Question

Problem 17-12 A project manager has compiled a list of major activties that will be required to nstall a computer Information system in her firm. The st Includes estimated completion times for activties and precedence relationships. Use Table B1 and Table B2. Immediate Est mated Times 6-8-10 7-9-12 2-3-5 3-4-8 2-2-3 2-3-6 3-4-5 4-5-8 S-8-12 H. G, K, O If the project is tinished within 26 weeks of its start, the project manager will recelve a bonus of S1,000; and if the project is finished within 27 weeks of Its start, the bonus will be $500. Find the probabilty of each bonus. (Round path means and path standard deviations to 2 decimal places. Round probabilities to 4 decimal places. Do not round any other intermediate calculations.) Path Std. Dev. 51,000) s500)

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Problem 17-12 A project manager has compiled a list of major activties that will be required...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A project manager has compiled a list of major activities that will be required to install...

    A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships. (Use Table B1 and Table B2.) (table B1) (table b2) Immediate Predecessor Estimated Times (weeks) A — 2-4-6                    D A 6-8-10                    E D 7-9-12                    H E 2-3-5                    F A 3-4-8                    G F 5-7-9                    B — 2-2-3                    I B 2-3-6                    J I 3-4-5                    K J 4-5-8                    C...

  • A project manager has compiled a list of major activities that will be required to install...

    A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships. (Z-Table is needed) Activity Immediate Predecessor Estimated Times (weeks) A — 2-4-6 D A 6-8-10 E D 7-9-12 H E 2-3-5 F A 3-4-8 G F 5-7-9 B — 2-2-3 I B 2-3-6 J I 3-4-5 K J 4-5-8 C — 5-8-12 M C 1-1-1 N...

  • A project manager discovers that his team has neglected tocomplete the network diagram for the...

    A project manager discovers that his team has neglected to complete the network diagram for the project. the network diagram is shown below. however the project manager has some information available, specifically that each activity a-g, has a different duration between one and seven weeks. also the slack time for each of the activity is known as shown belowDuration (weeks): 1,2,3,4,5,6,7 Slack time (weeks): 0,0,0,1,1,3,7 A D E G B FINISH START C F Using the clues provided below, determine...

  • Question 13 The following table provides a list of activities in a project, along with their...

    Question 13 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 B 3 с 2 D A,B 5 E CD F D 4 G E 2 1 Determine the duration of the project. a. 13 weeks b. 12 weeks OC. 11 weeks d. 10 weeks e. 9 weeks Question 14 Assume that activity F has the following times: Early start time (ES) =...

  • A senior manager has finished reviewing the latest draft of an upcoming project. the following table...

    A senior manager has finished reviewing the latest draft of an upcoming project. the following table provides information about the project including the normal time for each activity, activity sequence and information about costs to shorten some of the activities and therefore the project duration. As he prepares ro review rhe proposal with the owners he is concerned about the project duration and expects the owners will want the project shortened. Activity Precedes Normal Time. (week) Crashing Costs ($000) 1st...

  • A Question 11 The following table provides a list of activities in a project, along with...

    A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...

  • can you explain how to fo the mean variance wnd z score and st dev each...

    can you explain how to fo the mean variance wnd z score and st dev each path Problem 17-11 The following precedence diagram reflects three time estimates for each activity. Determine: Use Table B1 and Table B2. 9-10-12 5-7-10 8-10-14 11-12-13 11 14-18-26 8-8-8 5-6-7 6-6-6 2 13-13-13 10.5-13-15.5 10 10-12-14 10-11-12 7-10-12 a. The expected completion time for each path and its variance. (Round intermediate calculations to 4 answers to 2 decimal places.) Path 1-2-3-8-11 1-2-4-6-11 1-2-4-7-11 1-2-5-9-10-11 Mean...

  • 6. A project has been defined to contain the following list of activities, along with their...

    6. A project has been defined to contain the following list of activities, along with their precedence relations and time and cost estimates for the activity durations. Time estimates (weeks L Cost estimates ($) Activity Predecessor(s) Normal time Crashed time Normal cost Crashed cost 10 9 $6000 $8000 - 85 $1100 $2000 A 7 5 $3000 $3800 B 12 4 $4000 $6000 B 4 2 $5000 $6500 AD 6 3 $2500 $4000 CE $2800 $$3000 a. Draw the Activity-on-node (AON)...

  • Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be...

    Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 6 0.29 7 0.38 8 0.27 9 0.06 B 3 0.21 5 0.53 7 0.26 C 6 0.06 8 0.26 10 0.37 12 0.22 14 0.09 D 11 0.63 13 0.37 Provide the base-case, worst-case, and best-case calculations for the...

  • MGMT335 HW3 (2) Compatibility Mode Mailings Review View Help Tell me what you want to do...

    MGMT335 HW3 (2) Compatibility Mode Mailings Review View Help Tell me what you want to do MGMT 335 HW#3 Please solve the folloving problems related to Chapter 17: Project Management 1. Based on the following AOA diagram, please answer the following question: (1) Determine the cntical path and the expected project duration (2) Determine the following quantities for each activity: the earliest start time, the latest start time, the earliest finish time and the latest finish time and the slack...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT