates. For example, the usage rate for item A is 2. A2 C3 C2 B1 Item X L4L On Hand 80 Lead Time 4 70 120 85 50 70 100 Gross Requirements Scheduled Receipts On Hand Net Requirements) Planned Order Receipt Planned Order Release Styles Paragraph tem A 150 FOQ+ 30 On Hand Lead Time 8 5 2 Gross...
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 73 55 74 On hand 43 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J LT = 1...
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 75 50 70 On hand 40 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J OH = 40...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...
Problem 14-5 To simplify data handling to include the receipt of orders that have actually been placed in previous periods, the following six-level scheme can be used. (A number of different techniques are used in practice, but the important issue is to keep track of what is on hand, what is expected to arrive, what is needed, and what size orders should be placed.) One unit of A is made of three units of B, one unit of C, and...
Product structure: Data: M(5) On Hand MPS Schedukid Receipts 150, week 3 Lot Size/ Order Policy FOO 800 90 | 1 740. week 5: FOQ - Fixed order quantity. "C" signifies usage. Using the data given, answ parts A and B. START by COPYING the rest of the QUESTION (from "A" to "Zzz. into the answer space. A. For Item L. fill out gross requirements, schedule receipts, projected on hand, net requirements and planned orders. Items left blank are assumed...