Problem 17-12 A project manager has compiled a list of major activties that will be required...
A project manager has compiled a list of major activities that
will be required to install a computer information system in her
firm. The list includes estimated completion times for activities
and precedence relationships. (Use Table B1 and Table B2.)
(table B1)
(table b2)
Immediate
Predecessor
Estimated Times (weeks)
A
—
2-4-6
D
A
6-8-10
E
D
7-9-12
H
E
2-3-5
F
A
3-4-8
G
F
5-7-9
B
—
2-2-3
I
B
2-3-6
J
I
3-4-5
K
J
4-5-8
C...
A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships. (Z-Table is needed) Activity Immediate Predecessor Estimated Times (weeks) A — 2-4-6 D A 6-8-10 E D 7-9-12 H E 2-3-5 F A 3-4-8 G F 5-7-9 B — 2-2-3 I B 2-3-6 J I 3-4-5 K J 4-5-8 C — 5-8-12 M C 1-1-1 N...
A project manager discovers that his team has neglected to
complete the network diagram for the project. the network diagram
is shown below. however the project manager has some information
available, specifically that each activity a-g, has a different
duration between one and seven weeks. also the slack time for each
of the activity is known as shown belowDuration (weeks): 1,2,3,4,5,6,7 Slack time (weeks): 0,0,0,1,1,3,7 A D E G B FINISH START C F Using the clues provided below, determine...
Question 13 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 B 3 с 2 D A,B 5 E CD F D 4 G E 2 1 Determine the duration of the project. a. 13 weeks b. 12 weeks OC. 11 weeks d. 10 weeks e. 9 weeks Question 14 Assume that activity F has the following times: Early start time (ES) =...
A senior manager has finished reviewing the latest draft of an upcoming project. the following table provides information about the project including the normal time for each activity, activity sequence and information about costs to shorten some of the activities and therefore the project duration. As he prepares ro review rhe proposal with the owners he is concerned about the project duration and expects the owners will want the project shortened. Activity Precedes Normal Time. (week) Crashing Costs ($000) 1st...
A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...
can you explain how to fo the mean variance wnd z score and st
dev each path
Problem 17-11 The following precedence diagram reflects three time estimates for each activity. Determine: Use Table B1 and Table B2. 9-10-12 5-7-10 8-10-14 11-12-13 11 14-18-26 8-8-8 5-6-7 6-6-6 2 13-13-13 10.5-13-15.5 10 10-12-14 10-11-12 7-10-12 a. The expected completion time for each path and its variance. (Round intermediate calculations to 4 answers to 2 decimal places.) Path 1-2-3-8-11 1-2-4-6-11 1-2-4-7-11 1-2-5-9-10-11 Mean...
6. A project has been defined to contain the following list of activities, along with their precedence relations and time and cost estimates for the activity durations. Time estimates (weeks L Cost estimates ($) Activity Predecessor(s) Normal time Crashed time Normal cost Crashed cost 10 9 $6000 $8000 - 85 $1100 $2000 A 7 5 $3000 $3800 B 12 4 $4000 $6000 B 4 2 $5000 $6500 AD 6 3 $2500 $4000 CE $2800 $$3000 a. Draw the Activity-on-node (AON)...
Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 6 0.29 7 0.38 8 0.27 9 0.06 B 3 0.21 5 0.53 7 0.26 C 6 0.06 8 0.26 10 0.37 12 0.22 14 0.09 D 11 0.63 13 0.37 Provide the base-case, worst-case, and best-case calculations for the...
MGMT335 HW3 (2) Compatibility Mode Mailings Review View Help Tell me what you want to do MGMT 335 HW#3 Please solve the folloving problems related to Chapter 17: Project Management 1. Based on the following AOA diagram, please answer the following question: (1) Determine the cntical path and the expected project duration (2) Determine the following quantities for each activity: the earliest start time, the latest start time, the earliest finish time and the latest finish time and the slack...