Question

the maker of the world famous chocolate chip cookies needs to design a product layout for...

the maker of the world famous chocolate chip cookies needs to design a product layout for a new product, mint chocolate chip. the company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. the following table describes the tasks involved in the production of a mint chocolate chip cookie.

Task Predecessor Time (seconds)
U ----- 4
V U 14
W V 12
X V 10
Y W 6
Z X,Y 8

1. Draw a predence diagram for the tasks listed above.

2. Without considering projected demands, what is the minimum possible cycle time for this production line?

3. For output to equal projected demand, what should be the actual cycle time for this production line?

4. For output equal projected demand, what is the minimum number of workstatsions needed?

5. For output to equal projected demand, what will be the effciency of the production line that uses the minimum number of workstations?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.

2 16

2.


Minimum cycle time = time taken by longest task = 14 seconds

3.Actual cycle time = Time available for production/ desired output = (8*3600)/1440 = 20 seconds

4.

Minimum number of machine = Time required to produce desired output/Time available for production

= (1440*54)/(8*3600) [ Sum of all task times = 55]

= 2.7

= 3(Rounded to nearest whole number)

Add a comment
Know the answer?
Add Answer to:
the maker of the world famous chocolate chip cookies needs to design a product layout for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • the maker of the world famous chocolate chip cookies needs to design a product layout for a new product, mint chocolate chip. the company plans to use this new production line eight hours a day in ord...

    the maker of the world famous chocolate chip cookies needs to design a product layout for a new product, mint chocolate chip. the company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. the following table describes the tasks involved in the production of a mint chocolate chip cookie. Task Predecessor Time (seconds) U ----- 4 V U 14 W V 12 X V 10 Y W...

  • Answer questions 32-37, they are all oart of the same question Theres no more information provided,what...

    Answer questions 32-37, they are all oart of the same question Theres no more information provided,what are you asking for? Questions 32 to 37 refer to the following: The maker of the world-famous Chocolate Chip Cookies needs to design a product layout for a new product, Mint Chocolate Chip. The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. The following table describes the tasks involved...

  • An unnamed company is designing a product layout for a new product. It plans to use...

    An unnamed company is designing a product layout for a new product. It plans to use this production line to meet projected demand of 320 units per 7.00 hour day, and the tasks necessary to produce this product are as follows... Task Time (sec) Predecessor u 30 none v 33 u w 4 v x 17 u, v y 51 x z 23 v, y If the company wants the output rate to be equal to demand, what is the...

  • A bakery works out a demand function for its chocolate chip cookies and finds it to...

    A bakery works out a demand function for its chocolate chip cookies and finds it to be q equals Upper D left parenthesis x right parenthesis equals 567 minus 22 xq=D(x)=567−22x​, where qq is the quantity of cookies sold when the price per​cookie, in​ cents, is xx. Use this information to answer parts ​a) through ​f). A bakery works out a demand function for its chocolate chip cookies and finds it to be q=Dx) = 567-22x, where is the quantity...

  • Mr. Meadows Cookie Company (MCC) makes a variety of chocolate chip cookies in a certain plant....

    Mr. Meadows Cookie Company (MCC) makes a variety of chocolate chip cookies in a certain plant. Based on orders received and forecasts of buying habits, it is estimated that the demand for the next four months is 850, 1260, 510, and 980, expressed in thousands of cookies. During a 46-day period when there were 120 workers, the company produced 1.7 million cookies. Assume that the number of workdays over the four months is respectively 26, 24, 20, and 16. There...

  • QUESTION 37 A company is designing a product layout for a new product. It plans to...

    QUESTION 37 A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet a schedule of 400 units per day. The tasks necessary to produce this product are detailed in the table below. Task Predecessor Time (seconds) 50 А B А 20 С А 26 D 40 B, C C E 30 a. Draw the network described in the table. b. What is the required...

  • A company is designing a product layout for a new product. It plans to use this...

    A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet a schedule of 400 units per day. The tasks necessary to produce this product are detailed in the table below. a. Draw the network described in the table. b. What is the required cycle time (in seconds) in order to meet the schedule? c. What is the theoretical minimum number of workstations needed to...

  • QUESTION 6 An industrial food processor needs to design a product layout for a new line...

    QUESTION 6 An industrial food processor needs to design a product layout for a new line of frozen pizza. The company plans to use this new production line ten hours a day in order to meet projected demand of 1,000 pizzas per day. The following table describes the tasks involved in the production of a frozen pizza. Task Immediate Predecessors Task Duration (Seconds) none 10 B C,D F E Design this layout using the decision rule of Longest Processing Time...

  • Step 1. determine output rate of final item Step 2. Determine cycle time Step 3. determine...

    Step 1. determine output rate of final item Step 2. Determine cycle time Step 3. determine macimum output Step 4. compute the theoretical minimum number step 5. assign tasks Step 6. compute efficiency and balance delay 3) The XYX company need to line balance the new production line for their snap together tablet. The production line will run seven hours a day in order to meet projected demand of 500 units per day. The following table describes the tasks involved...

  • Francis Johnson's plant needs to design an efficient assembly line to make a new product. The...

    Francis Johnson's plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 12 units per hour, and there is room for only five workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task. TASK TIME IMMEDIATE TASK (MINUTES) PREDECESSOR 2.5 2.0 2.0 3.0 3.0 3.0 3.0 A,B, C b....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT